The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Technical Evaluation Report on the Content of the U.S. Department of Energy’s Yucca Mountain Repository License Application – Administrative and Programmatic Volume (NUREG-2109)

On this page:

Download complete document

Publication Information

Manuscript Completed: September 2011
Date Published: September 2011

Office of Nuclear Material Safety and Safeguards
U.S. Nuclear Regulatory Commission
Office of Nuclear Reactor Regulation
Washington, DC 20555-0001

Availability Notice

Abstract

This "Technical Evaluation Report on the Content of the U.S. Department of Energy's Yucca Mountain License Application; Administrative and Programmatic Volume" (TER Administrative and Programmatic Volume) presents information on the NRC staff's review of the U.S. Department of Energy (DOE) Safety Analysis Report (SAR), provided on June 3, 2008, as updated on February 19, 2009. The NRC staff also reviewed information DOE provided in response to NRC staff requests for additional information and other information that DOE provided related to the SAR. In particular, this report provides information on the NRC staff's evaluation of DOE's proposed administrative and programmatic activities regarding the following:

  • Research and Development Program to resolve safety question
  • Performance Confirmation Program
  • Quality Assurance Program
  • Records, reports, tests, and inspections
  • DOE organizational structure
  • Key positions assigned responsibility for safety and operations
  • Personnel qualifications and training
  • Plans for startup activities and testing
  • Plans for conduct of normal activities
  • Emergency planning
  • Controls to restrict access and regulate land uses
  • Uses of geologic repository operations area for purposes other than disposal ofradioactive wastes