The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

SUBCOMMITTEE ON FIRE PROTECTION

MEETING OF THE ADVISORY COMMITTEE ON REACTOR SAFEGUARDS
SUBCOMMITTEE ON FIRE PROTECTION
OCTOBER 16-17, 2000
ROCKVILLE, MARYLAND

ACRS CONTACT
Amarjit Singh (axs3@nrc.gov)
301-415-6899

- PROPOSED SCHEDULE -
October 16, 2000

  TOPIC SPEAKER TIME  
I. Opening Remarks Sieber 8:30-8:35 A.M.
II. BWROG Presentation: Gorman 8:35-10:35A.M.
  a. Use of SRVs and Low
Pressure Systems (LPS) as
Redundant SRVs and LPS as
Redundant Safe Shutdown Paths
   
  b. Associated Circuit
Analysis for Post-Fire
Safe Shutdown
   
***BREAK***   10:35-10:50 A.M.
EI Presentation: Emerson 10:50-12:30 P.M.    
      Associated Circuit
    Analysis for Post-Fire
    Safe Shutdown
   
***LUNCH***   12:30-1:30 P.M.
IV. RES Presentation: Siu 1:30:-3:30 P.M.
      Research Activities
    in the area of Fire Protection
*** BREAK***
  3:30-3:45 P.M.
V. NFPA Presentation: Bielen/Snopili 3:45-5:45 P.M.
      Proposed NFPA 805
    Fire Protection Standard
***RECESS***    
October 17, 2000
VI. NRR Presentation:    
a. Use of SRVs and Low
Pressure Systems (LPS) as
Redundant SRVs and LPS as
Redundant Safe Shutdown Paths
Qualls 8:30-9:30 A.M.
b. Associated Circuit Analysis Whitney 9:30-10:30 A.M.

***BREAK***

10:30-10:45 A.M.
c. Proposed NFPA 805
Fire Protection Standard
Connell 10:45-12:00 Noon.

***LUNCH ***

12:00-1:00 P.M.
VII. Inspection Procedures
    for Baseline Inspection
    Fire Protection
Whitney 1:00:-2:00 P.M.
VIII NEI Presentation
    On Inspection Procedures
    for Baseline Fire Protection
Emerson 2 :00-2:45 P.M.
IX Remarks by Subcommittee Members   2:45-3:00 P.M.
***ADJOURN***    