Subject: 10CFR21 Interim Report 21-97-042: Discrepancies Between General
Electric Boiling Water Reactor (BWR) Design Requirements
Documents and System Vendor Manuals
Dear Madam or Sir:
On August 21, 1997, Illinois Power (IP) identified a discrepancy
between the General Electric (GE) Boiling Water Reactor (BWR) design
requirements 22A5604, "Turbine-Generator Control Requirements GE-Nuclear
Energy Division," and the field line-up instructions contained in GE
vendor manual K2804-0007C, "GEK-64903, Volume III, Steam Turbine-
Generator (EHC and TSI Section)." The specific discrepancy identified was
a difference between the GE BWR Design Requirements document and the
system vendor manual for the specified closing rate of the turbine
control valves. Condition Report (CR) 1-97-08-183 was initiated to track
an investigation of this issue.
On August 27, 1997, during investigation of CR 1-97-08-183, IP
determined that conflicts may exist between other GE BWR Design
requirements documents and the system vendor manuals. Condition Report
(CR) 1-97-08-303 was initiated to track an investigation of this issue.
This issue was determined to be potentially reportable under the
provisions of 10CFR21 on September 2, 1997. IP's evaluation of this
condition under 10CFR21 has not yet been completed. IP does not have a
firm date for resolving this issue but will provide, as a minimum, an
update on the resolution progress by December 18, 1997.
U-602855
Page 2
Additional information about this issue may be obtained by
contacting K. E. Moore, Plant Engineering, at (217) 935-8881, extension
3598.
Sincerely yours,
J. G. Cook
Senior Vice President
RSF/krk
cc: NRC Clinton Licensing Project Manager
NRC Resident Office, V-690
Regional Administrator, Region III, USNRC
Illinois Department of Nuclear Safety
INPO Records Center
General Electric
Sargent & Lundy
*** END OF DOCUMENT ***
Page Last Reviewed/Updated Wednesday, March 24, 2021