2012 - Comanche Peak Nuclear Power Plant, Units 3 and 4 Application
On this page:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Applicant Documents
The following table provides access to the COL Application and other documents that Luminant submitted in 2012 for Comanche Peak Nuclear Power Plant, Units 3 & 4.
Date |
Description |
11/29/12 |
Preliminary Evaluation of the USAPWR Standard Plant Design for the Comanche Peak Units 3 and 4 Site |
08/29/12 |
Combined License Application Part 10, Update Tracking Report Revision 0 |
08/23/12 |
Extension of Regulatory Commitment |
06/11/12 |
Final Safety Analysis Report Revision 2, Update Tracking Report Revision 1 |
05/31/12 |
Part 4, Update Tracking Report Revision 0 |
05/31/12 |
Environmental Report Update Tracking Report Revision 0 |
05/21/12 |
Part 10, Update Tracking Report Revision 0 |
04/23/12 |
Notification of Completed Regulatory Commitments |
04/30/12 |
Notification of Completed Regulatory Commitments |
04/27/12 |
Integrated Hydrology Closure Plan |
04/16/12 |
Integrated Seismic Closure Plan |
01/30/12 |
Notification of Completed Regulatory Commitments |