The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Communications Regarding Increased Oversight at Pilgrim Nuclear Power Plant

On this page:

Assessment

No. Title Date Issued
1. 2014 Annual Assessment Letter (Degraded Cornerstone) 03/04/2015
2. Mid-Cycle Assessment Letter For Pilgrim Nuclear Power Station (Report 05000293/2015005) 09/01/2015
3. Pilgrim Nuclear Power Station - NRC Integrated Inspection Report 3rd Quarter 05000293/2015003 (see Sect 4OA5 for quarterly assessment) 11/12/2015
4. 2015 Annual Assessment Letter (Repetitive Degraded Cornerstone) 03/02/2016
5. Pilgrim Nuclear Power Station - NRC Integrated Inspection Report 1st Quarter 05000293/2016001 (see Sect 4OA5 for quarterly assessment) 05/12/2016
6. Mid-Cycle Assessment Letter For Pilgrim Nuclear Power Station (Report 05000293/2016005) 08/31/2016
7. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 3rd Quarter 05000293/2016003 (see Sect 4OA5 for quarterly assessment) 11/14/2016
8. Annual Assessment Letter for Pilgrim Nuclear Power Station (Report 05000293/2016006) 03/01/2017
9. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017001 (see Sect 4OA5 for quarterly assessment) 05/15/2017
10. Quarterly Assessment and Updated Inspection Plan for Pilgrim Nuclear Power Station (Report 05000293/2017005) 08/28/2017
11. Annual Assessment Letter for Pilgrim Nuclear Power Station (Reports 05000293/2017006, 05000293/2017402, and 05000293/2017501) 02/28/2018
12. Pilgrim Nuclear Power Station - Assessment Follow-up Letter and Updated Inspection Plan (Inspection Report 05000293/2018005) 08/30/2018
13. Annual Assessment Letter For Pilgrim Nuclear Power Station (Report 05000293/2018006) And Confirmatory Action Letter Closure 03/04/2019

To top of page

Inspection

No. Title Date Issued
1. Pilgrim Nuclear Power Station – NRC 95002 Supplemental Inspection Report 05000293/2014008 And Assignment Of Two Parallel White Performance Indicator Inspection Findings 01/26/2015
2. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 1st Quarter 05000293/2015001 (1 NCV) 05/11/2015
3. Pilgrim Nuclear Power Station – NRC Special Inspection Report 05000293/2015007; And Preliminary White Finding 05/27/2015
4. Pilgrim Nuclear Power Station – NRC 95002 Supplemental Follow-Up Inspection Report 05000293/2015009 06/18/2015
5. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 2nd Quarter 05000293/2015002 (4 NCV, 1 FIN) 08/11/2015
6. Final Significance Determination For A White Finding And Notice Of Violation - Inspection Report No. 05000293/2015011 – Pilgrim Nuclear Power Station 09/01/2015
7. Biennial PI&R Inspection w/ CAP Marginally Effective (2 NOV, 2 NCV) 10/01/2015
8. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 3rd Quarter 05000293/2015003 (4 NCV, 1 SLIV) 11/12/2015
9. Security Baseline – Access, Equipment and Training (5 NCV) 12/01/2015
10. Triennial Fire Protection Inspection (1 NCV) 12/21/2015
11. Pilgrim Nuclear Power Station, NRC Inspection Report No. 05000293/2016010 And NRC Office Of Investigations Report NO. 1-2015-005 02/10/2016
12. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 4th Quarter 05000293/2015004 (4 NCV) 02/11/2016
13. Pilgrim Nuclear Power Station – IP 95003 Supplemental Inspection Report (Phase A) 05000293/2016008 (1 NCV) 02/29/2016
14. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 1st Quarter 05000293/2016001 05/12/2016
15. Pilgrim Nuclear Power Station – IP 95003 Supplemental Inspection Report (Phase B) 05000293/2016008 (1 NCV) 05/23/2016
16. Pilgrim Nuclear Power Station – NRC Permanent Plant Modifications Inspection Report 05000293/2016007 07/06/2016
