Information Notice No. 83-55: Misapplication of Valves by Throttling Beyond Design Range
SSINS No.: 6835
IN 83-55
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
WASHINGTON, D.C. 20555
August 22, 1983
Information Notice No. 83-55: MISAPPLICATION OF VALVES BY THROTTLING
BEYOND DESIGN RANGE
Addressees:
All nuclear power facilities holding an operating license (OL) or a
construction permit (CP).
Purpose:
This information notice is provided to alert licensees to a potentially
generic problem regarding the throttling of valves outside the design limits
of these valves. No new requirements are imposed in this notice but
licensees should review this notice for applicability to their facilities.
Discussion:
Pressurized Water Reactors
Based on analysis of the Crystal River Unit 3 (CR-3) plant by Babcock and
Wilcox (B&W), Florida Power Corporation reported by letter addressed to NRC
Region II dated July 27, 1983, that throttling of the high pressure
injection (HPI) valves as described in the emergency operating procedure
guidelines for small-break LOCA could result in unacceptable valve damage.
The emergency operating procedures require the throttling of coolant flow
through the HPI valve in order to prevent overcooling and pressurized
thermal shock. The HPI valves at CR-3, manufactured by the Walworth Company,
are not designed for throttling and such activity could result in damage to
the valve from cavitation, high velocity erosion of seat, and/or excessive
vibration of valve stem and plug. Degradation of the integrity of these
valves would impose a significant safety hazard. B&W believes that CR-3 is
the only B&W plant that uses the Walworth valve as an HPI valve.
It is our understanding that Westinghouse plants do not throttle the safety
injection valves but rather vary the flow with the safety injection pumps.
However, some Combustion Engineering (CE) plants do throttle and could be
susceptible to the same problems encountered in the B&W plant.
The requirement for restricting safety injection flow was not imposed until
after most operating plants were designed and constructed. Thus, it is
possible that plants constructed before the requirements for throttling
contain valves
8308040032
.
IN 83-65
August 22, 1983
Page 2 of 3
that are not specifically designed for these purposes. Throttling of valves
not designed for throttling could also be a problem in other systems in
addition to the high pressure safety injection systems.
Boiling Water Reactors
On February 18, 1983, while in the shutdown mode of operation at Susquehanna
Station, a local operator discovered a low pressure coolant injection (LPCI)
valve in the "B" loop of the RHR system severely vibrating. Upon further
inspection the valve was found to have lost its packing, the valve position
indicator had vibrated off, and the adjacent saddle-type pipe hanger had
broken welds. At the time of the discovery, the valve was being used to
control the shutdown cooling flow to the vessel. This loop of the LPCI was
immediately declared inoperable and the "A" loop was put into service for
shutdown cooling.
On June 9, 1983, at Susquehanna Station, shift personnel noticed that the
keep fill system pressure in the RHR system was less than normal on the
upsteam side of the LPCI throttle valve. The loss of pressure indicated
possible blockage at this normally open valve. Further investigation showed
that the throttle valve disc to skirt nut tack welds were broken and the
skirt nut had separated from the valve disc. This allowed the disc to
separate from the stem block the keep fill system flow, and render the "B"
loop of LPCI inoperable. It is suspected that the skirt nut tack welds broke
as a result of high vibrational loadings during testing and normal operation
early in 1983.
Following the February 18 event it was concluded that the shutdown cooling
flow rates were outside the optimum throttling range of the LPCI throttle
valve causing severe valve vibration. The system was being operated in this
manner to afford finer control of reactor coolant temperatures. The
operating procedures were subsequently changed to operate the system
intermittently at higher flow rates. The separation of the throttle valve
disc and stem by June 9 was also attributed to severe valve vibration
experienced before the February 18 event, but it was not until June 9 that
the skirt nut had finally worked itself free.
Similar problems occurred during startup and the early operational phase at
Browns Ferry 1 (circa 1975). In order to adjust cooldown rates, the residual
heat removal (RHR) service water valves were throttled. Severe vibration
occurred which caused extensive damage to valve internals. When the RHR
24-inch angle valves were used to throttle RHR flow, these valves also
vibrated excessively and similar damage occurred. TVA consulted with the
valve manufacturer, the Walworth Company, and was advised that the disc
characteristics were improper for the throttling that was necessary for
controlling the cooldown rate. A "fluted flow-disc" was installed in each of
the angle valves and the system has provided satisfactory service since
then.
Operating personnel should be made aware of the operating characteristics of
throttle valves, and procedures should be provided to limit valve operation
outside the optimum throttling range.
.
IN 83-55
August 22, 1983
Page 3 of 3
If you have any questions regarding this matter, please contact the Regional
Administrator of the appropriate NRC Regional Office, or this office.
Edward L. Jordan Director
Division of Emergency Preparedness
and Engineering Response
Office of Inspection and Enforcement
Technical Contact: P. R. Farron, IE
492-4766
Attachment:
List of Recently Issued IE Information Notices
.
Page Last Reviewed/Updated Tuesday, March 09, 2021