Plant-Specific Actions in Response to the Japan Nuclear Accident: Kewaunee Power Station
subscribe to page updates
subscribe to page updates

Kewaunee Power Station is no longer an operating reactor. Please see Kewaunee Power Station decommissioning information.
Orders and Requests for Information Licensee Responses/Submittals
** Order for Ensuring Reliable Hardened Containment Vents is not applicable to this plant **
Request for Information
|
Request for Information for Seismic and Flooding Reevaluations and Walkdowns, and Reevaluations of Emergency Communications Systems and Staffing Levels
[+] Show More |
- Seismic Reevaluations
[-] Show Less
- Licensee Hazard Evaluation
- NRC Staff Assessment of Hazard Evaluation
- Licensee Expedited Seismic Evaluation Process (ESEP) Report
- NRC Staff Assessment of ESEP Report
- Limited Scope Evaluations (as applicable for each reactor site)
- Licensee High Frequency Evaluation
- NRC Staff Assessment of High Frequency Evaluation
- Licensee Spent Fuel Pool Evaluation
- NRC Staff Assessment of Spent Fuel Pool Evaluation
- Licensee Seismic Probabilistic Risk Assessment (SPRA) Report (if required)
- NRC Staff Assessment of SPRA Report
- Licensee Reevaluated Hazard (Seismic) Mitigating Strategies Assessment
- NRC Staff Response to Reevaluated Hazard (Seismic) Mitigating Strategies Assessment
- Flooding Reevaluations
[-] Show Less
- Flooding Hazard Reevaluation Report (due March 12, 2013 to March 12, 2015, depending on NRC prioritization)
- NRC Safety Evaluation of Hazard Reevaluation Report
- Integrated Assessment (due two years after flooding hazard evaluations and if needed)
- NRC Safety Evaluation of Integrated Assessment
- Reevaluations of Emergency Communications Systems
- Reevaluations of Staffing Levels
|