17. Pilgrim Nuclear Power Station – Temporary Instruction 2515/191 Inspection Report 05000293/2016013 07/07/2016
18. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 2nd Quarter 05000293/2016002 (1 NCV) 08/10/2016
19. Pilgrim Nuclear Power Station – NRC Integrated Inspection Report 3rd Quarter 05000293/2016003 (4 NCV) 11/14/2016
20. Pilgrim Nuclear Power Station – Evaluated Emergency Preparedness Exercise Inspection Report 05000293/2016502 12/20/2016
21. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2016004 and Independent Spent Fuel Storage Installation Report 07201044/2016001 02/14/2017
22. Pilgrim Nuclear Power Station – Problem Identification and Resolution Sample Inspection Report 05000293/2016404 (3 NCV) 04/07/2016
23. Pilgrim Nuclear Power Station – Supplemental Inspection Report (Inspection Procedure 95003 Phase 'C') 05000293/2016011 and Preliminary Greater-than-Green Finding (7 NCV, 2 FIN, 1 SLIV) 05/10/2017
24. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017001 (2 NCV, 1 SLIV) 05/15/2017
25. Pilgrim Nuclear Power Station – Initial Operator Licensing Examination Report 05000293/2017301 05/15/2017
26. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017002 08/14/2017
27. Pilgrim Nuclear Power Station – Problem Identification and Resolution Sample Inspection Report 05000293/2017405 (Letter Only) 09/05/2017
28. Pilgrim Nuclear Power Station – Design Bases Assurance Inspection Report 05000293/2017007. 09/28/2017
29. Pilgrim Nuclear Power Station – Baseline Security Inspection Report 05000293/2017403, (Letter Only). 10/12/2017
30. Pilgrim Nuclear Power Station – Material Control and Accounting Program Inspection Report 05000293/2017404 (Letter Only). 10/17/2017
31. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017003. 11/14/2017
32. Pilgrim Nuclear Power Station – NRC Security Inspection Report 05000293/2017201. 11/21/2017
33. Pilgrim Nuclear Power Station – Problem Identification and Resolution Inspection Report 05000293/2017009. 12/21/2017
34. Pilgrim Nuclear Power Station – Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2017010. 02/01/2018
35. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2017004 02/14/2018
36. Pilgrim Nuclear Power Station – NRC Investigation Report No. 1-2017-015. 02/27/2018
37. Pilgrim Nuclear Power Station – NRC Investigation Report No. 1 -2017-011 and Notice of Violation 02/28/2018
38. Pilgrim, and Independent Spent Fuel Storage Installation – Radioactive Effluent Release Report. 02/28/2018
39. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2018001 05/14/2018
40. Pilgrim Nuclear Power Station – Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018010. 06/13/2018
41. Pilgrim Nuclear Power Station - Baseline Security Inspection Report 05000293/2018411 09/27/2018
42. Pilgrim Nuclear Power Station - Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018011 10/09/2018
43. Pilgrim Nuclear Power Station – Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018012 11/01/2018
44. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2018003 and Independent Spent Fuel Storage Installation Inspection Report 07201014/2018001 11/13/2018
45. Pilgrim Nuclear Power Station – Triennial Fire Protection Inspection Report 05000293/2018015 11/21/2018
46. Pilgrim Nuclear Power Station – Evaluated Emergency Preparedness Exercise Inspection Report 05000293/2018501 12/06/2018
47. Pilgrim Nuclear Power Station – Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018013. 01/23/2019
48. Pilgrim Nuclear Power Station – Integrated Inspection Report 05000293/2018004 and Independent Spent Fuel Storage Installation Report 07201044/2018201 02/13/2019

