General Electric Co. – Vallecitos Boiling Water Reactor (VBWR)
1.0 Site Identification
Type of Site: |
Power Reactor |
Location: |
Sunol, CA |
License No.: |
DPR-1 |
Docket No.: |
50-18 |
License Status: |
DECON |
Project Manager: |
Jack Parrott |
2.0 Site Status Summary
The VBWR was shutdown in 1963 and NRC issued a possession-only license in 1965. The license was renewed in 1973 and has remained effective under the provisions of 10 CFR 50.51(b). The facility has been maintained in SAFSTOR condition. The licensee submitted a Limited Post Shutdown Decommissioning Activities Report in 2022 that describes a change to active decommissioning (DECON) of the VBWR. A license termination plan is scheduled to be submitted to NRC in September 2023. The spent fuel has been removed from the site.
3.0 Major Technical or Regulatory Issues
In 2015, the licensee, GE Hitachi (GEH), began a licensing process to exempt the VBWR from the 60-year decommissioning schedule limit of 10 CFR 50.82(a)(3). The exemption request was disapproved by the Commission on August 6, 2021. GEH subsequently withdrew the exemption request by letter dated August 25, 2021. The licensee has begun active decommissioning of the VBWR and plans to terminate the license by 2025.
4.0 Estimated Date For Closure
Calendar year 2025