Communications Regarding Increased Oversight at Pilgrim Nuclear Power Plant

On this page:

Assessment

No. Title Date Issued
1. 2014 Annual Assessment Letter (Degraded Cornerstone) 03/04/2015
2. Mid-Cycle Assessment Letter For Pilgrim Nuclear Power Station (Report 05000293/2015005) 09/01/2015
3. Pilgrim Nuclear Power Station - NRC Integrated Inspection Report 3rd Quarter 05000293/2015003 (see Sect 4OA5 for quarterly assessment) 11/12/2015
4. 2015 Annual Assessment Letter (Repetitive Degraded Cornerstone) 03/02/2016
5. Pilgrim Nuclear Power Station - NRC Integrated Inspection Report 1st Quarter 05000293/2016001 (see Sect 4OA5 for quarterly assessment) 05/12/2016
6. Mid-Cycle Assessment Letter For Pilgrim Nuclear Power Station (Report 05000293/2016005) 08/31/2016
7. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 3rd Quarter 05000293/2016003 (see Sect 4OA5 for quarterly assessment) 11/14/2016
8. Annual Assessment Letter for Pilgrim Nuclear Power Station (Report 05000293/2016006) 03/01/2017
9. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017001 (see Sect 4OA5 for quarterly assessment) 05/15/2017
10. Quarterly Assessment and Updated Inspection Plan for Pilgrim Nuclear Power Station (Report 05000293/2017005) 08/28/2017
11. Annual Assessment Letter for Pilgrim Nuclear Power Station (Reports 05000293/2017006, 05000293/2017402, and 05000293/2017501) 02/28/2018
12. Pilgrim Nuclear Power Station - Assessment Follow-up Letter and Updated Inspection Plan (Inspection Report 05000293/2018005) 08/30/2018
13. Annual Assessment Letter For Pilgrim Nuclear Power Station (Report 05000293/2018006) And Confirmatory Action Letter Closure 03/04/2019

To top of page

Inspection

No. Title Date Issued
1. Pilgrim Nuclear Power Station – NRC 95002 Supplemental Inspection Report 05000293/2014008 And Assignment Of Two Parallel White Performance Indicator Inspection Findings 01/26/2015
2. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 1st Quarter 05000293/2015001 (1 NCV) 05/11/2015
3. Pilgrim Nuclear Power Station – NRC Special Inspection Report 05000293/2015007; And Preliminary White Finding 05/27/2015
4. Pilgrim Nuclear Power Station – NRC 95002 Supplemental Follow-Up Inspection Report 05000293/2015009 06/18/2015
5. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 2nd Quarter 05000293/2015002 (4 NCV, 1 FIN) 08/11/2015
6. Final Significance Determination For A White Finding And Notice Of Violation - Inspection Report No. 05000293/2015011 – Pilgrim Nuclear Power Station 09/01/2015
7. Biennial PI&R Inspection w/ CAP Marginally Effective (2 NOV, 2 NCV) 10/01/2015
8. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 3rd Quarter 05000293/2015003 (4 NCV, 1 SLIV) 11/12/2015
9. Security Baseline – Access, Equipment and Training (5 NCV) 12/01/2015
10. Triennial Fire Protection Inspection (1 NCV) 12/21/2015
11. Pilgrim Nuclear Power Station, NRC Inspection Report No. 05000293/2016010 And NRC Office Of Investigations Report NO. 1-2015-005 02/10/2016
12. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 4th Quarter 05000293/2015004 (4 NCV) 02/11/2016
13. Pilgrim Nuclear Power Station – IP 95003 Supplemental Inspection Report (Phase A) 05000293/2016008 (1 NCV) 02/29/2016
14. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 1st Quarter 05000293/2016001 05/12/2016
15. Pilgrim Nuclear Power Station – IP 95003 Supplemental Inspection Report (Phase B) 05000293/2016008 (1 NCV) 05/23/2016
16. Pilgrim Nuclear Power Station – NRC Permanent Plant Modifications Inspection Report 05000293/2016007 07/06/2016
17. Pilgrim Nuclear Power Station – Temporary Instruction 2515/191 Inspection Report 05000293/2016013 07/07/2016
18. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 2nd Quarter 05000293/2016002 (1 NCV) 08/10/2016
19. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 3rd Quarter 05000293/2016003 (4 NCV) 11/14/2016
20. Pilgrim Nuclear Power Station – Evaluated Emergency Preparedness Exercise Inspection Report 05000293/2016502 12/20/2016
21. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2016004 and Independent Spent Fuel Storage Installation Report 07201044/2016001 02/14/2017
22. Pilgrim Nuclear Power Station – Problem Identification and Resolution Sample Inspection Report 05000293/2016404 (3 NCV) 04/07/2016
