Pioneer Units 1 and 2 Limited Work Authorization Application

Image
Pioneer Units 1 and 2 Graphic


Graphic provided by SMR, LLC

Who:   Palisades SMR, LLC
What:   Pioneer Units 1 and 2 Phased Construction Permit Application - Limited Work Authorization
When:   December 31, 2025 (date of application submittal) to present
Website:   https://holtecinternational.com/products-and-services/smr/
Dashboard:   pending

On this page:

Project Overview

The U.S. Nuclear Regulatory Commission (NRC) is currently engaged in review activities for the first part of a phased construction permit application, including a limited work authorization request, from Palisades SMR, LLC, for a dual-unit SMR-300 plant located at the Palisades Energy Center in Covert, Michigan.  The units are individually named Pioneer Unit 1 and Pioneer Unit 2.

Application docket numbers: 05000616 and 05000617.

Additional information on pre-application activities can be obtained from ADAMS using a search by docket number 99902049.

To top of page

Key Events and Milestones

Milestones Completion Date
Actual - A
Target - T
SMR, LLC, Submittal of Pioneer Units 1 and 2 Limited Work Authorization Application (Project No. 99902049) (ML25365A983), received. December 31, 2025 - A
Federal Register Notice of Receipt and Availability; SMR, LLC; Pioneer Units 1 and 2; Phased Construction Permit Application – Limited Work Authorization (91 FR 2803), issued. January 22, 2026 - A
Letter to SMR, LLC, Acceptance Review Results for a Limited Work Authorization Application for SMR-300 Pioneer Units 1 and 2 (ML26A041A223), issued. February 13, 2025 - A
Federal Register Notice of Pioneer Units 1 and 2 Limited Work Authorization Application Acceptance and Opportunity for Hearing (91 FR 9892), issued. February 27, 2026 - A
Audit Plan for the Regulatory Audit of Pioneer Units 1 and 2 Limited Work Authorization Application, issued. (ML26082A164) March 27, 2026 - A
Draft Safety Evaluation Report (with information gaps) August 31, 2026 – T
Draft Environmental Impact Statement October 31, 2026 – T
Advanced Safety Evaluation Report (without open items) January 31, 2027 – T
Final Safety Evaluation Report March 31, 2027 – T
Final Environmental Impact Statement March 31, 2027 – T

To top of page

Contacts

Contacts for Pioneer Units 1 and 2 LWA Application
Lead Safety Project Manager Victoria Huckabay
Safety Project Manager Andrea Johnson
Lead Environmental Project Manager Robert Hoffman
Environmental Project Manager Laura Willingham