Part 21 Report - 1997-170
ACCESSION #: 9702120176
Detroit
Edison
Douglas R. Gipson
Senior Vice President
Nuclear Generation
Fermi 2
6400 North Dixie Highway
Edison Newport, Michigan 48166
(313) 586-5249
10CFR21.21
February 6, 1997
NRC-97-0005
U. S. Nuclear Regulatory Commission
Attn: Document Control Desk
Washington, D. C. 20555
Reference: Fermi 2
NRC Docket No. 50-341
NRC License No. NPF-43
Subject: 10CFR21 Interim Report for Emergency Diesel Generator
Automatic Voltage Regulator Printed Circuit Board
On November 13, 1996 at 0037 hours Emergency Diesel Generator (EDG)
number 11 failed surveillance test 24.307.01 (i.e., Technical
Specification 4.8.1.1.2) for Loss of Offsite Power coincident with Loss
of Coolant Accident (LOP/LOCA). The electrical system voltage dropped to
approximately 50% when Residual Heat Removal (RHR) system pump A was auto
initiated. Deviation Event Report (DER) 96-1655 was written to determine
a root cause and corrective actions for the problem.
Analysis of EDG number 11 components in the Automatic Voltage Regulator
(AVR) board revision B determined that the operational amplifier U8 chip
had failed. Voltage regulator system testing was conducted. The AVR was
again replaced with a revision B board and surveillance 24.307.01 run
with the same failure occurring. AVR board revision B was replaced with
the earlier revision A board. On November 26, 1996 surveillance
24.307.01 was performed successfully with the revision A board installed.
As part of the continuing investigation to determine the root cause, the
AVR board revision B was sent offsite to an independent engineering test
facility. On December 9, 1996 Detroit Edison determined that a 10CFR21
reportability evaluation should be performed. On January 30, 1997
Detroit Edison received a
USNRC
NRC-97-0005
Page 2
report from the testing facility on the U8 chip and the report is being
analyzed for its applicability to the AVR failure.
The AVR boards and U8 chips were supplied by Parsons Peebles as a safety
related component under 10CFR50 Appendix B requirements. Parsons Peebles
is now Peebles Electric Inc. and no longer supplies 10CFR50 Appendix B
components. If the AVR board (revision B) or U8 chip is defective, it
would create a substantial safety hazard because the ability of the EDGs
to perform their safety function would be adversely affected.
Corrective actions include more analysis and testing of the AVR board and
operational amplifier U8 chips. The 10CFR21 report should be completed
by June 30, 1997.
If you have any questions, please contact Joseph M. Pendergast,
Licensing Engineer at (313) 586-1682.
Sincerely,
cc: A. B. Beach
M. J. Jordan
A. J. Kugler
C. F. O'Keefe
*** END OF DOCUMENT ***
Page Last Reviewed/Updated Wednesday, March 24, 2021