Crystal River Unit 3 Nuclear Generating Plant
1.0 Site Identification
Type of Site: |
Power Reactor Facility |
Location: |
Crystal River, FL |
License No.: |
DPR-72 |
Docket No.: |
50-302 |
License Status: |
DECON |
Project Manager: |
Chris Allen |
2.0 Site Status Summary
Crystal River Unit 3 Nuclear Generating Plant (CR-3) was a 2,609 Mwt, pressurized water reactor that was licensed to operate from December of 1976 to February 20, 2013. During a refueling outage that started on September 26, 2009, CR-3 replaced the steam generators (SG), requiring a large hole to be made in the containment structure. When attempting to restore the containment structure following the SG replacement, damage to the containment structure was observed. The licensee attempted to repair the damage, but later decided to decommission the reactor.
The licensee submitted a SAFSTOR post-shutdown decommissioning activities report (PSDAR), including the site-specific cost estimate, on December 2, 2013. The plant began construction of an ISFSI in 2016, and begin loading fuel in summer 2017. Fuel transfer to the ISFSI was completed in January 2018. On October 1, 2020, Duke Energy Florida transferred the license for Crystal River Unit 3, to Accelerated Decommissioning Partners (ADP). ADP is a joint venture between NorthStar Group Services and Orano USA. Per the agreement, Duke remains the NRC-licensed owner of the plant, property, and decommissioning trust fund but not the spent fuel. ADP-CR3 became the NRC-licensed operator responsible for decommissioning and ADP-SF1 became the owner of the spent nuclear fuel. A revised PSDAR reflecting the changes from SAFSTOR to DECON was submitted on June 26, 2019.
On December 12, 2022, ADP-CR3 submitted a license amendment request (LAR) to add a license condition to include the requirements of a License Termination Plan (LTP) for CR-3. The NRC staff accepted the LAR on July 25, 2023. On August 12, 2024, ADP-CR3 withdrew its request citing the need for additional detail. The NRC staff acknowledged the request by letter dated August 27, 2024.
3.0 Major Technical or Regulatory Issues
No known issues exist at this time.
4.0 Estimated Date for Closure
Calendar year 2037
Page Last Reviewed/Updated Thursday, August 29, 2024