To top of page

Other

No. Title Date Issued
1. Inspection Approach/Phase Schedule Communication Letter 12/18/2015
2. OEDO-15-00479: David Lochbaum and Others 2.206 Petition Regarding Pilgrim's Current License Basis for Flooding Acknowledgement Letter (CAC No. MF6460) 02/11/2016
3. Pilgrim Nuclear Power Station -- Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 03/03/2016
4. NRC Notice of Violation (NRC Investigation Report No. 1-2015-005) (Fire watch NOV) 04/11/2016
5. NRC Annual Assessment Meeting Summary 04/13/2016
6. NRC Annual Assessment Meeting Presentation 04/13/2016
7. Entergy Annual Assessment Meeting Presentation 04/13/2016
8. 2016 AARM Meeting Agenda 06/02/2016
9. 2016 AARM Slides 06/02/2016
10. 2016 AARM Transcript 06/02/2016
11. 2016 AARM Meeting SRM 06/02/2016
12. LER 2016-001-00 06/09/2016
13. LTR-15-0319-1, LTR-15-0375-1 – Response Letter 2.206 Petition Re: Pilgrim Severe Weather Emergency Preparedness 06/22/2016
14. LER 2016-002-00 06/30/2016
15. Pilgrim Extension Request for Order EA-13-109 Schedule Requirements 07/13/2016
16. LER 2016-003-00 07/25/2016
17. LER 2016-004-00 07/25/2016
18. Interim Staff Response to Reevaluated Flood Hazards Submitted in Pilgrim Response to the 10CFR50.54(f) Information Request 08/03/2016
19. PNPS Letter – Request for Deferral of Beyond-DBE Flooding Actions 08/18/2016
20. PNPS Letter – Request for Deferral Beyond-DBE Seismic Actions 08/18/2016
21. LER 2016-002-001 Supplement 08/18/2016
22. Entergy Announces Pilgrim Readiness for Phase C Inspection 08/31/2016
23. PNP Ltr 2.16.057 – LER 2016-004 Retraction 09/09/2016
24. Formal Notification of Phase C IP 95003 Inspection dates 10/13/2016
25. LER 2016-005-00 11/04/2016
26. LER 2016-006-00 11/04/2016
27. Pilgrim Response to NRC Generic Letter 2016-01 , "Monitoring of Neutron-Absorbing Material in Spent Fuel Pools" 11/03/2016
28. Licensee Event Report 2016-007-00 – Pilgrim Nuclear Power Station Regarding Manual Reactor Scram Due To Feedwater Regulating Valve Malfunction 11/04/2016
29. NRC Response to Town of Plymouth regarding Pilgrim 12/13/2016
30. JRWA Letter Expressing Concerns About Flooding Risks at Pilgrim Nuclear Power Station 12/26/2016
31. Letter from Massachusetts Attorney General Requesting NRC meet with public to discuss inadvertently released email 01/04/2017
32. Licensee Event Report 2016-009-00 – HPCI Declared Inoperable Due to Failure of IST Surveillance Test 01/05/2017
33. Letter from Chairman responding to Massachusetts Attorney General Request for NRC to meet with public to discuss inadvertently released email 01/11/2017
34. Letter to Mary Lampert, Director, Pilgrim Watch, from Stephen Koenick, LPL1, DORL/NRR Re: Pilgrim Nuclear Power Station - Liability and Holtec Guarantees 01/17/2017
35. Notice of Category 3 Public Meeting - Preliminary Findings and Status of 95003 Inspection at Pilgrim Nuclear Power Station 01/19/2017
36. Pilgrim Watch response to Stephen Koenick January 7 reply to our October 27, 2016 email regarding liability and Holtec guarantees at Pilgrim Nuclear Power Station 01/24/2017
37. Press Release-I-17-002: NRC Plans Plymouth Public Meeting to Discuss Reviews at Pilgrim Nuclear Power Plant 01/30/2017
38. Pilgrim Nuclear Power Station – Petition Received at Pilgrim 95003 Public Meeting from Pilgrim Legislative Advisory Coalition 01/31/1017
39. LTR-16-0609 NRC Response to Senator Viriato M. deMacedo, et al, Plymouth and Barnstable District, Massachusetts Senate, letter regarding concern about the current state of Pilgrim Nuclear Power Station 02/01/2017
40. Pilgrim Nuclear Power Station – Request for Approval of Certified Fuel Handler Training and Retraining Program 02/02/2017
