Nuclear Test Reactor (NTR)
1.0 Site Identification
Type of Site: |
Research and Test Reactor Facility |
Location: |
Sunol, CA |
License No.: |
R-33 |
Docket No.: |
50-73 |
License Status: |
SAFSTOR |
Project Manager: |
Chris Allen |
2.0 Site Status Summary
The NTR license was renewed on June 29, 2023, in response to the GE-Hitachi application for license renewal dated November 19, 2020. The licensee informed NRC that it had permanently ceased operation of the NTR on December 21, 2023, NRC issued a possession-only license for NTR on February 28, 2024. The facility is being maintained in a storage condition.
The licensee plans to submit a decommissioning plan for the NTR in December 2025.
3.0 Major Technical or Regulatory Issues
NONE
4.0 Estimated Date For Closure
Calendar year 2030