Change Notice 05-011
Issue Date: 05/02/05
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
| DELETED: Number | Date | TRANSMITTED: Number | Date |
1. | ----- | ----- | TI 2515/163 | 05/02/05 |
TRAINING: | None. |
REMARKS: | TI 2515/163 (Operational Readiness of Offsite Power) is issued to verify the operational readiness of offsite power systems in accordance with the following NRC requirements: General Design Criterion (GDC) 17, "Electric power systems;" Plant Technical Specifications for offsite power systems; 10 CFR 50.63, "Loss of all alternating current power;" and 10 CFR 50.65(a)(4), "Requirements for monitoring the effectiveness of maintenance at nuclear power plants." This inspection would also ensure the readiness of nuclear power plants to cope with the potential challenges by power outage events during the summer of 2005. |
DISTRIBUTION: Standard
END
Page Last Reviewed/Updated Thursday, July 02, 2015