41. Pilgrim Nuclear Power Station – Request for Exemption from Specific Provisions in 10 CFR 73.55 02/07/2017
42. Pilgrim Nuclear Power Station – ISFSI Radioactive Effluent Release Report for 2016 02/10/2017
43. LER 16-010-00 for Pilgrim Nuclear Power Station Regarding MSIV Inoperability Led to a Condition Prohibited by the Plant's Technical Specifications 02/13/2017
44. Status of Decision on Petitioners Request for Hearing Regarding Entergy's Request for Extension to Comply with NRC Order EA-13-109 02/17/2017
45. Region I/DRP Response to James R. Garb, Pilgrim Legislative Advisory Coalition re: Degraded Safety Status of the Pilgrim Nuclear Power Station 02/21/2017
46. NRC Response to Jones River Watershed Association Letter Dated December 26, 2016 to the NRC on Pilgrim Nuclear Power Station 02/27/2017
47. 01/31/2017 – Summary of Category 3 Public Meeting - Preliminary Findings and Status of 95003 Inspection at Pilgrim 02/28/2017
48. NRC Response to Petition Received at Pilgrim 95003 Public Meeting from Pilgrim Legislative Advisory Coalition 03/06/2017
49. Pilgrim Nuclear Power Station – Notice of Public Meeting (Annual Assessment and 95003 Inspection Exit Meeting) - 3/21/2017 03/10/2017
50. Press Release-I-17-005: NRC to Hold Pilgrim Nuclear Plant Public Exit Meeting for Inspection, Annual Assessment Discussion 03/14/2017
51. LER 17-001-00 for Pilgrim Regarding Reactor Building Isolation Dampers Failed to Isolate 03/15/2017
52. Pilgrim Nuclear Power Station - Supplement to Requests for Relief from ASME Section XI Volumetric Examination Requirements - Fourth 10-Year Interval 03/16/2017
53. 3/21/2017 – Annual Assessment/95003 Inspection Exit Meeting for Pilgrim Nuclear Power Station - Speaker Sign-Up Sheets 03/21/2017
54. Statement from the Office of U.S. Senator Elizabeth Warren – NRC Annual Meeting, Plymouth, MA 03/21/2017
55. Statement of Congressman Keating – NRC Annual Assessment Meeting for PNPS - March 21, 2017. 03/21/2017
56. Statement of Senator Edward J. Markey – NRC Annual Assessment Meeting for Pilgrim Nuclear Power Station - March 21, 2017 03/21/2017
57. 3/21/2017 – Annual Assessment & 95003 Exit Meeting for Pilgrim Nuclear Power Station – Entergy Presentation Slides 03/21/2017
58. 3/21/2017 – Annual Assessment & IP 95003 Exit Meeting for Pilgrim Nuclear Power Station – NRC Presentation Slides 03/21/2017
59. 03/21/2017 Transcript of Annual Assessment/95003 Inspection Exit Meeting for Pilgrim Nuclear Power Station 03/21/2017
60. 3/21/2017 – Annual Assessment/95003 Inspection Exit Summary Meeting for Pilgrim Nuclear Power Station 03/21/2017
61. Pilgrim, License Amendment Request - Cyber Security Plan Implementation Schedule 03/30/2017
62. Nuclear Property Damage Insurance [10 CFR 50.54(w)(3)] 03/30/2017
63. Entergy Nuclear Operations, Inc. – Decommissioning Funding Status Report per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v). 03/31/2017
64. Pilgrim Nuclear Power Station - Issuance of Relief Request Nos. PNPS-ISI-004 and PNPS-ISI-005 for Relief from American Society of Mechanical Engineers Code, Section XI, Volumetric Examination Requirements. 04/03/2017
65. Commission Memorandum and Order regarding PW request for Hearing related to Fukushima Orders (CLI-17-06). 04/06/2017
66. Notification for Information Only – Pilgrim Deviation from EPRI Report 3002000091, Rev. 1 04/10/2017
67. OEDO-15-00479 – 2.206 Petition regarding Pilgrim current licensing basis for flooding – 60 DAY STATUS (CAC NO. MF6460) 04/10/2017
68. Pilgrim Nuclear Power Station – Approval of Certified Fuel Handler Training and Retraining Program (CAC No. MF9275) 04/12/2017
