Clinch River Nuclear Site Application

Image of Clinch River Nuclear Site for illustrative purpose only
Graphic provided by Tennessee Valley Authority

Who:   Tennessee Valley Authority (TVA)
What:   Application for a Construction Permit for a small modular reactor (BWRX-300)
When:   April 2025 to present (date of application submittal)                                                                                         
February 2022 to April 2025 (pre-application)
Website:   https://www.tva.com/energy/technology-innovation/advanced-nuclear-solutions
Dashboard:   TVA Clinch River Dashboard

On this page:

Project Overview

The U.S. Nuclear Regulatory Commission (NRC) is currently engaged in review activities for Tennessee Valley Authority’s (TVA) construction permit application for the Clinch River Nuclear Site in Oak Ridge, Tennessee. This comes after the NRC’s issuance of the site’s Early Site Permit (ESP) in 2019.

Additional information on pre-application activities can be obtained from ADAMS using a search by docket number 99902056.

Additional information regarding the ESP can be found at Clinch River Nuclear Site Early Site Permit webpage.

To top of page

Topical Reports

Submittal Date Title Reference Status
08/25/2022 Clinch River, Topical Report Quality Assurance Program Description for New Nuclear Program Rev 0

Rev 1

Rev 2

Safety Evaluation Issued

Verification Letter for -A Version of QAPD Topical Report

To top of page

Public Meeting Materials and Meeting Summaries

Meeting Date Title
01/14/2025

Meeting between the U.S. Nuclear Regulatory Commission and Tennessee Valley Authority (TVA) regarding TVA’s request for clarification and alignment on the acceptability of TVA's approach to mapping of geology and geologic features during excavation activities at the Clinch River Nuclear Site

12/05/2024

Meeting between the U.S. Nuclear Regulatory Commission and Tennessee Valley Authority regarding Tennessee Valley Authority’s request for clarification on the following question: “When the Spent Fuel Pool and Reactor Cavity pool water volumes are cojoined during refueling operation (Pool divider gate removed), is the Regulatory Guidance provided in Regulatory Guide 1.13 and Standard Review Plans 9.1.2 and 9.1.4 applicable to the contiguous volume of water?

10/18/2023 Pre-Submittal Meeting for CRN PSAR Chapter 7 NRC Annotated Outline Audit Comments on Use of NRC I&C Design Review Guide
09/13/2023 TVA Clinch River CRN-1 Reactor Building Excavation
10/03/2022

Pre-Application Topics for Discussion

08/22/2022

Pre-Application Standing Meeting with Tennessee Valley Authority on Matters Related to the Development of a Construction Permit Application for the Clinch River Nuclear Site

05/02/2023 TVA CRN Strategy on Structural and Seismic Analyses based on existing Subsurface Investigation

To top of page

Audits and Audit Reports

Title Status/Report
Pre-Application Readiness Assessment Activities and Audit Plan for the Clinch River Nuclear Site Draft Application Complete
Construction Permit Readiness Assessment for TVA’s Clinch River Nuclear Site (Preliminary Safety Analysis Report)

Safety Review Summary Report

Enclosure 1 to Summary Report

Construction Permit Readiness Assessment for TVA’s Clinch River Nuclear Site (Environmental Report)

Environmental Report Summary Report

Enclosure to Summary Report

To top of page

Environmental Review

The NRC staff prepared a draft SEIS (ML25261A214) documenting its environmental review. Based on the environmental review, the NRC made a preliminary determination that the proposed actions would not significantly impact the quality of the human environment. The NRC is offering a 45-day public comment period, ending on December 22, 2025. Methods for submitting comments are included in the federal register notice.

After consideration of the public comments, the NRC staff will make a final determination regarding the environmental impacts for the construction permit application for the Clinch River Nuclear Site. A final SEIS will be issued with the NRC’s determination.

On April 6, 2026, the NRC as the lead agency, and the U.S. Army Corp of Engineers as a cooperating agency, completed a SEIS of the proposed Federal actions related to a construction permit at the Clinch River Nuclear Site. The SEIS may be located in ADAMS at ML26035A285. A Notice of Availability was published in the Federal Register at ML26056A096 (91 FR 17312).

To top of page

Exemption Requests

Title Status/Report
Request for Exemption from Certain Requirements of 10 CFR 2.101(a)(5) Granted
Request for Exemption from 10 CFR 50.10(c) to Allow Excavation at the Clinch River Nuclear Site Prior to Construction Permit Issuance Granted
Final Environmental Assessment for the Clinch River Nuclear Site Exemption Request Complete
Clinch River Exemption Request EA Issuance Letter Complete
Letter to Tennessee Valley Authority transmitting Exemption Allowing Early Excavation at the Clinch River Nuclear Site Complete
Letter to Tennessee Valley Authority - NRC Acceptance of Exemption Request on Early Excavation at the Clinch River Nuclear Site Complete
NRC's Response to TVA's Request for Regulatory Interpretation of the Applicability of 10 CFR 50.10(a)(1) to the Permanent Backfill underneath the Power Block Foundations Complete
Letter to Tennessee Valley Authority - Geologic and Geotechnical Audit Plan, Exemption for Early Excavation at the Clinch River Nuclear Site Complete

To top of page

Key Milestones

Milestones Completion Date
Actual - A
Target - T
Environmental Report Submitted (Part One) April 28, 2025 – A
Preliminary Safety Analysis Report Submitted (Part Two) May 20, 2025 – A
Environmental Report Acceptance Review Completion (Decision Letter Issued) June 12, 2025 – A
Preliminary Safety Analysis Report Acceptance Review Completion (Decision Letter Issued) July 11, 2025 – T; July 9, 2025  – A
Review Schedule Established/Schedule Letter Issued to Applicant (Schedule & Resource Letter) July 25, 2025  – A
Safety Review* (Milestones Letter) November 2026
Draft Safety Evaluation1 (ML26005A247) February 2026 - T; January 16, 2026 - A
Advance Safety Evaluation Report2 October 2026 - T
Final Safety Evaluation Report November 2026 - T
Environmental Review* April 2026
Complete Draft SEIS Sections September 18, 2025  – A
Finalize Draft SEIS and Related Activities December 19, 2025 – T, November 7, 2025 – A
Comment Responses and Final SEIS March 2026 – T, February 27, 2026 – A
Finalize Final SEIS and Related Activities April 2026 – T, April 6, 2026 – A
Hearing TBD
Construction Permit Decision TBD

Notes:
1. Safety Evaluation sections drafted and information gaps identified.
2. Advanced Safety Evaluation Report without open items.

 

To top of page

Contacts

Contacts for Clinch River Nuclear Site
Safety Project Manager (co-lead) Allen Fetter
Safety Project Manager (co-lead) Ricky Vivanco
Environmental Project Manager Madelyn Nagel
Contact a Public Affairs Officer