23. Pilgrim Nuclear Power Station – Supplemental Inspection Report (Inspection Procedure 95003 Phase 'C') 05000293/2016011 and Preliminary Greater-than-Green Finding (7 NCV, 2 FIN, 1 SLIV) 05/10/2017
24. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017001 (2 NCV, 1 SLIV) 05/15/2017
25. Pilgrim Nuclear Power Station – Initial Operator Licensing Examination Report 05000293/2017301 05/15/2017
26. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017002 08/14/2017
27. Pilgrim Nuclear Power Station – Problem Identification and Resolution Sample Inspection Report 05000293/2017405 (Letter Only) 09/05/2017
28. Pilgrim Nuclear Power Station – Design Bases Assurance Inspection Report 05000293/2017007. 09/28/2017
29. Pilgrim Nuclear Power Station – Baseline Security Inspection Report 05000293/2017403, (Letter Only). 10/12/2017
30. Pilgrim Nuclear Power Station – Material Control and Accounting Program Inspection Report 05000293/2017404 (Letter Only). 10/17/2017
31. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017003. 11/14/2017
32. Pilgrim Nuclear Power Station – NRC Security Inspection Report 05000293/2017201. 11/21/2017
33. Pilgrim Nuclear Power Station – Problem Identification and Resolution Inspection Report 05000293/2017009. 12/21/2017
34. Pilgrim Nuclear Power Station – Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2017010. 02/01/2018
35. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017004 02/14/2018
36. Pilgrim Nuclear Power Station – NRC Investigation Report No. 1-2017-015. 02/27/2018
37. Pilgrim Nuclear Power Station – NRC Investigation Report No. 1 -2017-011 and Notice of Violation 02/28/2018
38. Pilgrim, and Independent Spent Fuel Storage Installation – Radioactive Effluent Release Report. 02/28/2018
39. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2018001 05/14/2018
40. Pilgrim Nuclear Power Station – Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018010. 06/13/2018
41. Pilgrim Nuclear Power Station - Baseline Security Inspection Report 05000293/2018411 09/27/2018
42. Pilgrim Nuclear Power Station - Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018011 10/09/2018
43. Pilgrim Nuclear Power Station – Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018012 11/01/2018
44. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2018003 and Independent Spent Fuel Storage Installation Inspection Report 07201014/2018001 11/13/2018
45. Pilgrim Nuclear Power Station – Triennial Fire Protection Inspection Report 05000293/2018015 11/21/2018
46. Pilgrim Nuclear Power Station – Evaluated Emergency Preparedness Exercise Inspection Report 05000293/2018501 12/06/2018
47. Pilgrim Nuclear Power Station – Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018013. 01/23/2019
48. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2018004 and Independent Spent Fuel Storage Installation Report 07201044/2018201 02/13/2019

To top of page

Other

No. Title Date Issued
1. Inspection Approach/Phase Schedule Communication Letter 12/18/2015
2. OEDO-15-00479: David Lochbaum and Others 2.206 Petition Regarding Pilgrim's Current License Basis for Flooding Acknowledgement Letter (CAC No. MF6460) 02/11/2016
3. Pilgrim Nuclear Power Station -- Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 03/03/2016
4. NRC Notice of Violation (NRC Investigation Report No. 1-2015-005) (Fire watch NOV) 04/11/2016
5. NRC Annual Assessment Meeting Summary 04/13/2016
6. NRC Annual Assessment Meeting Presentation 04/13/2016
7. Entergy Annual Assessment Meeting Presentation 04/13/2016
8. 2016 AARM Meeting Agenda 06/02/2016
9. 2016 AARM Slides 06/02/2016
10. 2016 AARM Transcript 06/02/2016
11. 2016 AARM Meeting SRM 06/02/2016
12. LER 2016-001-00 06/09/2016
13. LTR-15-0319-1, LTR-15-0375-1 – Response Letter 2.206 Petition Re: Pilgrim Severe Weather Emergency Preparedness 06/22/2016
14. LER 2016-002-00 06/30/2016
15. Pilgrim Extension Request for Order EA-13-109 Schedule Requirements 07/13/2016
16. LER 2016-003-00 07/25/2016
17. LER 2016-004-00 07/25/2016
18. Interim Staff Response to Reevaluated Flood Hazards Submitted in Pilgrim Response to the 10CFR50.54(f) Information Request 08/03/2016
19. PNPS Letter – Request for Deferral of Beyond-DBE Flooding Actions 08/18/2016
20. PNPS Letter – Request for Deferral Beyond-DBE Seismic Actions 08/18/2016
