Bulletin 79-09: Failures of GE Type AK-2 Curcuit Breaker in Safety Related Systems
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
WASHINGTON, D.C. 20555
April 17, 1979
IE Bulletin No. 79-09
FAILURES OF GE TYPE AK-2 CURCUIT BREAKER IN SAFETY RELATED SYSTEMS
Description of Circumstances:
Twelve failures of General Electric (GE) type AK-2 (i.e., AK-2A-15, 25, 50,
75, or 100) Circuit Breakers installed in safety-related systems have been
reported since 1975. The failures occurred at the following facilities:
Date Facility System
1. 9/16/78 Arkansas-1 Control Rod Drive System
2. 9/25/78 Arkansas-1 Control Rod Drive System
3. 10/17/78 Arkansas-1 Control Rod Drive System
4. 1/22/78 Crystal River-3 Control Rod Drive System
5. 8/7/75 Oconee Unit-3 Control Rod Drive System
6. 1/18/79 Oconee Unit-3 Control Rod Drive System
7. 1/22/79 Oconee Unit-1 Control Rod Drive System
8. 1/31/79 Oconee Unit-1 Control Rod Drive System
9. 4/25/75 TMI/1 Control Rod Drive System
10. 11/26/78 Oyster Creek-1 Containment Spray Pump
11. 11/30/78 Oyster Creek-1 Service Water Pump No. 1
12. 11/30/78 Oyster Creek-1 Service Water Pump No. 2
It is significant to note that during a loss-of-off-site power test on
November 30, 1978, at Oyster Creek, both service water pump circuit breakers
failed to trip, as required. The undervoltage relays which monitor voltage
level on each emergency bus functioned properly but could not actuate the
trip mechanism via the undervoltage trip device within each circuit breaker.
These failures, in turn, created a potential overload condition on each
emergency diesel generator unit by allowing simultaneous starting of
multiple high horse power motors during sequential loading phase of the
test.
The causes for failure were attributed to either binding within the linkage
mechanism of the undervoltage (UV) trip device and trip shaft assembly or
out-of-adjustment conditions in the same linkage mechanism. Babcock and
Wilcox (B&W) and GE determined that the binding and out-of-adjustment
resulted from inadequate preventive maintenance programs
.
IE Bulletin No. 79-09 April 17, 1979
Page 2 of 3
at the affected operating facilities. In each case listed above, cleaning
and relubricating the trip shaft mechanism within the circuit breaker was
required to correct the problem.
The enclosed GE Service Advice Letter (SAL) 175(CPDD) 9.3 is being sent to
all power reactor facilities notifying them of the potential problems. The
SAL identifies the causes for failure and provides their recommended
corrective action. Similar notification of the problem has been issued by
B&W to all specific B&W designed facilities.
Action to be Taken by Licensees:
For all power reactor facilities with an operating license or construction
permit:
1. Determine whether or not GE type AK-2 breakers are used or planned for
use in safety-related systems at your facility(ies).
2. If such circuit breakers are used or planned for use, identify the
safety system involved and provide in written form your plans for
developing a preventive maintenance program which will assure design
performance with the GE type AK-2 circuit breaker.
3. The program shall include as a minimum but not be limited to the
following:
a. Establish and adhere to a preventive maintenance schedule
regarding the subject circuit breakers.
b. Have the maintenance performed by qualified personnel. The GE
power circuit breaker instruction manual should be used as
guidance in setting up the maintenance procedures.
c. During the preventive maintenance, perform the recommended
corrective actions described in the enclosed GE Service Alert -
Letter No. 175(CPDD) 9.3, dated April 2, 1979. A copy of this
letter is enclosed for your information and appropriate use.
4. For facilities with an operating license, a written report of the above
actions, including the date(s) when they will be completed, shall be
submitted within 30 days of receipt of this Bulletin.
5. For facilities with a construction permit, a written report of the
above actions, including the date(s) when they will be completed, shall
be submitted within 60 days of receipt of this Bulletin.
.
IE Bulletin No. 79-09 April 17, 1979
Page 3 of 3
Reports should be submitted to the Director of the appropriate NRC Regional
Office. A copy of your report should be sent to the U.S. Nuclear Regulatory
Commission, Office of Inspection and Enforcement, Division of Reactor
Operations Inspection, Washington, D.C. 20555.
