The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for September 25, 2024

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 100
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100
*
Ginna 95 Coastdown To Refueling Outage
Hope Creek 1 100

Limerick 1 100


Limerick 2 100
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 0 9/24/2024 Reactor scram refer to EN # 57334
*
Peach Bottom 2 93 Coastdown To Refueling Outage
Peach Bottom 3 100
Salem 1 100
Salem 2 97
Coastdown To Refueling Outage
Seabrook 1 100 Down power contingencies to 900 MWe, 1000 MWe.
Susquehanna 1 100
Susquehanna 2 100

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 0 8/31/2024 Refueling Outage
Browns Ferry 2 100
Browns Ferry 3 100
Brunswick 1 100 *
Brunswick 2 100
Catawba 1 95
Coastdown To Refueling Outage
Catawba 2 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 99 Reduced Power For Maintenance *
Hatch 2 100
McGuire 1 100
McGuire 2 100
*
North Anna 1 100
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 0 8/31/2024 Refueling Outage
Sequoyah 1 100
Sequoyah 2 0 7/31/2024 Refueling Outage
Summer 0 9/21/2024 Refueling Outage
*
Surry 1 100
Surry 2 100
Turkey Point 3 100

Turkey Point 4 100
Vogtle 1 0 9/8/2024 Refueling Outage
*
Vogtle 2 100 Conservative operations due to weather *
Vogtle 3 0 9/17/2024 Reactor Trip. EN 57326.
Vogtle 4 100
Watts Bar 1 100
Watts Bar 2 100

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100
Braidwood 2 99 Coastdown To Refueling Outage
*
Byron 1 0 9/9/2024 Refueling Outage
*
Byron 2 100
Clinton 100 *
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 100
Dresden 3 100
Fermi 2 100
LaSalle 1 100
LaSalle 2 100
Monticello 100
Perry 1 96 Reduced Power Due to Environmental Conditions
*
Point Beach 1 100
Point Beach 2 93 Coastdown To Refueling Outage
Prairie Island 1 0 9/21/2024 Refueling Outage *
Prairie Island 2 100
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 80 Coastdown To Refueling Outage
*
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100


Comanche Peak 2 100
Cooper 88 Coastdown To Refueling Outage
*
Diablo Canyon 1 100
Diablo Canyon 2 100
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 100

Palo Verde 3 100
River Bend Station 1 96 Reduced Power For Maintenance
*
South Texas 1 100
South Texas 2 100
Waterford 3 93 Transformer Limitation.
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.
  • Additional plant status information is made available on the web page after 28 days.

Page Last Reviewed/Updated Wednesday, October 23, 2024