Application Review Schedule for the Combined License Application for Fermi, Unit 3
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Detroit Edison Company submitted to obtain a combined license (COL) for an Economic Simplified Boiling Water Reactor (ESBWR) designated as Fermi, Unit 3.
Key Milestones |
Completion Date
Actual - A
Target - T |
Application Tendered |
09/18/08 - A |
Acceptance Review |
Acceptance Review Start
|
09/18/08 - A |
Docketing Decision Letter Issued/Acceptance Review Complete
|
11/25/08 - A |
Review Schedule Established/Schedule Letter Issued to Applicant
|
06/30/09 - A |
Safety Review |
Phase 1 - Requests for Additional Information (RAIs) and Supplemental RAIs
|
08/20/10 - A |
Phase 2 - Advanced Final Safety Evaluation Report (SER) without Open Items
|
07/14 - A |
Phase 3 - ACRS Review of SER without Open Items
|
09/14 - A |
Phase 4 - Final SER
|
11/14 - A |
Environmental Review |
Phase 1 - Environmental Impact Statement (EIS) Scoping Summary Report Issued
|
07/02/09 - A |
Phase 2 - EPA Issues Federal Register Notice of Filing for Draft EIS/Draft EIS Complete
|
10/11 - A |
Phase 3 - Federal Register Notice of Availability of the FEIS Published/Final EIS Complete
|
01/13 - A |
Hearing |
Commission or ASLB hold mandatory hearing
|
02/04/15 - A |
License |
Commission decision on issuance of COL application
|
04/30/15 - A |
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.