Part 21 Report - 1997-780
ACCESSION #: 9710070133
Coltec Industries Fairbanks Morse
Engine Division
701 White Avenue
Beloit, WI 53511-5492
608/364-4411
FAX: 608/364-0382
INTERIM LETTER
To: Document Control Desk
U.S. Nuclear Regulatory Commission
Washington, DC. 20555
From: Coltec Industries-Fairbanks Morse Engine Division (FMED)
Date: 30 September 1997
Subject: Weldments on Opposed Piston and Coltec-Pielstick Emergency
Stand-By Diesel Gen-Set Lube-Oil and Jacket Water Piping Systems
On 4 August 1997, FMED became aware that a weldment associated with the
lube-oil piping system failed at Millstone Unit 2. Further investigation
by the utility revealed less than full penetration in the affected weld.
The condition was observed in a weld joint associated with a 4 inch
mechanical tube section with a .250 inch wall located on the lube oil
pump discharge piping.
At this time, the root cause of the Millstone piping failure is not yet
known. However, due to the fact that the failure occurred in a weld with
partial penetration, the quality of the weldment is being considered.
The welds at issue are the original welds performed in the late 1960s,
and early 1970s; when contract requirements did not invoke either ASME
Section III, Class 3 Piping, or ANSI B31.1 Piping design requirements.
The following utility sites are affected:
Arkansas Nuclear One Millstone 1 & 2
Calvert Cliffs 1 & 2 North Anna 1 & 2
Crystal River 3 Peach Bottom 2 & 3
Duane Arnold Energy Center Plant Hatch 1 & 2
Farley 1 & 2 Prairie Island 1 & 2
Fermi 2 & 3 Vermont Yankee
A division of Coltec Industries, Inc.
Coltec Industries, Fairbanks Morse Engine Division is currently
conducting an evaluation under the rules of 10 CFR Part 21. Pipe
sections returned from Florida Power Corporation, Crystal River 3 and
sections of pipe from a spare unit returned by Baltimore Gas & Electric
earlier this year provide the source for initial samples currently being
analyzed by FMED. Additional samples of lube-oil and/or jacket water
piping have been requested from Florida Power, Millstone and Vermont
Yankee.
As a minimum, the following questions will be answered as a result of the
evaluation.
1) is the weld design compliant with customer requirements?
2) are the subject welds compliant with FMED design requirements?
3) if not, do the existing welds posses sufficient strength?
4) what is the root cause of the identified condition?
5) what corrective action, if any, should the customer take?
6) what preventive action is required by FMED?
It is estimated that the evaluation will require an additional six (6) to
ten (10) weeks to complete.
Sincerely,
Scott A. Fratianne
Sr. Quality Assurance Engineer
*** END OF DOCUMENT ***
Page Last Reviewed/Updated Wednesday, March 24, 2021