Information Notice No. 81-10: Inadvertent Containment Spray Due to Personnel Error
SSINS No.: 6835
Accession No.:
8011040273
IN 81-10
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
WASHINGTON, D.C. 20555
March 25, 1981
Information Notice No. 81-10: INADVERTENT CONTAINMENT SPRAY DUE TO
PERSONNEL ERROR
Description of Circumstances:
On February 11, 1981 while in mode 5 (cold shutdown), an auxiliary unit
operator at Sequoyah Unit 1 misunderstood a verbal instruction and opened a
single valve in the residual heat removal (RHR) system. The opened valve
created direct flow path through the RHR system from the primary coolant
system to the RHR containment spray header. A rapid primary system
depressurization to the atmospheric pressure resulted, and a total of about
110,000 gallons of water was sprayed into the containment from the primary
system and from the refueling water storage tank (RWST).
Licensees and applicants should be aware of the following aspects of this
event and should take appropriate steps to prevent a recurrence a their
plant.
The auxiliary unit operator did not have adequate training or orientation at
the particular duty station involved. A single valve at that station is
part of the primary coolant system pressure boundary when using the residual
heat removal (RHR) system for shutdown cooling. Thus,
personnel/administrative problems and a plant design feature combined to
cause the event.
Design of the control room annunciators contributed to prolonging the event.
The panel indicating emergency core cooling system (ECCS) valve positions is
designed to warn when the ECCS is not properly aligned for the injection
(safety) mode. When the first valve misalignment occurs, one light comes on
in an otherwise dark field of indicators, and an alarm sounds and flashes.
However, in the shutdown cooling mode, several valves are not in their
injection mode position. Therefore, in the event at Sequoyah, the alarm
light had already been on continuously for some time, the annunciator was
not supposed to operate, and one more light coming "on" in a valve-position-
indicating field with several lights already "on" was easily missed. The
operators thus failed to detect the presence of the inadvertently opened
valve for at least 35 minutes.
Lack of an ECCS initiation procedure for use in the shutdown cooling mode
did not significantly delay recovery from this event, but potentially could
have done so had the primary system been at a higher pressure. To provide
injection flow for pressurizer level recovery, the operators opened the RHR
system suction valve from the RWST, but they neglected to close the RHR
system suction valves from the reactor coolant system (RCS). A proper
procedure would require those latter valves to be closed to prevent reactor
pressure
.
IN 81-10
March 25, 1981
Page 2 of 2
from seating a check valve in the RWST suction line, which would prevent the
injection mode for the low-pressure (RHR) pumps from being effective and
delay recovery from the event.
A similar problem with the borated water storage tank (BWST) check valve
occurred at Crystal River 3 on July 16, 1980 while the unit was in Mode 5
with the decay heat system in use for shutdown cooling. Improper valve
alignment on the decay heat system heat exchangers caused a rapid cooldown
of the RCS which resulted in a loss of pressurizer level. When recovery was
attempted by realigning the decay heat system suction to the BWST, injection
flow could not be established until RCS pressure approached atmospheric
conditions since the RCS suction valves remained open.
This problem would be particularly significant under a LOCA condition with
the RCS temperature above boiling (Mode 4).
The information herein is being provided as an early notification of a
possibly significant matter that is still under review by the NRC staff.
Recipients should review the information for possible applicability to their
facilities. If NRC evaluation so indicates, further licensee actions may be
requested.
No written response to this information notice is required. If you need
additional information regarding is matter, contact the Director of the
appropriate NRC Regional Office.
Attachment: Recently issued IE Information Notices.
Page Last Reviewed/Updated Tuesday, March 09, 2021