Information Notice No. 91-81: Switchyard Problems that Contribute to Loss of Offsite Power
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555
December 16, 1991
NRC INFORMATION NOTICE 91-81: SWITCHYARD PROBLEMS THAT CONTRIBUTE TO
LOSS OF OFFSITE POWER
Addressees
All holders of operating licenses or construction permits for nuclear power
reactors.
Purpose
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information
notice to alert addressees to several problems associated with plant
switchyards. It is expected that recipients will review the information for
applicability to their facilities and consider actions, as appropriate, to
avoid similar problems. However, suggestions contained in this information
notice are not NRC requirements; therefore, no specific action or written
response is required.
Description of Circumstances
On April 23, 1991, a complete loss of offsite power occurred at the Vermont
Yankee Nuclear Power Station as a result of maintenance activities in the
switchyard. Maintenance workers were installing a new battery for one of
the two non-1E 125 VDC buses. The two normally independent buses were cross
tied through the swing battery charger 4A-5A after defeating a mechanical
interlock (Figure 1). Furthermore, the licensee was paralleling the battery
chargers on bus DC-4A without a battery on this bus. When the 4A-5A battery
charger output breaker feeding bus DC-5A was opened prior to connection of
the new battery 4A to bus DC-4A, a voltage transient propagated through the
switchyard DC control system that caused all but one of the 345kV and 115kV
circuit breakers to trip and lock open. The loss of offsite power which
occurred caused a main turbine and automatic reactor trip. Restoration of
full offsite power took thirteen hours.
The NRC dispatched an augmented inspection team (AIT) to investigate this
event, and the following generic concerns were identified by the team in its
report (50-217/91-13): (1) a lack of preventive maintenance on battery
chargers, (2) presence of sensitive components in logic cards making them
susceptible to failure, (3) switchyard protective relays that were
susceptible to a single failure, and (4) a lack of clear authority over the
switchyard during emergency conditions.
9112110011
.
IN 91-81
December 16, 1991
Page 2 of 3
Lack of Preventive Maintenance
Three of the four non-1E battery chargers (4A, B, and 4A-5A) in the
switchyard DC control system were in a degraded condition at the time of the
event. In each of the degraded battery chargers, manufactured by Exide, the
output filter circuit was not functional. The problems included blown fuses
in one filter circuit, blown and wrong-sized fuses in another, and a failed
capacitor in the third filter circuit. If the 4A-5A battery charger output
filter circuit had been functional, the effect of the voltage transient may
have been mitigated and loss of offsite power might have been prevented.
The problems resulted directly from infrequent preventive maintenance on the
battery chargers. The licensee had no regular maintenance program for the
chargers and it appeared that the last maintenance was performed in 1985.
These battery chargers are not safety related and no surveillance testing or
preventive maintenance is required. However, at this facility, the
switchyard battery system, including the switchyard batteries, their
associated chargers, and associated distribution panels, is part of the
auxiliary electrical power system and is required to be operable by the
plant's Technical Specifications.
Sensitive Components in Logic Cards
The voltage spike in the switchyard DC control system destroyed zener diodes
in the stuck breaker failure units (SBFUs) of two switchyard circuit
breakers which led to a chain reaction that caused most of the breakers in
the 345kV and 115kV switchyard to trip and lock open. These SBFUs are
manufactured by ASEA Brown Boveri, and previous models were made by the
Westinghouse Electric Corporation. The manufacturer has developed new units
that are not as susceptible to voltage spikes because the new units do not
contain zener diodes.
Protective Relays Subject to a Single Failure
All of the SBFU relays are powered from a single bus (DC-4A) even though two
DC buses are available in the switchyard DC control system. This design is
subject to a single failure. Other facilities may have similar protective
relaying designs that could be vulnerable to a common cause failure.
Authority Over the Switchyard Under Emergency Conditions
The restoration of offsite power was delayed because of a lack of
communications between plant staff and the transmission and distribution
(T&D) personnel. Under normal conditions, T&D is responsible for operating
the switchyard. The licensee's procedure specifies that, under emergency
conditions, the responsibility is transferred to the plant staff. However,
the procedure does not define "emergency." These operational problems
suggest the need to clarify switchyard authority during a loss of offsite
power or other emergency conditions when timely switchyard activities are
important.
Additional Example of Switchyard Communication Problems
Another example of communication problems in the switchyard can be seen in
an event that took place at the McGuire Nuclear Generating Station, Unit 1,
on February 11, 1991. The unit tripped from 100% power when T&D personnel
caused
.
IN 91-81
December 16, 1991
Page 3 of 3
a loss of all offsite power while testing a modification to the protective
relay circuitry in the 230 kV switchyard. Since the majority of the
switchyard is outside of the plant equipment boundary, the T&D personnel did
not notify the station operations personnel that work was in progress even
though switch-yard activities can impact the station. Prior to this event
there was no agreement between station operations and T&D personnel on how
to handle switch-yard activities outside the plant equipment boundary.
Subsequent to this event, a work control policy was established to provide
improved communication between the station operations personnel and T&D
personnel.
No specific action or written response is required by this information
notice. If you have any questions about this matter, please contact one of
the technical contacts listed below or the appropriate Office of Nuclear
Reactor Regulation (NRR) project manager.
Charles E. Rossi, Director
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical contacts: Cliff Anderson, Region I
(215) 337-5376
Peter Kang, NRR
(301) 504-0779
David Skeen, NRR
(301) 504-1174
Attachments:
1. Figure 1: Switchyard House DC Distribution
One Line Diagram
2. List of Recently Issued NRC Information Notices
.
Page Last Reviewed/Updated Wednesday, March 24, 2021