Approved Power Uprate Application Information For Braidwood 1 & 2 and Byron 1 & 2 (Combined Application)

The following table refers to NRC-approved power uprate applications. The table shows the ADAMS accession number for (1) each plant's power uprate application, (2) any supplement to the application, and (3) the license amendment approving the application and allowing the licensee to increase power. These documents illustrate the information that the NRC staff requires in order to complete a power uprate review.

NRC encourages licensees to review the documents listed in the table before preparing a power uprate application. Addressing the information contained in these documents below may improve the quality of the application, thereby reducing the number of RAIs, and expedite the staff's review.

On this page:

Braidwood Station, Units 1 and 2
Facility Operating License Nos. NPF-72 and NPF-77 ( Docket Nos. STN 50-456 and STN 50-457)

Byron Station, Units 1 and 2
Facility Operating License Nos. NPF-37 and NPF-66 ( Docket Nos. STN 50-454 and STN 50-455)

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Application Information

Date Description Adams
Accession No.
07/05/2000 Request for a License Amendment to Permit Uprated Power Operations at Byron and Braidwood Stations ML003730608

To top of page

Supplement Information

Date Description Adams
Accession No.
11/27/2000 Response to Request for Additional Information Regarding the License Amendment Request to Permit Uprated Power Operations at Byron and Braidwood Stations ML003772455
12/21/2000 Response to Request for Additional Information Regarding the License Amendment Request to Permit Uprated Power Operations at Byron and Braidwood Stations ML003780801
1/31/2001 Response to Request for Additional Information Regarding the License Amendment Request to Permit Uprated Power Operations at Byron and Braidwood Stations ML010330145
02/20/2001 Additional Information Supporting the License Amendment Request to Permit Uprated Power Operations at Byron and Braidwood Stations ML010580161
02/28/2001 Release Point and Receptor Intake Locations ML010620057
03/26/2001 Additional Information Supporting the License Amendment Request to Permit Uprated Power Operations at Byron and Braidwood Stations ML010890050
04/05/2001 Additional Information Supporting the License Amendment Request to Permit Uprated Power Operations at Byron and Braidwood Stations ML011010101
04/16/2001 Additional Information Supporting the License Amendment Request to Permit Uprated Power Operations at Byron and Braidwood Stations ML011100181

To top of page

Amendment Information

Date Description Adams
Accession No.
05/04/2001 Amendment Nos. 119 for Byron 1 & 2 and 113 for Braidwood 1 & 2 - Issuance of Amendments; Increase in Reactor Power, Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2 (TAC Nos. MA9428, MA9429, MA9426, and MA9427) ML033040016

To top of page