The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for August 7, 2006

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 100        
FitzPatrick 100        
Ginna 100        
Hope Creek 1 95   INCREASING POWER *  
Indian Point 2 100        
Indian Point 3 100        
Limerick 1 100        
Limerick 2 100        
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 91   HIGH CONDENSER DISCHARGE TEMPERATURE *  
Peach Bottom 2 100        
Peach Bottom 3 100        
Pilgrim 1 100        
Salem 1 100        
Salem 2 100        
Seabrook 1 100        
Susquehanna 1 100        
Susquehanna 2 100        
Three Mile Island 1 100        
Vermont Yankee 99   XENON BUILDING IN *  

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 0 03/03/1985 DEFUELED    
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 100   0900 ENTERING GRID CONTINGENCY ALERT *  
Brunswick 2 100   0900 ENTERING GRID CONTINGENCY ALERT *  
Catawba 1 100        
Catawba 2 100        
Crystal River 3 100        
Farley 1 100        
Farley 2 100        
Harris 1 100   0700-2200 GRID CONTINGENCY ALERT *  
Hatch 1 100        
Hatch 2 100        
McGuire 1 100        
McGuire 2 100        
North Anna 1 100        
North Anna 2 100        
Oconee 1 100   GRID YELLOW *  
Oconee 2 100   GRID YELLOW *  
Oconee 3 100   GRID YELLOW *  
Robinson 2 100   0700 ENTERING GRID CONTINGENCY ALERT *  
Saint Lucie 1 100        
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 100        
Vogtle 2 100        
Watts Bar 1 100     *  

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 97   100% ELECTRICAL CAPABILITY *  
D.C. Cook 1 100        
D.C. Cook 2 100        
Davis-Besse 100        
Dresden 2 99   100% ELECTRICAL CAPABILITY    
Dresden 3 100        
Duane Arnold 96   100% ELECTRICAL CAPABILITY    
Fermi 2 100        
Kewaunee 100        
La Salle 1 100        
La Salle 2 100        
Monticello 100        
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 100        
Quad Cities 1 98   100% ELECTRICAL CAPABILITY *  
Quad Cities 2 98   100% ELECTRICAL CAPABILITY    

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 100   HIGH FLOW OF POWER SOUTH OUT OF COOPER SUBSTATION DUE TO DEMAND *  
Diablo Canyon 1 100   AT 0600 PDT 500KV BUS #2 WILL BE OOS FOR MAINTENANCE FOR APPROXIMATELY 12 HOURS. *  
Diablo Canyon 2 100   AT 0600 PDT 500KV BUS #2 WILL BE OOS FOR MAINTENANCE FOR APPROXIMATELY 12 HOURS. *  
Fort Calhoun 100   345KV RAUN LINE LOST FROM FT. CALHOUN TO SIOUX CITY, IA DUE TO FAILURE OF TOWER KNEE BRACE WHICH BROKE DOWN THE ALPHA PHASE - ANTICIPATE RESTORATION SHORTY *  
Grand Gulf 1 100        
Palo Verde 1 80   REDUCED POWER DUE TO PARTIAL LENGTH CONTROL ROD SLIPPING APPROXIMATELY 6" INTO CORE - TROUBLESHOOTING IN PROGRESS *  
Palo Verde 2 100        
Palo Verde 3 100        
River Bend 1 100        
San Onofre 2 99        
San Onofre 3 100        
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.