The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for April 12, 2021

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 0 4/11/2021 High System Voltage Action,
Refueling Outage
*
Beaver Valley 2 100 High System Voltage Action
Calvert Cliffs 1 97 Grid dispatcher request
High System Voltage Action
Calvert Cliffs 2 100 High System Voltage Action
FitzPatrick 100

Ginna 100
Hope Creek 1 77 Coastdown To Refueling Outage
Indian Point 2 0 4/30/2020 Reactor defueled for permanent shutdown
Indian Point 3 84 Coastdown To Refueling Outage *
Limerick 1 100 *
Limerick 2 80 Coastdown To Refueling Outage

Millstone 2 100
Millstone 3 100
Nine Mile Point 1 60 Increasing Power
*
Nine Mile Point 2 100
Peach Bottom 2 100
Peach Bottom 3 100
Salem 1 100 High System Voltage Action
Salem 2 100 High System Voltage Action
Seabrook 1 100 One contingency from downpower to 1100 MWe. *
Susquehanna 1 100 High System Voltage Action
Susquehanna 2 0 3/22/2021 Refueling Outage
High System Voltage Action

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 0 2/26/2021 Refueling Outage
Browns Ferry 3 100
Brunswick 1 100
Brunswick 2 99 Increasing Power
*
Catawba 1 100
Catawba 2 0 3/28/2021 Refueling Outage
Farley 1 0 3/22/2021 Refueling Outage
Farley 2 100
Harris 1 99 Coastdown To Refueling Outage
*
Hatch 1 100
Hatch 2 96 Reduced Power For Rod Pattern Adjustment
*
McGuire 1 100
McGuire 2 100
North Anna 1 0 3/14/2021 Refueling Outage
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 0 4/10/2021 Planned Maintenance Outage
Saint Lucie 2 100
Sequoyah 1 0 4/10/2021 Refueling Outage
Sequoyah 2 100
Summer 100
Surry 1 97 Reduced Power For Unplanned Maintenance Until Outage
Surry 2 100
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 100
Watts Bar 2 90 Max Power until Steam Generator Replacement.

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 0 4/5/2021 Refueling Outage

Braidwood 2 100
Byron 1 100
Byron 2 100
Clinton 99 Full Electrical Output
*
D.C. Cook 1 100

High System Voltage Action
D.C. Cook 2 100
High System Voltage Action
Davis-Besse 100
High System Voltage Action
Dresden 2 100 High System Voltage Action
Dresden 3 100
High System Voltage Action
Fermi 2 100
LaSalle 1 100 High System Voltage Action
LaSalle 2 0 2/22/2021 Refueling Outage,
High System Voltage Action
Monticello 81 Coastdown To Refueling Outage *
Palisades 100
Perry 1 73
Increasing Power
*
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 100
Quad Cities 1 100

Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 0 4/10/2021
Refueling Outage
Arkansas Nuclear 2 100
Callaway 0 12/25/2020 See EN# 55049
Columbia Generating Station 92 Coastdown To Refueling Outage
*
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 0 2/4/2021 Forced Outage and Refueling Outage
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 0 4/10/2021 Refueling Outage
River Bend Station 1 100
*
South Texas 1 100
South Texas 2 0 3/20/2021 Refueling Outage
Waterford 3 99 Holding Power

Wolf Creek 1 0 3/25/2021
Refueling Outage

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.