Approved by GAO, B180225 (R0072); clearance expires 7/31/80. Approval was
given under a blanket clearance specifically for identified generic
problems.
Enclosure:
Copy of Text of General
Electric Service Advice
Letter (SAL) No. 175(CPDD)
9.3
.
EXTRACT OF GE SERVICE ADVICE LETTER
NO. 175(CPDD)9.3
An undervoltage device is used on some AK type breakers to trip the breaker
when loss of voltage occurs on the undervoltage device coil. The
undervoltage device is an optional accessory for tripping the breaker and is
used in some circuits in place of a shunt trip device because of the
inference that it "fails safe" i.e., it trips the breaker when all normal
sources of control voltage have become unavailable for shunt trip type
operations. Because of the many constraints imposed on the undervoltage
device, such as the need to withstand rated voltage continuously, to pick-up
at 80 percent or rated voltage (industry standards now require pick-up at 85
percent of rated voltage) and to drop out at 30 percent to 60 percent of
rated voltage, both the undervoltage device and breaker must be maintained
at a high level of performance to provide the assurance the breaker will
trip when voltage is removed from the undervoltage device coil. The
following is recommended and except where the breaker is in warranty, should
be performed at the customer's expense.
Refer To Figure 1
1. Check the undervoltage trip device to assure there is not excessive
clearance between the armature and the rivet and that there are no
binds as the armature moves through its travel when manually operated.
If excessive clearance or binding exists, it should be adjusted by
loosening screws (11) and moving the magnet (10) up or down as
necessary to obtain the proper freedom of the armature (3) with respect
to its pivot on magnet (10) and the guide provided by pivet (13).
2. Check (and adjust if necessary) the trip latch engagement. This
adjustment is described in the maintenance manual for that particular
breaker.
3. Check (and adjust if necessary) the pick-up setting of the
instantaneous undervoltage device. In some instances, the standards for
nominal voltage ratings and pick-up settings have been raised since the
breakers were shipped from the factory. The new nominal voltages and
pick-up settings deviate substantially from these values, the device
should be readjusted while it is on the breaker.
.
- 2 -
Nominal Voltage Pick-up Setting
125V DC 106
250V DC 213
120V AC 102
240V AC 204
To adjust the pick-up of the instantaneous undervoltage trip device,
remove the Locking Wire (15) and turn the adjusting screw (14)
clockwise to raise the pick-up to the desired setting. A suitable
voltmeter and adjustable voltage source should be connected to the
undervoltage device coil leads at the terminal board for stationary
breakers or the secondary disconnects for drawout type breakers. On AC
devices, the pick-up voltage should be read immediately before the
armature closes its air gap. After the pick-up is adjusted, locking
wire (15) should be installed.
No adjustment is necessary on time-delay undervoltage devices, since
the undervoltage device coil is switched by a relay in the time-delay
unit.
4. The torque required on the trip shaft to trip a closed breaker should
not exceed 1.5 pounds-inches. This may be checked with the equivalent
of an open-end wrench fabricated from a piece of sheet metal to which
a spring scale can be fastened approximately 1 inch from the trip shaft
centerline. Where the torque required to trip the breaker exceeds 1.5
pound-inches, hardened grease in the trip shaft bearings and/or latch
bearing may be suspected or dirt may have accumulated on the trip latch
surface. Hardened grease must be replaced or revitalized with a
suitable solvent such as WD-40 or CRC 5-56 or the bearing must be
replaced. Excessive grease and dirt should be removed from the trip
latch surface.
5. The adjustment between the undervoltage trip device and the trip paddle
on the trip shaft should be checked to assure the required positive
trip is maintained (positive trip exists when approximately 1/32 inch
additional travel of the armature occurs after the undervoltage device
trips the breaker.) This adjustment is made with adjusting screw (20).
6. The frequency of inspection of the involved breakers should be
increased until it can be verified that the revitalization of the
grease is effective for the normal should be revitalized at normal
maintenance intervals.
Attachment:
Figure 1
Page Last Reviewed/Updated Tuesday, March 09, 2021