21. LER 2016-002-001 Supplement 08/18/2016
22. Entergy Announces Pilgrim Readiness for Phase C Inspection 08/31/2016
23. PNP Ltr 2.16.057 – LER 2016-004 Retraction 09/09/2016
24. Formal Notification of Phase C IP 95003 Inspection dates 10/13/2016
25. LER 2016-005-00 11/04/2016
26. LER 2016-006-00 11/04/2016
27. Pilgrim Response to NRC Generic Letter 2016-01 , "Monitoring of Neutron-Absorbing Material in Spent Fuel Pools" 11/03/2016
28. Licensee Event Report 2016-007-00 – Pilgrim Nuclear Power Station Regarding Manual Reactor Scram Due To Feedwater Regulating Valve Malfunction 11/04/2016
29. NRC Response to Town of Plymouth regarding Pilgrim 12/13/2016
30. JRWA Letter Expressing Concerns About Flooding Risks at Pilgrim Nuclear Power Station 12/26/2016
31. Letter from Massachusetts Attorney General Requesting NRC meet with public to discuss inadvertently released email 01/04/2017
32. Licensee Event Report 2016-009-00 – HPCI Declared Inoperable Due to Failure of IST Surveillance Test 01/05/2017
33. Letter from Chairman responding to Massachusetts Attorney General Request for NRC to meet with public to discuss inadvertently released email 01/11/2017
34. Letter to Mary Lampert, Director, Pilgrim Watch, from Stephen Koenick, LPL1, DORL/NRR Re: Pilgrim Nuclear Power Station - Liability and Holtec Guarantees 01/17/2017
35. Notice of Category 3 Public Meeting - Preliminary Findings and Status of 95003 Inspection at Pilgrim Nuclear Power Station 01/19/2017
36. Pilgrim Watch response to Stephen Koenick January 7 reply to our October 27, 2016 email regarding liability and Holtec guarantees at Pilgrim Nuclear Power Station 01/24/2017
37. Press Release-I-17-002: NRC Plans Plymouth Public Meeting to Discuss Reviews at Pilgrim Nuclear Power Plant 01/30/2017
38. Pilgrim Nuclear Power Station – Petition Received at Pilgrim 95003 Public Meeting from Pilgrim Legislative Advisory Coalition 01/31/1017
39. LTR-16-0609 NRC Response to Senator Viriato M. deMacedo, et al, Plymouth and Barnstable District, Massachusetts Senate, letter regarding concern about the current state of Pilgrim Nuclear Power Station 02/01/2017
40. Pilgrim Nuclear Power Station – Request for Approval of Certified Fuel Handler Training and Retraining Program 02/02/2017
41. Pilgrim Nuclear Power Station – Request for Exemption from Specific Provisions in 10 CFR 73.55 02/07/2017
42. Pilgrim Nuclear Power Station – ISFSI Radioactive Effluent Release Report for 2016 02/10/2017
43. LER 16-010-00 for Pilgrim Nuclear Power Station Regarding MSIV Inoperability Led to a Condition Prohibited by the Plant's Technical Specifications 02/13/2017
44. Status of Decision on Petitioners Request for Hearing Regarding Entergy's Request for Extension to Comply with NRC Order EA-13-109 02/17/2017
45. Region I/DRP Response to James R. Garb, Pilgrim Legislative Advisory Coalition re: Degraded Safety Status of the Pilgrim Nuclear Power Station 02/21/2017
46. NRC Response to Jones River Watershed Association Letter Dated December 26, 2016 to the NRC on Pilgrim Nuclear Power Station 02/27/2017
47. 01/31/2017 – Summary of Category 3 Public Meeting - Preliminary Findings and Status of 95003 Inspection at Pilgrim 02/28/2017
48. NRC Response to Petition Received at Pilgrim 95003 Public Meeting from Pilgrim Legislative Advisory Coalition 03/06/2017
49. Pilgrim Nuclear Power Station – Notice of Public Meeting (Annual Assessment and 95003 Inspection Exit Meeting) - 3/21/2017 03/10/2017
50. Press Release-I-17-005: NRC to Hold Pilgrim Nuclear Plant Public Exit Meeting for Inspection, Annual Assessment Discussion 03/14/2017
51. LER 17-001-00 for Pilgrim Regarding Reactor Building Isolation Dampers Failed to Isolate 03/15/2017
52. Pilgrim Nuclear Power Station - Supplement to Requests for Relief from ASME Section XI Volumetric Examination Requirements - Fourth 10-Year Interval 03/16/2017
53. 3/21/2017 – Annual Assessment/95003 Inspection Exit Meeting for Pilgrim Nuclear Power Station - Speaker Sign-Up Sheets 03/21/2017
54. Statement from the Office of U.S. Senator Elizabeth Warren – NRC Annual Meeting, Plymouth, MA 03/21/2017
55. Statement of Congressman Keating – NRC Annual Assessment Meeting for PNPS - March 21, 2017. 03/21/2017
56. Statement of Senator Edward J. Markey – NRC Annual Assessment Meeting for Pilgrim Nuclear Power Station - March 21, 2017 03/21/2017
