The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for April 08, 2020

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 79 COASTDOWN TO REFUELING OUTAGE *
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100
Ginna 0 4/5/2020 REFUELING OUTAGE
Hope Creek 1 100
Indian Point 2 83 COASTDOWN TO DEFUELING *
Indian Point 3 100
Limerick 1 0 3/27/2020 REFUELING OUTAGE
Limerick 2 100
Millstone 2 100
Millstone 3 0 4/1/2020 FORCED OUTAGE
Nine Mile Point 1 100
Nine Mile Point 2 95 CONTROL ROD ADJUSTMENT *
Peach Bottom 2 100
Peach Bottom 3 100
Salem 1 100
Salem 2 91 COASTDOWN TO REFUELING OUTAGE *
Seabrook 1 0 4/1/2020 REFUELING OUTAGE
Susquehanna 1 0 3/27/2020 REFUELING OUTAGE
Susquehanna 2 99 MAINTAIN 100 MVAR DUE TO GRID INSTABILITIES
100% ELECTRICAL CAPABILITY
Three Mile Island 1 0 9/20/2019 REACTOR DEFUELED FOR PERMANENT SHUTDOWN

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 100
Browns Ferry 3 95 INCREASING POWER *
Brunswick 1 60 POWER SUPPRESSION TESTING *
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 97 TROUBLE SHOOTING SRV TEMP SWING *
Hatch 2 100
McGuire 1 100
McGuire 2 0 3/20/2020 REFUELING OUTAGE - REFUELED
North Anna 1 100
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 92 COASTDOWN TO REFUELING OUTAGE *
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 81 COASTDOWN TO REFUELING OUTAGE
Summer 91 REDUCED POWER FOR TESTING *
Surry 1 100
Surry 2 100
Turkey Point 3 0 3/29/2020 DEFUELED
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 100
Watts Bar 2 100

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100 *
Braidwood 2 96 COASTDOWN TO REFUELING OUTAGE *
Byron 1 100
Byron 2 100
Clinton 99 100% ELECTRICAL CAPABILITY
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 99 REDUCED POWER FOR PLANNED MAINTENANCE *
Dresden 2 100
Dresden 3 100
Duane Arnold 100
Fermi 2 0 3/21/2020 REFUELING OUTAGE
LaSalle 1 100
LaSalle 2 100
Monticello 100
Palisades 100
Perry 1 100
Point Beach 1 100
Point Beach 2 74 HOLDING POWER FOR TESTING *
Prairie Island 1 100 *
Prairie Island 2 100
Quad Cities 1 100
Quad Cities 2 0 3/29/2020 REFUELING OUTAGE

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 0 3/13/2020 REFUELING OUTAGE
Callaway 99 INCREASING POWER *
Columbia Generating Station 100
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 100
Grand Gulf 1 0 2/22/2020 REFUELING OUTAGE
Palo Verde 1 100
Palo Verde 2 0 4/3/2020 REFUELING OUTAGE
Palo Verde 3 100
River Bend Station 1 68 REDUCED POWER FOR MAINTENANCE AND FUEL SUPPRESSION TESTING *
South Texas 1 0 3/13/2020 REFUELING OUTAGE
South Texas 2 100
Waterford 3 100
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.
  • Additional plant status information is made available on the web page after 28 days.

Page Last Reviewed/Updated Tuesday, June 30, 2020