69. Pilgrim Nuclear Power Station – NRC Response to Request for Deferral of Actions Related to Beyond-Design-Basis Seismic and Flooding External Events. 04/17/2017
70. Pilgrim Nuclear Power Station – Relaxation of the Schedule Requirements for Order EA-13-109: Order Modifying Licenses With Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions. 04/17/2017
71. 3/21/2017 – Annual Assessment/95003 Inspection Exit Summary Meeting for Pilgrim Nuclear Power Station. 04/18/2017
72. Pilgrim Nuclear Power Station – Relief Requests PNPS-ISI-001 and PNPS-ISI-002, Relief from ASME Code Volumetric Examination Requirements for the Fourth 10-Year Inservice Inspection Interval (CAC Nos. MF8092 and MF8093) 05/12/2017
73. Pilgrim Nuclear Power Station – Letter, Request for Exemption from Specific Provisions in 10 CFR 73.55 Related to Suspension of Security Measures for Licensed Senior Operator or Certified Fuel Handler (CAC No. MF9274) 05/16/2017
74. Pilgrim – Fuel Cycle 22, Core Operating Limits Report, Revision 37 05/12/2017
75. Pilgrim – Annual Radiological Environmental Operating Report for January 1 through December 31, 2016 05/12/2017
76. Pilgrim – Annual Radioactive Effluent Release Report for January 1 through December 31, 2016 05/12/2017
77. OEDO-15-00479: Federal Register Notice re: 2.206 Petition Regarding Pilgrim's Current License Basis for Flooding (CAC No. MF6460) 02/11/2016
78. Supplemental to Technical Specifications Proposed Change – Administrative Controls for Permanently Defueled Condition 05/25/2017
79. LER 17-002-00 for Pilgrim Regarding Isolation of HPCI 05/25/2017
80. LER 17-003-00 for Pilgrim Nuclear Power Station Regarding Pressure Suppression Pool Declared Inoperable Due to High Water Level 05/25/2017
81. LER 17-004-00 for Pilgrim Nuclear Power Station Regarding Secondary Containment Testing Led to Loss of Safety Function to Both Trains of Standby Gas Treatment System 06/02/2017
82. LER 17-005-00 for Pilgrim Regarding 10 CFR 50, Appendix J, Option B, Leak Rate Criteria Exceeded 06/07/2017
83. LER 17-006-00 for Pilgrim Nuclear Power Station Regarding Source Range Monitor Inoperable During Fuel Movement 06/13/2017
84. LER 16-010-01 for Pilgrim Nuclear Power Station re MSIV Inoperability 06/14/2017
85. LER 17-007-00 for Pilgrim Regarding Potential Inoperability of Safety Relief Valve 3A 06/22/2017
86. Pilgrim – NRC Investigation Report 1-2016-011 06/28/2017
87. Pilgrim Nuclear Power Station's Sixth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order No. EA-13-109) 06/30/2017
88. Pilgrim Nuclear Power Station – Issuance of Amendment No. 246, Revise Administrative Controls Section of Technical Specifications to Change Staffing and Training Requirements for Permanently Defueled Condition (CAC No. MF9304) 07/10/2017
89. Pilgrim Nuclear Power Station: Regulatory Conference Presentation 07-13-17 07/13/2017
90. Press Release-I-17-026: NRC to Hold Regulatory Conference with Entergy Regarding Apparent Violation at Pilgrim Nuclear Power Plant 07/12/2017
91. Pilgrim Nuclear Power Station Recovery Plan 07/28/2017
92. Confirmatory Action Letter – Pilgrim Nuclear Power Station 08/02/2017
93. Press Release-I-17-028: NRC Issues Confirmatory Action Letter to Pilgrim Nuclear Power Plant on Safety Performance Improvement Commitments 08/02/2017
94. LER 17-008-00 for Pilgrim re 480V Bus B6 Auto Transfer Function Degraded Due to Time Delay Relay Failure 06/30/2017
95. Pilgrim Nuclear Power Station – Final Significance Determination For A Green Finding And Results Of Regulatory Conference – Inspection Report 05000293/2017008 08/09/2017