57. 3/21/2017 – Annual Assessment & 95003 Exit Meeting for Pilgrim Nuclear Power Station – Entergy Presentation Slides 03/21/2017
58. 3/21/2017 – Annual Assessment & IP 95003 Exit Meeting for Pilgrim Nuclear Power Station – NRC Presentation Slides 03/21/2017
59. 03/21/2017 Transcript of Annual Assessment/95003 Inspection Exit Meeting for Pilgrim Nuclear Power Station 03/21/2017
60. 3/21/2017 – Annual Assessment/95003 Inspection Exit Summary Meeting for Pilgrim Nuclear Power Station 03/21/2017
61. Pilgrim, License Amendment Request - Cyber Security Plan Implementation Schedule 03/30/2017
62. Nuclear Property Damage Insurance [10 CFR 50.54(w)(3)] 03/30/2017
63. Entergy Nuclear Operations, Inc. – Decommissioning Funding Status Report per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v). 03/31/2017
64. Pilgrim Nuclear Power Station - Issuance of Relief Request Nos. PNPS-ISI-004 and PNPS-ISI-005 for Relief from American Society of Mechanical Engineers Code, Section XI, Volumetric Examination Requirements. 04/03/2017
65. Commission Memorandum and Order regarding PW request for Hearing related to Fukushima Orders (CLI-17-06). 04/06/2017
66. Notification for Information Only – Pilgrim Deviation from EPRI Report 3002000091, Rev. 1 04/10/2017
67. OEDO-15-00479 – 2.206 Petition regarding Pilgrim current licensing basis for flooding – 60 DAY STATUS (CAC NO. MF6460) 04/10/2017
68. Pilgrim Nuclear Power Station – Approval of Certified Fuel Handler Training and Retraining Program (CAC No. MF9275) 04/12/2017
69. Pilgrim Nuclear Power Station – NRC Response to Request for Deferral of Actions Related to Beyond-Design-Basis Seismic and Flooding External Events. 04/17/2017
70. Pilgrim Nuclear Power Station – Relaxation of the Schedule Requirements for Order EA-13-109: Order Modifying Licenses With Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions. 04/17/2017
71. 3/21/2017 – Annual Assessment/95003 Inspection Exit Summary Meeting for Pilgrim Nuclear Power Station. 04/18/2017
72. Pilgrim Nuclear Power Station – Relief Requests PNPS-ISI-001 and PNPS-ISI-002, Relief from ASME Code Volumetric Examination Requirements for the Fourth 10-Year Inservice Inspection Interval (CAC Nos. MF8092 and MF8093) 05/12/2017
73. Pilgrim Nuclear Power Station – Letter, Request for Exemption from Specific Provisions in 10 CFR 73.55 Related to Suspension of Security Measures for Licensed Senior Operator or Certified Fuel Handler (CAC No. MF9274) 05/16/2017
74. Pilgrim – Fuel Cycle 22, Core Operating Limits Report, Revision 37 05/12/2017
75. Pilgrim – Annual Radiological Environmental Operating Report for January 1 through December 31, 2016 05/12/2017
76. Pilgrim – Annual Radioactive Effluent Release Report for January 1 through December 31, 2016 05/12/2017
77. OEDO-15-00479: Federal Register Notice re: 2.206 Petition Regarding Pilgrim's Current License Basis for Flooding (CAC No. MF6460) 02/11/2016
78. Supplemental to Technical Specifications Proposed Change – Administrative Controls for Permanently Defueled Condition 05/25/2017
79. LER 17-002-00 for Pilgrim Regarding Isolation of HPCI 05/25/2017
80. LER 17-003-00 for Pilgrim Nuclear Power Station Regarding Pressure Suppression Pool Declared Inoperable Due to High Water Level 05/25/2017
81. LER 17-004-00 for Pilgrim Nuclear Power Station Regarding Secondary Containment Testing Led to Loss of Safety Function to Both Trains of Standby Gas Treatment System 06/02/2017
82. LER 17-005-00 for Pilgrim Regarding 10 CFR 50, Appendix J, Option B, Leak Rate Criteria Exceeded 06/07/2017
83. LER 17-006-00 for Pilgrim Nuclear Power Station Regarding Source Range Monitor Inoperable During Fuel Movement 06/13/2017
84. LER 16-010-01 for Pilgrim Nuclear Power Station re MSIV Inoperability 06/14/2017
85. LER 17-007-00 for Pilgrim Regarding Potential Inoperability of Safety Relief Valve 3A 06/22/2017
86. Pilgrim – NRC Investigation Report 1-2016-011 06/28/2017
87. Pilgrim Nuclear Power Station's Sixth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order No. EA-13-109) 06/30/2017
88. Pilgrim Nuclear Power Station – Issuance of Amendment No. 246, Revise Administrative Controls Section of Technical Specifications to Change Staffing and Training Requirements for Permanently Defueled Condition (CAC No. MF9304) 07/10/2017
