The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for April 11, 2022

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100
*
Beaver Valley 2 100 *
Calvert Cliffs 1 100 *
Calvert Cliffs 2 100 *
FitzPatrick 100
Ginna 100
Hope Creek 1 100
Limerick 1 0 4/4/2022 Refueling Outage; *
Limerick 2 100 *
Millstone 2 100
Millstone 3 0 4/8/2022 Refueling Outage
Nine Mile Point 1 100
Nine Mile Point 2 100
Peach Bottom 2 100
*
Peach Bottom 3 100 *
Salem 1 0 4/9/2022 Refueling Outage
Salem 2 100
Seabrook 1 100 Two contingencies to downpower to 1000 MW Net due to offsite transmission concerns
Susquehanna 1 0 3/28/2022 Refueling Outage
*
Susquehanna 2 100 *

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 100
Browns Ferry 3 100
*
Brunswick 1 80 Holding power for testing *
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Farley 1 100
Farley 2 0 4/11/2022 Refueling Outage
*
Harris 1 100
Hatch 1 100
Hatch 2 100
McGuire 1 0 4/2/2022 Refueling Outage
McGuire 2 100
North Anna 1 100 *
North Anna 2 28 Increasing Power
*
Oconee 1 100
Oconee 2 100
Oconee 3 95 Coastdown To Refueling Outage
*
Robinson 2 100
Saint Lucie 1 99 Holding power due to condensate pump design margin issue.
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 100
Summer 100
Surry 1 100
Surry 2 100
Turkey Point 3 100
Turkey Point 4 3 Commencing Startup *
Vogtle 1 100
Vogtle 2 65 Reduced Power due to equipment failure
*
Watts Bar 1 100
Watts Bar 2 0 3/2/2022 Refueling Outage

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100
*
Braidwood 2 100
*
Byron 1 100
*
Byron 2 78 Coastdown To Refueling Outage
*
Clinton 100
*
D.C. Cook 1 0 4/2/2022 Refueling Outage

*
D.C. Cook 2 100 *
Davis-Besse 0 3/5/2022 Refueling Outage
*
Dresden 2 100
*
Dresden 3 0 4/10/2022
Forced Outage
*
Fermi 2 0 2/5/2022 Refueling Outage
*
LaSalle 1 100 *
LaSalle 2 100 *
Monticello 100 *
Palisades 100 *
Perry 1 100
*
Point Beach 1 0 3/26/2022 Refueling Outage
*
Point Beach 2 100 *
Prairie Island 1 100
*
Prairie Island 2 100
*
Quad Cities 1 100 *
Quad Cities 2 0 3/21/2022 Refueling Outage
*

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 0 4/4/2022 Refueling Outage
Columbia Generating Station 100
Comanche Peak 1 0 4/10/2022 Refueling Outage
*
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 0 3/27/2022 Refueling Outage
Diablo Canyon 2 100
Grand Gulf 1 0 2/27/2022 Refueling Outage
Palo Verde 1 0 4/8/2022

Refueling Outage
Palo Verde 2 100

Palo Verde 3 100

River Bend Station 1 100
South Texas 1 100
South Texas 2 100
Waterford 3 0 4/2/2022 Refueling Outage
Wolf Creek 1 100
*

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.
  • Additional plant status information is made available on the web page after 28 days.

Page Last Reviewed/Updated Monday, May 9, 2022