Power Reactor Status Report for September 14, 2014

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100   HIGH SYSTEM VOLTAGE ACTION *  
Calvert Cliffs 2 80   REDUCED POWER FOR WATER BOX CLEANING HIGH SYSTEM VOLTAGE ACTION *  
FitzPatrick 0 08/24/2014 REFUELING OUTAGE - LOADING FUEL    
Ginna 100        
Hope Creek 1 100   HIGH SYSTEM VOLTAGE ACTION *  
Indian Point 2 100        
Indian Point 3 100        
Limerick 1 100     *  
Limerick 2 63   REDUCED POWER FOR WATERBOX CLEANING *  
Millstone 2 100        
Millstone 3 100     *  
Nine Mile Point 1 81   INCREASING POWER *  
Nine Mile Point 2 100     *  
Oyster Creek 97   COASTDOWN TO REFUELING OUTAGE *  
Peach Bottom 2 98   COASTDOWN TO REFUELING OUTAGE    
Peach Bottom 3 100        
Pilgrim 1 100        
Salem 1 100     *  
Salem 2 100     *  
Seabrook 1 100        
Susquehanna 1 100   HIGH SYSTEM VOLTAGE ACTION *  
Susquehanna 2 1   REACTOR CRITICAL HIGH SYSTEM VOLTAGE ACTION *  
Three Mile Island 1 100   HIGH SYSTEM VOLTAGE ACTION *  
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 61   COASTDOWN TO REFUELING OUTAGE REDUCED POWER FOR POWER SUPPRESSION TESTING *  
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 100        
Catawba 1 100        
Catawba 2 100        
Farley 1 100        
Farley 2 100        
Harris 1 100        
Hatch 1 100        
Hatch 2 100        
McGuire 1 0 09/12/2014 REFUELING OUTAGE *  
McGuire 2 100        
North Anna 1 100        
North Anna 2 0 09/06/2014 REFUELING OUTAGE    
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 100        
Saint Lucie 1 100        
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 100        
Vogtle 2 30   SHUTTING DOWN FOR REFUELING OUTAGE *  
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100     *  
Byron 2 100        
Clinton 98   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100   HIGH SYSTEM VOLTAGE ACTION    
D.C. Cook 2 100   HIGH SYSTEM VOLTAGE ACTION *  
Davis-Besse 100   HIGH SYSTEM VOLTAGE ALERT *  
Dresden 2 100        
Dresden 3 97   COASTDOWN TO REFUELING OUTAGE    
Duane Arnold 89   COASTDOWN TO REFUELING OUTAGE *  
Fermi 2 100     *  
La Salle 1 100        
La Salle 2 100        
Monticello 53   LOSS OF RECIRC PUMP *  
Palisades 100     *  
Perry 1 100     *  
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 98   INCREASING POWER AFTER TURBINE VALVE TESTING *  
Quad Cities 1 94   INCREASING POWER AFTER ROD PATTERN ADJUSTMENT *  
Quad Cities 2 100        

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 92   COASTDOWN TO REFUELING OUTAGE    
Diablo Canyon 1 100        
Diablo Canyon 2 100        
Fort Calhoun 100        
Grand Gulf 1 100        
Palo Verde 1 100        
Palo Verde 2 100        
Palo Verde 3 100        
River Bend 1 100        
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Thursday, March 25, 2021