89. Pilgrim Nuclear Power Station: Regulatory Conference Presentation 07-13-17 07/13/2017
90. Press Release-I-17-026: NRC to Hold Regulatory Conference with Entergy Regarding Apparent Violation at Pilgrim Nuclear Power Plant 07/12/2017
91. Pilgrim Nuclear Power Station Recovery Plan 07/28/2017
92. Confirmatory Action Letter – Pilgrim Nuclear Power Station 08/02/2017
93. Press Release-I-17-028: NRC Issues Confirmatory Action Letter to Pilgrim Nuclear Power Plant on Safety Performance Improvement Commitments 08/02/2017
94. LER 17-008-00 for Pilgrim re 480V Bus B6 Auto Transfer Function Degraded Due to Time Delay Relay Failure 06/30/2017
95. Pilgrim Nuclear Power Station – Final Significance Determination For A Green Finding And Results Of Regulatory Conference – Inspection Report 05000293/2017008 08/09/2017
96. LER 17-010-00 for Pilgrim re Air Accumulation Creates Small Void in Core Spray Discharge Piping 08/07/2017
97. LER 17-009-00 for Pilgrim Nuclear Power Station Regarding Potential Primary Containment System lnoperability Due to Relay Concerns 07/17/2017
98. LER 17-001-01 for Pilgrim Nuclear Power Station Regarding Reactor Building Isolation Dampers Failed to Isolate 07/17/2017
99. Requalification Program Inspection – Pilgrim Nuclear Power Station 08/22/2017
100. Pilgrim Nuclear Power Station, Transmittal of Reply to a Notice of Violation, EA-17-030 08/11/2017
101. LER 17-011-00 for Pilgrim Nuclear Power Station Regarding Simultaneously Opened Reactor Building Airlock Doors Caused Loss of Secondary Containment 08/15/2017
102. OEDO-15-00479 – E-mail to David Lochbaum Re. 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding; 60-Day Status Report (CAC NO. MF6460; EPID L-2015-CRS-0002) 10/10/2017
103. Presentations on Reactor Decommissioning at MA NDCAP at Plymouth MA Public Meeting Oct 18, 2017 10/23/2017
104. LER 17-008-01 for Pilgrim Nuclear Power Station Regarding Supplement to 480V Bus B6 Auto Transfer Function Degraded Due to Time Delay Relay Failure 11/17/2017
105. LER 17-003-01 for Pilgrim Nuclear Power Station Regarding Supplement to Suppression Pool Declared Inoperable Due to High Water Level 11/30/2017
106. LER 17-012-00 for Pilgrim Nuclear Power Station Regarding Start-Up Transformer Degraded Voltage Relay Found Outside Technical Specification Limit 11/30/2017
107. Pilgrim Nuclear Power Station's Seventh Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions. 12/8/2017
108. OEDO-15-00479 – 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding – 60-Day Status Report (CAC NO. MF6460; EPID L-2015-CRS-0002) 12/11/2017
109. LER 17-007-01 for Pilgrim Nuclear Power Station Regarding Supplement to Potential Inoperability of Safety Relief Valve 3A 01/12/2018
110. LER 17-009-01 for Pilgrim Nuclear Power Station Regarding Supplement to Potential Primary Containment System Inoperability Due to Relay Concerns 01/18/2018
111. LER 17-013-00 for Pilgrim Nuclear Power Station Regarding Reportable Conditions Involving Standby Gas Treatment System and Secondary Containment lnoperability Not Reported During the Previous Three Years 02/12/2018
112. OEDO-15-00479 – 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding – 60-Day Status Report (CAC No. MF6460; EPID L-2015-CRS-0002) 02/12/2018
113. 02-14-18 Acknowledgement Letter to Senators Warren, Markey and Keating Regarding the Pilgrim Plant 02/21/2018
114. 03/27/2018 – Notice of Category 1 Public Meeting – Annual Assessment Meeting for Pilgrim Nuclear Power Station 03/14/2018
115. Press Release-I-18-003: NRC Staff to Conduct Public Meeting to Discuss 2017 Performance of Pilgrim Nuclear Power Plant 03/26/2018
116. Response to Request for Information Senator Elizabeth Warren, Senator Edward Markey, and Representative William Keating Letter dated February 12, 2017 (Enclosure) 03/26/2018
117. LER 2018-001-00 for Pilgrim Nuclear Power Station Regarding Manual Reactor Scram Due To Loss of One Offsite Transmission Line 03/28/2018
118. LER 2018-002-00 for Pilgrim re: Diesel Generator A Inoperable, a Condition Prohibited by the Plant Technical Specifications 03/28/2018
119. LER 2018-003-00 for Pilgrim, Target Rock Relief Valve Pilot Assembly Failed As-Found Lift Test, a Condition Prohibited by Plant Technical Specifications 04/11/2018
