Information Notice No. 80-44: Actuation of ECCS in the Recirculation Mode While in Hot Shutdown
SSINS No.: 6835
Accession No.:
8012160001
IN 80-44
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
WASHINGTON, D.C. 20555
December 16, 1980
Information Notice No. 80-44: ACTUATION OF ECCS IN THE RECIRCULATION
MODE WHILE IN HOT SHUTDOWN
PURPOSE:
The intent of this Information Notice is to alert PWR licensees and holders
of construction permits of a potentially generic problem involving
inadvertent actuation of the emergency core cooling system (ECCS) in the
"Recirculation Mode". Such an event occurred at the Davis-Besse Nuclear
Power Station (Docket No. 50-346) on December 5, 1980. The plant was in a
hot shutdown mode of operation at the time of the event and was undergoing
certain maintenance activities as described below.
DISCUSSION:
Just prior to the inadvertent actuation of the ECCS, the licensee was
attempting to isolate electrical shorts and/or grounds in the Safety
Features Actuation System (SFAS). Towards this end, A-C power had been
removed from Channel 3 of the SFAS. Upon reenergizing Channel 3 it was noted
that an indicating lamp was out; therefore, an attempt was made to replace
the failed lamp with a spare unit. While removing a lamp from a spare output
slot in a Channel 3 chassis, an arc was drawn between the lamp and the
module chassis. This arcing was apparently due to a combination of shorts or
grounds in the SFAS, which coupled with the "common" connection between
Channel 1 and 3 resulted in the loss of a power supply in Channel 1. Since
all the bistable trips in Channel 3 had not been completely reset, and since
a power supply to Channel 1 was lost, SFAS Levels 1, 2, 3 and 5 were
actuated by the two-out-of four actuation logic. Since SFAS Level 5
indicates that the Borated Water Storage Tank (BWST) is at a low level, the
ECCS was placed in a recirculation mode (i.e., the ECCS suction was aligned
to the emergency containment sump.)
In order to place the ECCS system in the recirculation mode, the supply
valves leading to the Decay Heat Removal (DHR) pumps from the BWST start
closing after those in the ECCS line and from the containment emergency sump
fully open. Thus, during this valve transition period, a flow path existed
to the reactor coolant system (RCS) via the BWST and the ECCS pumping system
(i.e., the DHR pumps); however, since the RCS pressure was higher than that
of the pumping system (2100 vs. 1600 psig) no BWST water was pumped into the
RCS. Rather, during the valve transition time of about 1-1/2 minutes,
approximately 15,000 gallons of borated water was drained from the BWST to
the containment emergency sump.
.
IN 80-44
December 16, 1980
Page 2 of 2
The Davis-Besse Nuclear Power Station has experienced several events during
the past three and one-half years which have either degraded the DHR system
or caused a temporary interruption of DHR operation. Of these, the one most
closely paralleling the event described above occurred on April 19, 1980.
(See Information Notice No. 80-20, "Loss of Decay Heat Removal Operability at
Davis Besse Unit 1 While in A Refueling Mode" dated May 8, 1980 and IE
Bulletin No. 80-12, "Decay Heat Removal System Operability" dated May 9,
1980.) During the December 5, 1980 event, the plant was in a hot shutdown
mode with RCS pressure at approximately 2100 psig; therefore, the operator
was able to promptly trip the DHR pumps, thereby precluding air entrapment
in the system or pump damage. In contrast, the April 19, 1980 event occurred
while the plant was in a quasi refueling mode (i.e., the reactor head was in
place but detensioned, RCS water level was below the steam generator's
bottom plate, the RCS was vented to the atmosphere by an open manhole at the
top of the steam generator, and decay heat was being removed by one DHR
system). Since the DHR pump was being used to remove decay heat during the
April 19 event, it was left running for approximately two minutes after the
pump had been aligned to the recirculation mode of operation, and tripped
when water was discharged from a temporary tygon line. Since the DHR system
was the only system available for decay heat removal, the DHR pump was
restarted approximately forty minutes later; however, it was tripped shortly
thereafter when it was determined that there was air in the suction line of
the system. In all, the April 19, 1980 event required approximately two and
one-half hours to vent the DHR system and reestablish DHR flow. As a
consequence of the relatively long recovery time, the temperature limit
specified in the Technical Specification for the refueling mode of operation
was exceeded during the April 19, 1980 event.
The above events illustrate means whereby the integrity of a major ECCS
system can be jeopardized by inadvertently or prematurely aligning the ECCS
to the recirculation mode of operation. The major concern in such cases is
that the DHR pumps could become air bound if their suction lines are aligned
to a dry sump. At best, with the pumps air bound, the pump motor would trip
automatically or could be tripped manually before any damage occurred, in
which case flow could be established after the system is vented; at worst,
the pump could be damaged and become inoperable, in which case the active
portion of the ECCS would not be available, if needed at that time.
This Information Notice is provided as an early notification of a possibly
significant matter that is still under review by the NRC staff. Recipients
should review the information for possible applicability to their
facilities. No specific action or response is requested at this time;
however, if NRC evaluations so indicate, further licensee actions may be
requested or required.
If you have any question regarding this matter, please contact the director
of the appropriate NRC Regional Office.
Page Last Reviewed/Updated Tuesday, March 09, 2021