Approved Power Uprate Application Information For Millstone 3

The following table refers to NRC-approved power uprate applications. The table shows the ADAMS accession number for (1) each plant's power uprate application, (2) any supplement to the application, and (3) the license amendment approving the application and allowing the licensee to increase power. These documents illustrate the information that the NRC staff requires in order to complete a power uprate review.

NRC encourages licensees to review the documents listed in the table before preparing a power uprate application. Addressing the information contained in these documents below may improve the quality of the application, thereby reducing the number of RAIs, and expedite the staff's review.

On this page:

Millstone Power Station Unit 3
Operating License No. NPF-49 (Docket No. 50-423)

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Application Information

Date Description Adams
Accession No.
07/13/2007 Dominion Nuclear Connecticut, Inc., Millstone Power Station Unit 3 License Amendment Request, Stretch Power Uprate ML072000386

To top of page

Supplement Information

Date Description Adams
Accession No.
07/13/2007 Millstone Power Station Unit 3 - License Amendment Request - Stretch Power Uprate - Supplemental Information ML072000281
09/12/2007 Millstone Power Station Unit 3 - Supplemental Information for License Amendment Request Stretch Power Uprate ML072570061
11/19/2007 Millstone Power Station Unit 3, Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request ML073230976
12/13/2007 Millstone Power Station Unit 3, Supplemental Information for License Amendment Request Stretch Power Uprate ML073480240
12/17/2007 Millstone Power Station Unit 3 - Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request ML073520051
01/10/2008 Millstone Power Station Unit 3, Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Questions EEEB-07-0049 Through EEEB-07-0057 ML080100600
ML080100604
ML080100606
ML080100611
01/11/2008 Millstone Power Station Unit 3 Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request, Response to Questions CSGB-07-0010 AND CSGB-07-0011 ML080110695
ML080140077
ML080170495
ML080580476
01/14/2008 Millstone Power Station Unit 3, Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Questions EMCB-07-0060 Through EMCB-07-0069 and EMCB-07-0071 Through EMCB-07-0081 ML080140570
01/18/2008 Millstone Power Station Unit 3, Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question EICB-07-0106 ML080220506
ML080220527
ML080220530
ML080220541
ML080280375
01/31/2008 Millstone Power Station Unit 3, Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question EMCB-07-0070 ML080320308
02/25/2008 Millstone Power Station Unit 3, Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request, Supplemental Response to Question EMCB-07-0072 ML080560392
ML080560615
03/05/2008 Millstone Power Station Unit 3 - Supplemental Information Regarding Stretch Power Uprate License Amendment Request ML080660108
03/10/2008 Millstone Power Station Unit 3, Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question AADB-07-0107 ML080710377
ML080710391
03/25/2008 Millstone Power Station, Unit 3 - Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Supplemental Response to Question EEEB-07-0052 ML080850894
03/27/2008 Millstone Power Station Unit 3 - Supplemental Information Regarding Stretch Power Uprate License Amendment Request ML080880268
04/04/2008 Millstone Power Station Unit 3 - Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Supplemental Response to Question EMCB-07-0072 ML081430014
04/24/2008 Millstone Power Station Unit 3, Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Supplemental Information, Rod Withdrawal at Power Event ML081150679
04/29/2008 Millstone Power Station Unit 3, Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Revised Response to Questions EEEB-07-0052, EEEB-07-0054 and EEEB-07-0055 ML081200643
05/15/2008 Millstone Power Station Unit 3 - Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Revised Response to Follow-ups EEEB-08-0108 Through EEEB08-0113 to Question EEEB-07-0052 ML081360625
05/20/2008 Millstone Power Station Unit 3, Supplemental Information Regarding Stretch Power Uprate License Amendment Request Miscellaneous Updates to the License Amendment Request ML081420443
05/21/2008 Millstone Power Station Unit 3, Stretch Power Uprate License Amendment Request Additional Information in Connection with the NRC Audit Held on May 13, 2008 in Rockville, Maryland ML081420824
07/10/2008 Millstone Power Station Unit 3, Stretch Power Uprate License Amendment Request DNC Comments on Draft Safety Evaluation - Stretch Power Uprate ML081930274
07/16/2008 Millstone Power Station Unit 3, Stretch Power Uprate License Amendment Request Supplement to DNC Comments on Draft Safety Evaluation Stretch Power Uprate ML081990112

To top of page

Amendment Information

Date Description Adams
Accession No.
08/12/2008 Millstone Power Station, Unit No. 3 - Issuance of Amendment Re: Stretch Power Uprate (TAC No. MD6070) ML082180137