120. Pilgrim, License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition 01/12/2018
121. Response to Request for Supplemental Information Regarding Generic Letter 2016-01, "Monitoring of Neutron Absorbing Materials in the Spent Fuel Pools" for Grand Gulf Nuclear Station Unit 1 and Pilgrim Nuclear Power Station. 02/08/2018
122. Revise the Pilgrim Emergency Plan to Address the Permanently Defueled Condition 02/20/2018
123. Pilgrim Nuclear Power Station – NRC Investigation Report No. 1 -2017-011 and Notice of Violation 02/27/2018
124. Pilgrim, and Independent Spent Fuel Storage Installation –  Radioactive Effluent Release Report 02/28/2018
125. FEMA Review Requested Of Revision To The Pilgrim Nuclear Power Station Emergency Plan To Address The Permanently Defueled Condition. 03/08/2018
126. Confirmatory Order, NRC Inspection Report 05000416/2017014, and NRC Investigation Reports 4-2016-004 and 4-2014-021 03/13/2018
127. Press Release-IV-18-002: NRC Issues Confirmatory Order to Entergy. 03/14/2018
128. Pilgrim Nuclear Power Station Notification of Changes to Comprehensive Recovery Plan and Area Action Plan Action Completion Dates. 03/14/2018
129. 03/27/2018 – Notice of Category 1 Public Meeting – Annual Assessment Meeting for Pilgrim Nuclear Power Station 03/14/2018
130. Response to Request for Information Senator Elizabeth Warren, Senator Edward Markey, and Representative William Keating  Letter dated February 12, 2017 (Enclosure) 03/19/2018
131. Pilgrim, Anchor Darling Double Disc Gate Valve Information and Status. 04/16/2018
132. 04-25-18 FEMA Letter to NRC, entitled "FEMA Review of Revision to Pilgrim Nuclear Power Station Emergency Plan to Address the Permanently Shutdown Condition 04/25/2018
133. Statement of Congressman William R. Keating – NRC Annual Assessment Meeting for Pilgrim Nuclear Power Station – 03/27/2018 05/07/2018
134. 03/27/2018 – Transcript of Annual Assessment Meeting for Pilgrim Nuclear Power Station. 05/07/2018
135. 03/27/2018 – Annual Assessment Meeting for Pilgrim Nuclear Power Station – Entergy Presentation Slides. 05/07/2018
136. Statement of Senator Edward J. Markey – NRC Annual Assessment Meeting for Pilgrim Nuclear Power Station – 03/27/2018. 05/07/2018
137. 03/27/2018 – Annual Assessment Meeting for Pilgrim Nuclear Power Station – NRC Presentation Slides. 05/07/2018
138. Letter to Power Reactor Licensees – U.S. Nuclear Regulatory Commission Analysis of Licensees' 2017 Decommissioning Funding Status Reports. 05/08/2018
139. 03/27/2018 – Summary of Annual Assessment Meeting for Pilgrim Nuclear Power Station 05/09/2018
140. LER 2018-004-00 for Pilgrim Nuclear Power Station, Automatic Emergency Diesel Generator System Actuation Caused By Loss of Offsite Power. 05/14/2018
141. LER 2017-013-01 for Pilgrim Nuclear Power Station re Supplement to Reportable Conditions Involving Standby Gas Treatment System and Secondary Containment Inoperability Not Reported During the Previous Three Years. 05/14/2018
142. Pilgrim, Submittal of Annual Radiological Environmental Operating Report for January 1 through December 31, 2017 05/15/2018
143. Pilgrim Nuclear Power Station – Annual Radioactive Effluent Release Report for January 1 through December 31, 2017. 05/15/2018
144. Responses to Request for Information – Senator Edward Markey Letter dated April 23, 2018 (Enclosure) 05/29/2018
145. Pilgrim Nuclear Power Station – Reply to Notice of Violation (NRC Investigation Report No. 1-2017-011) 05/30/2018
146. Entergy Letter dated June 1, 2018 to David Lew regarding Pilgrim Notification of Changes to Comprehensive Recovery Plan 06/01/2018
147. Pilgrim Extent of Condition Review in Response to Findings Associated with Inspection 95003:  Evaluation of NRC Assessment and Inspection Processes at Pilgrim Nuclear Power Station. 06/06/2018
148. Revision to Confirmatory Action Letter – Pilgrim Nuclear Power Station. 06/07/2018
149. Pilgrim 95003 Evaluation and Corrective Actions Memorandum dated June 7, 2018 06/07/2018
150. Pilgrim 95003 Evaluation – Memorandum regarding Licensee Event Report Safety Significance Review in Response to Findings Associated with Inspection Procedure 95003; Evaluation of NRC Assessment and Inspection Processes at Pilgrim Nuclear Power Station 06/07/2018
151. Inspection Procedure 95003:  Evaluation Of NRC Assessment And Inspection Processes At Pilgrim Nuclear Power Station. 06/11/2018
