IE Circular 77-13, Reactor Safety Signals Negated During Testing
CR77013
September 22, 1977
MEMORANDUM FOR: B. H. Grier, Director, Region I
J. P. O'Reilly, Director, Region II
J. G. Keppler, Director, Region III
E. M. Howard, Director, Region IV
R. H. Engelken, Director, Region V
FROM: H. D. Thornburg, Director, Division of Reactor
Operations Inspection, IE
SUBJECT: IE CIRCULAR 77-13, REACTOR SAFETY SIGNALS NEGATED
DURING TESTING
The subject document is transmitted for issuance on September 22, 1977. The
Circular should be issued to all holders of Reactor Operating Licenses and
Construction Permits. Also enclosed is a draft copy of the transmittal
letter.
Harold D. Thornburg, Director
Division of Reactor Operations
Inspection
Office of Inspection and
Enforcement
Enclosures:
1. Circular 77-13
2. Draft Transmittal Letter
CONTACT: V. D Thomas, IE
49-28180
.
Transmittal letter for Circular 77-13, to each holder of an NRC Operating
License and Construction Permit.
Addressee:
The enclosed Circular 77-13, is forwarded to you for information. If there
are any questions related to your understanding of the suggested actions,
please contact this office.
Signature
(Regional Director)
Enclosure:
IE Circular 77-13
.
IE Circular 77-13
Date: September 22, 1977
Page 1 of 3
REACTOR SAFETY SIGNALS NEGATED DURING TESTING
On July 12, 1977, the Commonwealth Edison Company reported that while
conducting a surveillance test at Zion Unit 2, test signals were
simultaneously injected into several sensors which affected both protection
and control systems. Injection of these test signals resulted in: (1) the
loss of instrument indications for the affected protection and control
systems, (2) the loss of automatic control capability for the affected
control systems, and (3) the loss of automatic protection capability for the
affected protection systems.
At the time of the event, the unit was in a hot shutdown condition and
preparations for start-up were underway. Station management decided to
perform a surveillance test of the reactor protection logic circuitry. A
combination of test procedure inadequacies and the failure to follow
prescribed administrative controls related to instrumentation testing led to
the insertion of test signals which replaced the actual signals from three
pressurizer water level sensors, three water level sensors in each of the
four steam generators, four pressurizer pressure sensors and three flow
sensors in each of the primary coolant loops. The test signals had been
inserted for approximately 40 minutes when, due to unexpected indications of
the main coolant pump seal flow rate and other anomalous indications, the
operator requested that the test signals be removed. When the test signals
were removed, it was observed that the pressurizer water level had dropped
below the range of indication.
The drop in pressurizer water level resulted from the pressurizer water
level test signal being slightly higher than the automatic pressurizer level
control set point. In response to this condition the changing pump flow was
automatically reduced to the minimum pump flow rate, which was maintained
until the test signals were removed. During this forty minute period the
letdown flow remained constant. Consequently, the rate at which coolant was
being removed from the primary coolant system was approximately 75 gpm
greater than the rate at which coolant was being returned to the system.
Approximately 5300 gallons of water was required to bring the pressurizer
water level back to its original level of twenty-two percent.
.
IE Circular 77-13
Date: September 22, 1977
Page 2 of 3
As mentioned above, operator action, in response to other available
instrumention indications terminated the event. Subsequent investigation by
the licensee revealed that no damage to plant equipment was sustained during
or after the event.
This incident represents an example of an event which resulted from a series
of errors involving lax management control and improper attention of plant
personnel to established procedures.
All holders of operating licenses should be aware of the potential for
adverse operational events which can occur during performance of particular
surveillance tests. For example, if an excessive number of safety sensors
are disabled simultaneously as was the case in this event, automatic action
may not occur as intended. Care must be taken to assure that test signals do
not negate automatic initiation of protection systems. It is recommended
that the following considerations be incorporated in your reviews of this
matter.
1. Facility procedures should specifically identify the limitations and
restrictions which are required for each mode of operation during which
testing or surveillance activities may be conducted such that required
safety protection systems will remain operable in accordance with the
facility Technical Specifications.
2. In order to provide additional assurance that required safety related
capabilities of plant systems are not defeated during testing or
surveillance activities, training programs for operations and craft
personnel should include sufficient information to assure an indepth
understanding of system functions, system interactions, and Technical
Specification requirements.
3. Management controls should be strengthened as necessary to assure
adherence to administrative procedures involving reviews, approvals,
and communication between, plant supervision, operators and craft
personnel performing testing and surveillance activities. Such controls
should consider the "man-machine" interfaces, and should assure that
the human component of this pair is not overburdened.
.
IE Circular 77-13
Date: September 22, 1977
Page 3 of 3
No written response to this Circular is required. If you require additional
information regarding this matter, contact the Director of the appropriate
NRC Regional Office. IE inspectors will review this matter with licensees
during future inspections.
Enclosure:
List of IE Circulars:
Issued in 1977
Page Last Reviewed/Updated Tuesday, March 09, 2021