Information Notice No. 91-29: Deficiencies Identified During Electrical Distribution System Functional Inspections
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555
April 15, 1991
Information Notice No. 91-29: DEFICIENCIES IDENTIFIED DURING ELECTRICAL
DISTRIBUTION SYSTEM FUNCTIONAL
INSPECTIONS
Addressees:
All holders of operating licenses or construction permits for nuclear power
reactors.
Purpose:
This information notice is intended to alert addressees to deficiencies
identified during recently performed electrical distribution system
functional inspections (EDSFIs). It is expected that recipients will review
the information for applicability to their facilities and consider actions,
as appropriate, to avoid similar problems. However, suggestions contained
in this information notice do not constitute NRC requirements; therefore, no
specific action or written response is required.
Description of Circumstances:
During multidisciplinary inspections, the U.S. Nuclear Regulatory Commission
(NRC) has identified many deficiencies related to the electrical
distribution system. To address these deficiencies, the NRC has developed
an inspection to specifically evaluate the electrical distribution system.
During the last year, the NRC completed eight EDSFIs, performing at least
one in each of the five NRC geographical regions. During these inspections,
the staff found several common deficiencies in the licensees' programs and
in the electrical distribution systems as designed and configured at each
plant. These deficiencies included inadequate ac voltages at the 480 Vac
and 120 Vac distribution levels, inadequate procedures to test circuit
breakers, and inadequate determinations and evaluations of setpoints.
Discussion:
Inadequate Voltage
During inspections conducted at the San Onofre Nuclear Generating Station
(Inspection Reports 50-361/89-200 and 50-362/89-200), the Susquehanna Steam
Electric Station (Inspection Reports 50-387/90-200 and 50-388/90-200), and
the
9104090124
.
IN 91-29
April 15, 1991
Page 2 of 4
Waterford Steam Electric Station (Inspection Report 50-382/90-23), the staff
found that, under certain conditions, the voltage available at the safety
buses would be inadequate to operate safety-related loads and associated
equipment. These conditions could occur when the plant's electrical
distribution systems were being supplied from an offsite grid that had
become degraded but that continued to supply voltages that remained above
the setpoints at which the degraded grid relays would be activated.
At San Onofre, the numerous voltage drops throughout the system could cause
the voltage to 120 Vac contactors to drop below the voltage range for which
these contactors were certified as acceptable by their manufacturers. To
resolve this problem the licensee has performed testing that established a
lower acceptable voltage range for this equipment.
At Susquehanna, the degraded grid relay setpoint was set at 84 percent on
the 4160 Vac buses. This setpoint could have allowed inadequate voltage to
be delivered to numerous safety-related loads at both the 480 Vac and
120 Vac levels. The licensee calculated that setpoints of at least
93 percent would be required to ensure adequate voltage to all
safety-related equipment. To resolve this problem, the licensee has raised
the setpoints of the degraded grid relays and has initiated a modification
to install 120 Vac regulating transformers.
At the Waterford nuclear plant, the degraded grid relays were set at
87.5 percent as sensed on the 4160 Vac buses. Although this setting was
found to be marginally adequate for equipment connected to the 4160 Vac
buses, the setting was too low to ensure that adequate voltage would be
maintained at the 480 Vac and 120 Vac levels. The licensee is evaluating
solutions to this problem and has instituted a procedure to manually
separate from the grid if the voltage falls to unacceptable levels but
remains above the relay setpoints.
The function of the degraded grid relays is to ensure that adequate voltage
is available to operate all Class 1E loads at all distribution levels. In
order to ensure that all required Class 1E loads will remain operable during
degraded voltage conditions, some licensees are currently reanalyzing the
basis for the degraded grid relay setpoints. The new analyses consider all
required Class 1E loads and include the assumption that the voltage on the
buses being sensed by these relays can remain at a level just above the
relay setpoints.
Inadequate Circuit Breaker Testing Procedures
During recent EDSFIs and previously on other NRC inspections, the staff
identified repetitive deficiencies in licensees' programs to test circuit
breakers. These deficiencies included inadequate procedures, inadequate
test acceptance criteria, inadequate test equipment, and inadequate control
of testing. At the Susquehanna plant (Inspection Reports 50-387/90-200 and
50-388/90-200), the staff found that the licensee was testing dc molded case
circuit breakers with a procedure written for testing ac breakers. The
licensee had not established specific acceptance criteria for the dc
breakers.
.
IN 91-29
April 15, 1991
Page 3 of 4
At the Shearon Harris Nuclear Power Plant (Inspection Report 50-400/90-200),
the staff identified that the licensee was testing molded case circuit
breakers against National Electrical Manufacturers Association (NEMA)
acceptance criteria, which were less stringent than the manufacturer's
time-current curves for these breakers. In addition, the staff identified
that the licensee was testing 480 V air circuit breakers with test equipment
that applied a test signal (secondary injection) to the solid state trip
units in the circuit breakers. Although this method adequately verified
that the trip units functioned properly, it did not verify that the
breaker's current transformer functioned properly or that the wiring and
connectors were adequate between the current transformer and the solid state
trip units. Other licensees have performed testing by primary current
injection or by individually checking each component of the circuit breaker,
including the wiring and connectors to demonstrate that the circuit breaker
functions properly.
Inadequate Determinations and Evaluations of Setpoints
Many of the findings identified during recent EDSFIs were related to
inadequate setpoint determinations. Useful guidance for determining
setpoints is provided by Instrument Society of America Standard 67.04-1982,
"Setpoints for Nuclear Safety-Related Instrumentation used in Nuclear Power
Plants," which the NRC staff has endorsed by Regulatory Guide 1.105 Revision
2 - 1986, "Instrument Setpoints for Safety-Related Systems." This guidance
applies both to process instrumentation and, in part, to certain relays that
perform a safety function.
Some licensees have operated equipment outside of acceptable limits because
they did not determine proper setpoints and did not evaluate and account for
instrument drift. Operating the equipment under these conditions could
compromise the safety functions of the equipment. The staff has identified
these circumstances primarily for those instruments in which the licensee
has determined the setpoints as opposed to those instruments for which the
setpoints were determined by the architect/engineer or the nuclear safety
system supplier. Those setpoints not contained in the plant technical
specifi-cations were also more frequently found to be deficient. During
recent EDSFIs, the staff identified deficiencies in setpoints for diesel day
tank level indicators, diesel air start compressor controllers and alarms,
inverter low voltage shutdown circuitry, degraded grid relays, and diesel
overcurrent relays.
In addition to identifying deficiencies in the setpoints themselves, the NRC
has determined that not all the licensees are typically verifying that the
magnitude of instrument drift that was assumed in the original setpoint
calculation coincides with the magnitude of drift observed in the plant.
Some licensees have corrected this deficiency by verifying the magnitude of
instrument drift by trending, (comparing "as found" calibration data to
previous "as left" data). This is particularly important for the degraded
grid relay setpoints, which often require very tight calibration tolerance
bands, and for which very low drift values are often assumed.
.
IN 91-29
April 15, 1991
Page 4 of 4
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
the technical contact listed below or the appropriate NRR project manager.
Charles E. Rossi, Director
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical Contact: Jeffrey B. Jacobson, NRR
(301) 492-0996
Attachment: List of Recently Issued NRC Information Notices
.
Page Last Reviewed/Updated Thursday, March 25, 2021