Bulletin 76-07: Crane Hoist Control - Circuit Modifications
IE Bulletin 76-07 DATE: July 27, 1976
CRANE HOIST CONTROL - CIRCUIT MODIFICATIONS
DESCRIPTION OF CIRCUMSTANCES:
In response to NRC concerns about the potential for, and consequences of,
dropping a spent fuel shipping cask or other heavy load, Commonwealth Edison
modified the hoist control system for the fuel cask handling cranes at their
Dresden Units 2 and 3 and Quad cities Units 1 and 2 to provide additional
hoist redundancy and slow speed hoist capability. The original design
utilized a General Electric "magspeed" hoist control system. In this system
which includes two electro-mechanical brakes in series, spring force holds
the brakes engaged while DC solenoids, energized when the hoist motor is
energized, disengage the brakes.
The modification which added the slow speed hoist capability included
installing additional contactors in the brake solenoid power circuit to
energize the solenoids when the low speed hoist motor was energized.
The original hoist control system design utilized a single Size 2 DC
contactor (two contacts in series) in the solenoid circuit. The design
modification added a circuit in parallel with the original DC contactor with
utilized four AC rated Size 1 single contacts in a series-parallel array to
distribute current carrying and interrupting burden.
Initial experience with the modified hoist control system at Dresden showed
that the circuit interrupting capacity of the series-parallel array was
marginal. On several occasions when the low speed motor was stopped in the
lowering mode, the solenoid circuit contacts arced resulting in power being
supplied to the solenoids long enough so that the load dropped some distance
before the brakes engaged. Over travel of as much as 15 inches was reported,
but no damage to hoist or load was found.
The crane manufacturer's representatives have advised the NRC that the
proposed corrective action is to install a single Size 2 DC contactor (two
contacts in series) with arc suppressors, the same as originally provided in
the General Electric design, in place of the added four AC rated contacts.
The original contactor in the normal speed control circuit has shown
satisfactory service since initial operation of the plant in 1969.
.
IE Bulletin 76-07 -2- DATE: July 27, 1976
ACTION TO BE TAKEN BY LICENSEE:
1. Determine and report to this office within 20 days the following
information:
(a) Have you made, or do you plan to make modifications to the hoist
control for your installed cranes similar to the described
modifications?
(b) If such modifications have been made, or are planned, identify
changes required in brake power and control circuitry?
(c) What steps have been taken or are planned, to provide assurance
that brake power contactors are adequate for the service?
2. If modifications are planned, provide the schedule for completion and a
brief description of your plans for design review and functional
testing.
Your response should be submitted to the Director of this Office, with a
copy to the Director, Division of Reactor Inspection Programs, Office of
Inspection and Enforcement, U. S. Nuclear Regulatory Commission, Washington,
D. C. 20555.
Approval of NRC requirements for reports concerning possible generic
problems has been obtained under 44 U. S. C. 3152 from the U. S. General
Accounting Office. (GAO Approval B-180255 (R0072), expires 7/31/77).
Enclosure:
Licensee Event Report dated 6/10/76
Page Last Reviewed/Updated Tuesday, March 09, 2021