The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for September 3, 2011

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 100     *  
FitzPatrick 100        
Ginna 100        
Hope Creek 1 100        
Indian Point 2 100        
Indian Point 3 100        
Limerick 1 64   ROD PATTERN ADJUSTMENT/CORE LEED TESTING *  
Limerick 2 100        
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 99        
Peach Bottom 2 100        
Peach Bottom 3 89   COASTDOWN TO REFUELING OUTAGE *  
Pilgrim 1 100        
Salem 1 80   DOWN POWER DUE TO GRASSING *  
Salem 2 100        
Seabrook 1 100   ISO NO GENERATION RISK(MLCC-2)    
Susquehanna 1 100        
Susquehanna 2 100        
Three Mile Island 1 50   DOWN POWER FOR SCHEDULED MAINTENANCE *  
Vermont Yankee 96   SEE EN #47238 *  

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100        
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 55   POWER SUPPRESSION TESTING *  
Catawba 1 100        
Catawba 2 100        
Crystal River 3 0 09/25/2009 DEFUELED; CONTAINMENT TENSIONING ON HOLD    
Farley 1 95   GOVERNOR VALVE TESTING *  
Farley 2 100        
Harris 1 100        
Hatch 1 100        
Hatch 2 90   HOLDING DUE TO SRV LEAKAGE *  
McGuire 1 100        
McGuire 2 100        
North Anna 1 0 08/23/2011 SEE EN# 47201    
North Anna 2 0 08/23/2011 SEE EN# 47201    
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 100        
Saint Lucie 1 100        
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 96   INCREASING POWER *  
Vogtle 2 96   COASTDOWN TO REFUELING OUTAGE    
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 72   TURBINE THROTTLE VALVE MAINTENANCE *  
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 97   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100        
D.C. Cook 2 100        
Davis-Besse 100        
Dresden 2 85   LIMITED BY DISCHARGE TEMPERATURE    
Dresden 3 100        
Duane Arnold 100        
Fermi 2 100        
Kewaunee 100        
La Salle 1 100        
La Salle 2 100        
Monticello 100        
Palisades 100        
Perry 1 96   CIRC WATER DISCHARGE LIMIT *  
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 100        
Quad Cities 1 100        
Quad Cities 2 75   TURBINE TESTING *  

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 0 04/02/2011 REFUELING OUTAGE    
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 100        
Diablo Canyon 1 50   CONDENSER CLEANING *  
Diablo Canyon 2 52   INCREASING POWER *  
Fort Calhoun 0 04/09/2011 REFUELING OUTAGE *  
Grand Gulf 1 96   2ND STAGE MSR LIMITED TO 96% POWER    
Palo Verde 1 100        
Palo Verde 2 100        
Palo Verde 3 100        
River Bend 1 100        
San Onofre 2 100        
San Onofre 3 100        
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Wednesday, March 24, 2021