Applicant Documents
The following table provides access to the COL Application and other documents that Luminant submitted in 2011 for Comanche Peak Nuclear Power Plant, Units 3 & 4.
Date |
Description |
12/20/11 |
Final Safety Analysis Report Update Tracking Report Revision 0 |
10/27/11 |
Notification of Completed Regulatory Commitments |
09/30/11 |
Integrated Seismic Closure Plan |
08/29/11 |
Comanche Peak Nuclear Power Plant, Units 3 and 4 Implementation of Licensing-Basis Freeze Point |
07/28/11 |
Notification of Completed Regulatory Commitments |
07/28/11 |
Request to Track Foreign Ownership, Control, or Domination as an Open Item |
06/30/11 |
Technical Specifications programs Implementation Methodology |
06/10/11 |
COLA Environmental Report Update Tracking Report Revision 6 (Chapters 1, 2, 3, 4, 5, 6 and 9) |
06/10/11 |
COLA Final Safety Analysis Report Update Tracking Report Revision 8 (FSAR chapters 1, 8, 9 and 14) |
06/01/11 |
COLA Part 4 Update Tracking Report Revision 2 |
05/31/11 |
COLA Final Safety Analysis Report Update Tracking Report Revision 7 (FSAR chapters 1, 2, 3, 8, 9, and 19) |
05/31/11 |
COLA Part 11 Update Tracking Report Revision 1, Quality Assurance Program Description |
05/17/11 |
COLA Final Safety Analysis Report Update Tracking Report Revision 6 |
05/25/11 |
Notification of Completed Regulatory Commitments |
05/25/11 |
Final Safety Analysis Report Update Tracking Report Revision 5 (FSAR Chapters 1, 2, 9, 12, and 14) |
05/09/11 |
COLA Part 10 Update Tracking Report Revision 2 |
04/19/11 |
Update to FSAR Subsection |
03/14/11 |
Re-Scheduled Regulatory Commitments |
03/11/11 |
Schedule Update |
02/28/11 |
Notification of Completed Regulatory Commitments |
NRC Documents
The following table provides access to documents and correspondence that the NRC has issued in 2011 in connection with its review of the COL application that Luminant submitted for Comanche Peak Nuclear Power Plant, Units 3 & 4.
Date |
Description |
05/13/11 |
Final Environmental Impact Statement for Combined Licenses (COLs) for Comanche Peak Nuclear Power Plant Units 3 and 4 |
03/02/11 |
Change to the Comanche Peak COL review schedule |