152. 2018 AARM Meeting Agenda 06/19/2018
153. 2018 AARM Slides 06/19/2018
154. 2018 AARM Transcript 06/19/2018
155. 2018 AARM Meeting SRM 06/19/2018
156. Pilgrim Nuclear Power Station – Baseline Security Inspection Report 05000293/2018410 (Letter Only). 06/20/2018
157. Pilgrim Nuclear Power Station – Retraction of Licensee Event Report 2018-002-00, Diesel Generator A Inoperability, a Condition Prohibited by the Plant Technical Specifications. 06/21/2018
158. Pilgrim Nuclear Power Station – Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E. 07/03/2018
159. 08/28/18 – Letter to Representative William Keating from Chairman Svinicki responds to his letter regarding the Proposed Sale of Pilgrim Nuclear Power Station by Entergy Nuclear Operations Inc. to a Subsidiary of Holtec International 09/05/2018
160. Pilgrim Nuclear Power Station - NRC License Transfer Application 9/25/2018 Pre-Submittal Meeting Presentation Slides 09/19/2018
161. Pilgrim Nuclear Power Station - Letter to Pilgrim Watch and Town of Duxbury Nuclear Advisory Committee Related to Questions Regarding Planned License Transfer Application 09/24/2018
162. LER 2018-005-00 for Pilgrim Nuclear Power Station, Condition Prohibited by Technical Specifications Involving Standby Gas Treatment System Pneumatic Leakage Rate 09/25/2018
163. Pilgrim, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications 09/25/2018
164. Pilgrim Nuclear Power Station - Closeout of Generic Letter 2016-01, "Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools" (CAC No. MF9424; EPID L-2016-LRC-0001) 09/27/2018
165. Pilgrim Nuclear Power Station - Response to Request for Information Relating to Notification of Changes to Comprehensive Recovery Plan 10/03/2018
166. 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding - 60 Day Status Report (OEDO-15-00479) (CAC NO. MF6460; EPID L-2015-CRS-0002) 10/10/2018
167. Attachments 1 & 2: Response to Request for Additional Information - License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition. Letters of Agreement Enclosed 10/20/2018
168. Pilgrim, Submittal of Response to Request for Additional Information - License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition 10/10/2018
169. Press Release-I-18-022: NRC Names New Senior Resident Inspector at Pilgrim Nuclear Plant 10/10/2018
170. Revision to Confirmatory Action Letter - Pilgrim Nuclear Power Station 10/11/2018
171. 9/25/2018 Summary of Pre-submittal Meeting with Entergy Nuclear and Holtec International to Discuss Potential License Transfer Application for Pilgrim Nuclear Power Plant 10/16/2018
172. LER 2017-012-01 for Pilgrim, Supplement to Start-Up Transformer Degraded Voltage Relay Found Outside Technical Specification Limit 10/25/2018
173. Pilgrim, Request for Rescission of Security Orders. 10/31/2018
174. Pilgrim Nuclear Power Station - Notification of Revised Post-Shutdown Decommissioning Activities Report and Revised Site-Specific Decommissioning Cost Estimate. 11/16/2018
175. Pilgrim Nuclear Power Station - Request for Exemption from 10 CFR 50.82(a)(8)(I)(A). 11/16/2018
176. Pilgrim Nuclear Power Station - Update to Spent Fuel Management Plan Pursuant to 10 CFR 50.54 (bb). 11/16/2018
177. Post Shutdown Decommissioning Activities Report
Pilgrim Nuclear Power Station
11/16/2018
178. Pilgrim Nuclear Power Station - Application for Order Consenting to Direct and Indirect Transfers of Control of Licenses and Approving conforming License Amendment; and Request for Exemption from 10 CFR 50.82(a)(8)(i)(A). 11/16/2018
179. Pilgrim Nuclear Power Station - Triennial Fire Protection Inspection Report 05000293/2018015. 11/21/2018
180. Pilgrim Nuclear Power Station - Issuance of Amendment No. 248, Revise Site Emergency Plan for On-Shift and Emergency Response Organization Staffing to Address Permanently Defueled Condition (EPID L-2018-LLA-0046). 11/30/2018
181. Pilgrim, Response to Request for Additional Information - Exemption from the Requirements of 10 CFR 50.47 and Appendix E to 10 CFR Part 50. 11/30/2018
182. Pilgrim, Response to Request for Additional Information - Exemption from the Requirements of 10 CFR 50.47 and Appendix E to 10 CFR Part 50. 12/04/2018
183. Pilgrim, Submittal of Emergency Plan Revision. 12/04/2018
184.

