The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for May 30, 2022

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100

Beaver Valley 2 100
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100
Ginna 100
Hope Creek 1 100
Limerick 1 100
Limerick 2 100
Millstone 2 100
Millstone 3 0 4/8/2022 Refueling Outage
Nine Mile Point 1 100
Nine Mile Point 2 100

Peach Bottom 2 100
Peach Bottom 3 100
Salem 1 100
Salem 2 100
Seabrook 1 100
Susquehanna 1 78 Increasing power after rod pattern adjustment. *
Susquehanna 2 100

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100

Browns Ferry 2 100 *
Browns Ferry 3 100
Brunswick 1 100
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Farley 1 100
Farley 2 100


Harris 1 100
Hatch 1 97 Decreased power following sequence exchange.

Hatch 2 100
McGuire 1 100
McGuire 2 100
North Anna 1 97
Decreased power for plant computer replacement
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 21 Increasing power after refueling outage.
*
Robinson 2 100
Saint Lucie 1 99 Holding power due to condensate pump design margin issue.
Saint Lucie 2 100

Sequoyah 1 100
Sequoyah 2 100
Summer 100
Surry 1 100
Surry 2 100

Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 100
Watts Bar 2 0 3/2/2022 Refueling Outage

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100
Braidwood 2 100
Byron 1 100
Byron 2 100
Clinton 100
D.C. Cook 1 12 Increasing Power
*
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 84 Reduced Power for Economic Dispatch
*
Dresden 3 100
Fermi 2 100
LaSalle 1 85 Reduced Power for Economic Dispatch
*
LaSalle 2 100
Monticello 100
Palisades 0 5/20/2022 Permanent Shutdown
Perry 1 100
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 100
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 10 Increasing Power
*
Columbia Generating Station 78 Reduced power due to feedwater heater trip.
*
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 100
Grand Gulf 1 95 Reduced Power For Rod Pattern Adjustment
*
Palo Verde 1 100
Palo Verde 2 100

Palo Verde 3 100

River Bend Station 1 100
South Texas 1 100
South Texas 2 100
Waterford 3 0 4/2/2022 Refueling Outage
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.
  • Additional plant status information is made available on the web page after 28 days.

Page Last Reviewed/Updated Monday, June 27, 2022