96. LER 17-010-00 for Pilgrim re Air Accumulation Creates Small Void in Core Spray Discharge Piping 08/07/2017
97. LER 17-009-00 for Pilgrim Nuclear Power Station Regarding Potential Primary Containment System lnoperability Due to Relay Concerns 07/17/2017
98. LER 17-001-01 for Pilgrim Nuclear Power Station Regarding Reactor Building Isolation Dampers Failed to Isolate 07/17/2017
99. Requalification Program Inspection – Pilgrim Nuclear Power Station 08/22/2017
100. Pilgrim Nuclear Power Station, Transmittal of Reply to a Notice of Violation, EA-17-030 08/11/2017
101. LER 17-011-00 for Pilgrim Nuclear Power Station Regarding Simultaneously Opened Reactor Building Airlock Doors Caused Loss of Secondary Containment 08/15/2017
102. OEDO-15-00479 – E-mail to David Lochbaum Re. 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding; 60-Day Status Report (CAC NO. MF6460; EPID L-2015-CRS-0002) 10/10/2017
103. Presentations on Reactor Decommissioning at MA NDCAP at Plymouth MA Public Meeting Oct 18, 2017 10/23/2017
104. LER 17-008-01 for Pilgrim Nuclear Power Station Regarding Supplement to 480V Bus B6 Auto Transfer Function Degraded Due to Time Delay Relay Failure 11/17/2017
105. LER 17-003-01 for Pilgrim Nuclear Power Station Regarding Supplement to Suppression Pool Declared Inoperable Due to High Water Level 11/30/2017
106. LER 17-012-00 for Pilgrim Nuclear Power Station Regarding Start-Up Transformer Degraded Voltage Relay Found Outside Technical Specification Limit 11/30/2017
107. Pilgrim Nuclear Power Station's Seventh Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions. 12/8/2017
108. OEDO-15-00479 – 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding – 60-Day Status Report (CAC NO. MF6460; EPID L-2015-CRS-0002) 12/11/2017
109. LER 17-007-01 for Pilgrim Nuclear Power Station Regarding Supplement to Potential Inoperability of Safety Relief Valve 3A 01/12/2018
110. LER 17-009-01 for Pilgrim Nuclear Power Station Regarding Supplement to Potential Primary Containment System Inoperability Due to Relay Concerns 01/18/2018
111. LER 17-013-00 for Pilgrim Nuclear Power Station Regarding Reportable Conditions Involving Standby Gas Treatment System and Secondary Containment lnoperability Not Reported During the Previous Three Years 02/12/2018
112. OEDO-15-00479 – 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding – 60-Day Status Report (CAC No. MF6460; EPID L-2015-CRS-0002) 02/12/2018
113. 02-14-18 Acknowledgement Letter to Senators Warren, Markey and Keating Regarding the Pilgrim Plant 02/21/2018
114. 03/27/2018 – Notice of Category 1 Public Meeting – Annual Assessment Meeting for Pilgrim Nuclear Power Station 03/14/2018
115. Press Release-I-18-003: NRC Staff to Conduct Public Meeting to Discuss 2017 Performance of Pilgrim Nuclear Power Plant 03/26/2018
116. Response to Request for Information Senator Elizabeth Warren, Senator Edward Markey, and Representative William Keating Letter dated February 12, 2017 (Enclosure) 03/26/2018
117. LER 2018-001-00 for Pilgrim Nuclear Power Station Regarding Manual Reactor Scram Due To Loss of One Offsite Transmission Line 03/28/2018
118. LER 2018-002-00 for Pilgrim re: Diesel Generator A Inoperable, a Condition Prohibited by the Plant Technical Specifications 03/28/2018
119. LER 2018-003-00 for Pilgrim, Target Rock Relief Valve Pilot Assembly Failed As-Found Lift Test, a Condition Prohibited by Plant Technical Specifications 04/11/2018
120. Pilgrim, License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition 01/12/2018