Response to Request for Additional Information - License Amendment Request to Revise the Pilgrim Nuclear Power Station Emergency Plan and Emergency Action Level Scheme to Address the Permanently Defueled Condition

12/08/2018
185. Pilgrim Nuclear Power Station - Request for Relief and Rescission of Commission Order Modifying Licenses With Regard To Requirements for Beyond-Design-Basis External Events (Order EA-12-049). 12/14/2018
186. Pilgrim Nuclear Power Station - Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Hardened Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109). 12/14/2018
187. Pilgrim Nuclear Power Station - Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051). 12/14/2018
188. Pilgrim - Application for Order Approving Direct and Indirect Transfer of Renewed Facility Operating License and Conforming License Amendment to Holtec Pilgrim, LLC (owner) and Holtec Decommissioning International, LLC (operator) (EPID L-2018-LLO-0003). 12/17/2018
189. Pilgrim - Request for Withholding Info from Public Disclosure - 11/12/18 Affidavit Executed by A. Rosenlieb, Entergy and 11/14/18 Affidavit Executed by A. Ryan, Holtec International Re:  Enclosure 1P, Equity Purchase and Sale Agreement (L-2018-LLO-0003). 12/17/2018
190. Pilgrim Nuclear Power Station - Acceptance Review Letter, Review of Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate (EPID L-2018-LLL-0031). 12/17/2018
191. Pilgrim Nuclear Power Station - Federal Register Notice, Notice of Receipt, Public Meeting, and Request for Comment on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate (EPID L-2018-LLL-0031). 12/18/2018
192. Pilgrim - Acceptance Review Letter, Application for Order for Direct and Indirect Transfers of Control of Licenses, Conforming License Amendment, and Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) (EPID L-2018-LLO-0003 and L-2018-LLE-0020). 12/19/2018
193. Pilgrim - Acceptance Review Letter, Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) to Allow Use of Funds from Nuclear Decommissioning Trust for Spent Fuel Management and Site Restoration Activities (EPID L-2018-LLE-0019). 12/20/2018
194. 12/20/2018, Letter to the Honorable William Keating Responds to His Letter Commenting on Recent NRC Inspection Reports Issued for the Pilgrim Nuclear Power Station. 12/20/2018
195. Arkansas Nuclear One, Indian Point Energy Center, Grand Gulf Nuclear Station, Palisades Nuclear Plant, River Bend Station, Pilgrim Nuclear Station and Waterford 3 - Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element K. 12/28/2018
196. Pilgrim - Letter, Notice of Application for Order for Direct and Indirect Transfer of Renewed Facility Operating License and Conforming License Amendment to Holtec Pilgrim, LLC and Holtec Decommissioning International, LLC (EPID L-2018-LLO-0003). 01/02/2019
197. Pilgrim - FRN, Notice of Application for Order for Direct and Indirect Transfer of Renewed Facility Operating License and Conforming License Amendment to Holtec Pilgrim, LLC and Holtec Decommissioning International, LLC (EPID L-2018-LLO-0003). 01/02/2019
198. Pilgrim Nuclear Power Station - Clarification of Post-Shutdown Decommissioning Activities Report. 01/09/2019
199. Pilgrim - Response to Request for Additional Information - License Amendment Request to Revise the Technical Specifications - Permanently Defueled Technical Specifications. 01/10/2019
200. Pilgrim Nuclear Power Station - Holtec Slides PSDAR Meeting 1-15-19. 01/15/2019
201. Pilgrim Nuclear Power Station - Post-Shutdown Decommissioning Activities Report, NRC Public Meeting January 15, 2019. 01/15/2019
202. Pilgrim Post-Shutdown Decommissioning Activities Report - NRC Presentation at Public Meeting on January 15, 2019. 01/15/2019
203. Pilgrim Nuclear Power Station - Public Meeting on Post-Shutdown Decommissioning Activities Report. 01/15/2019
204. Revision to Confirmatory Action Letter - Pilgrim Nuclear Power Station. 01/17/2019
205. Pilgrim Nuclear Power Station - NRC Investigation Report No.   1-2018-001 and Exercise of Enforcement Discretion. 01/23/2019
206. Summary of 1/15/2019 Public Meeting Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Which Includes the Site-Specific Decommissioning Cost Estimate (EPID L-2018-LLL-0031). 01/30/2019
207. Transcript for Public Meeting Held on Jan. 15, 2019, in Plymouth, Mass., Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report and License Transfer Application (EPID L-2018-LLL-0031). 02/07/2019
208. 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding - 60-Day Status Report (OEDO-15-00479) (CAC No. MF6460; EPID L-2015-CRS-0002). 02/08/2019
209. Pilgrim, Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications. 02/08/2019

To top of page

Page Last Reviewed/Updated Wednesday, March 24, 2021