United States Nuclear Regulatory Commission - Protecting People and the Environment
Home > Nuclear Materials > Uranium Recovery > Cost Projections for Uranium Recovery Licensing Actions

Cost Projections for Uranium Recovery Licensing Actions

Cost Projection Table

The table below offers resource estimates for many of the common licensing and oversight activities in the area uranium recovery. This information is being offered to enhance stakeholder awareness of the costs associated with these activities. It will also aid licensees and applicants in the planning and budgeting of future applications. This information was developed through a sampling of licensing and oversight actions that were completed in the past few years. The data provided in the table below are estimates. The actual costs may vary depending on the specific circumstances. The NRC encourages licensees and applicants to engage early in the process when submitting new actions. Licensees are encouraged to work with their NRC project manager to discuss details of any specific application. The table will be updated on a biennial basis.

Major Licensing Action Billed Number of NRC Direct Staff Hours:  Low Estimate of Level of Effort Billed Number of NRC Direct Staff Hours:  High Estimate of Level of Effort Billed Number of NRC Direct Staff Hours:  Average Estimate of Level of Effort Billed Contractor Costs:  Low Estimate of Level of Effort Billed Contractor Costs: High Estimate of Level of Effort Billed Contractor Costs: Average Estimate of Level of Effort
COST ESTIMATES FOR DECOMMISSIONING AND LOW LEVEL WASTE BUSINESS LINE
Uranium Recovery New Facility 7,410 9,607 8,352 $236,858 $1,706,097 $759,561
Uranium Recovery License Renewal 2,396 4,779 3,588 $91,271 $96,749 $94,010
Uranium Recovery Expansion of Existing Facility Expansions With An Increase in Production Area* 954 5,315 3,135 $0 $475,715 $237,857.50
Uranium Recovery Expansions With No Increase in Production Area** 123 396 260 $0 $0 $0
Uranium Recovery Financial Assurance Review 31 187 75 $0 $0 $0
Uranium Recovery  Routine Inspections 119 252 190 $0 $0 $0

To top of page

* This category is for expansions where new production areas, that were not considered in the initial evaluation, are added to the license. Example would be addition of new wellfields and satellite facilities adjacent to the existing license. Second example would be expanding to recover uranium from a different aquifer.

** This category is for expansions where the production area does not change, but the licensee seeks to increase capacity. Examples of these types of actions would include: adding or modifying the capacity of a dryer, or increasing the allowable flow rate of the processing plant.

To top of page

Page Last Reviewed/Updated Monday, September 25, 2017