Power Reactor Status Report for January 31, 2022

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100
*
Beaver Valley 2 100 *
Calvert Cliffs 1 97 Coastdown To Refueling Outage
*
Calvert Cliffs 2 100 *
FitzPatrick 100
Ginna 100
Hope Creek 1 100
Limerick 1 100
Limerick 2 100
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 98 Coastdown To Refueling Outage
*
Peach Bottom 2 100
Peach Bottom 3 100
Salem 1 100
Salem 2 100
Seabrook 1 100
*
Susquehanna 1 93 Coastdown To Refueling Outage, Flow Limited
*
Susquehanna 2 100

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100
*
Browns Ferry 2 100

Browns Ferry 3 85 Coastdown To Refueling Outage
Brunswick 1 96 Flow limited until rod pattern adjustment
Brunswick 2 0 1/28/2022 Shutdown for Unplanned Maintenance
Catawba 1 100 *
Catawba 2 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 92 Coastdown To Refueling Outage

Hatch 2 100
McGuire 1 100
McGuire 2 100
North Anna 1 100
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 98 Holding power due to feed regulating valve issue
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 100
Summer 100
Surry 1 100
*
Surry 2 100
*
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 100
Watts Bar 2 95 Holding power due to S/G conditions

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100
Braidwood 2 100
Byron 1 100
Byron 2 100
Clinton 99 100% Electrical Capability
D.C. Cook 1 100

D.C. Cook 2 100
Davis-Besse 100
Dresden 2 100
Dresden 3 100
Fermi 2 58 Coastdown To Refueling Outage *
LaSalle 1 93 Coastdown to Refueling Outage
LaSalle 2 100
Monticello 100
Palisades 100
Perry 1 100
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 100
Quad Cities 1 100
Quad Cities 2 99 Coastdown To Refueling Outage
*

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100

Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 100
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 0 1/25/2022 Shutdown For Maintenance
Palo Verde 3 100

River Bend Station 1 100
South Texas 1 100
South Texas 2 100
Waterford 3 100

Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.
  • Additional plant status information is made available on the web page after 28 days.