121. Response to Request for Supplemental Information Regarding Generic Letter 2016-01, "Monitoring of Neutron Absorbing Materials in the Spent Fuel Pools" for Grand Gulf Nuclear Station Unit 1 and Pilgrim Nuclear Power Station. 02/08/2018
122. Revise the Pilgrim Emergency Plan to Address the Permanently Defueled Condition 02/20/2018
123. Pilgrim Nuclear Power Station – NRC Investigation Report No. 1 -2017-011 and Notice of Violation 02/27/2018
124. Pilgrim, and Independent Spent Fuel Storage Installation –  Radioactive Effluent Release Report 02/28/2018
125. FEMA Review Requested Of Revision To The Pilgrim Nuclear Power Station Emergency Plan To Address The Permanently Defueled Condition. 03/08/2018
126. Confirmatory Order, NRC Inspection Report 05000416/2017014, and NRC Investigation Reports 4-2016-004 and 4-2014-021 03/13/2018
127. Press Release-IV-18-002: NRC Issues Confirmatory Order to Entergy. 03/14/2018
128. Pilgrim Nuclear Power Station Notification of Changes to Comprehensive Recovery Plan and Area Action Plan Action Completion Dates. 03/14/2018
129. 03/27/2018 – Notice of Category 1 Public Meeting – Annual Assessment Meeting for Pilgrim Nuclear Power Station 03/14/2018
130. Response to Request for Information Senator Elizabeth Warren, Senator Edward Markey, and Representative William Keating  Letter dated February 12, 2017 (Enclosure) 03/19/2018
131. Pilgrim, Anchor Darling Double Disc Gate Valve Information and Status. 04/16/2018
132. 04-25-18 FEMA Letter to NRC, entitled "FEMA Review of Revision to Pilgrim Nuclear Power Station Emergency Plan to Address the Permanently Shutdown Condition 04/25/2018
133. Statement of Congressman William R. Keating – NRC Annual Assessment Meeting for Pilgrim Nuclear Power Station – 03/27/2018 05/07/2018
134. 03/27/2018 – Transcript of Annual Assessment Meeting for Pilgrim Nuclear Power Station. 05/07/2018
135. 03/27/2018 – Annual Assessment Meeting for Pilgrim Nuclear Power Station – Entergy Presentation Slides. 05/07/2018
136. Statement of Senator Edward J. Markey – NRC Annual Assessment Meeting for Pilgrim Nuclear Power Station – 03/27/2018. 05/07/2018
137. 03/27/2018 – Annual Assessment Meeting for Pilgrim Nuclear Power Station – NRC Presentation Slides. 05/07/2018
138. Letter to Power Reactor Licensees – U.S. Nuclear Regulatory Commission Analysis of Licensees' 2017 Decommissioning Funding Status Reports. 05/08/2018
139. 03/27/2018 – Summary of Annual Assessment Meeting for Pilgrim Nuclear Power Station 05/09/2018
140. LER 2018-004-00 for Pilgrim Nuclear Power Station, Automatic Emergency Diesel Generator System Actuation Caused By Loss of Offsite Power. 05/14/2018
141. LER 2017-013-01 for Pilgrim Nuclear Power Station re Supplement to Reportable Conditions Involving Standby Gas Treatment System and Secondary Containment Inoperability Not Reported During the Previous Three Years. 05/14/2018
142. Pilgrim, Submittal of Annual Radiological Environmental Operating Report for January 1 through December 31, 2017 05/15/2018
143. Pilgrim Nuclear Power Station – Annual Radioactive Effluent Release Report for January 1 through December 31, 2017. 05/15/2018
144. Responses to Request for Information – Senator Edward Markey Letter dated April 23, 2018 (Enclosure) 05/29/2018
145. Pilgrim Nuclear Power Station – Reply to Notice of Violation (NRC Investigation Report No. 1-2017-011) 05/30/2018
146. Entergy Letter dated June 1, 2018 to David Lew regarding Pilgrim Notification of Changes to Comprehensive Recovery Plan 06/01/2018
147. Pilgrim Extent of Condition Review in Response to Findings Associated with Inspection 95003:  Evaluation of NRC Assessment and Inspection Processes at Pilgrim Nuclear Power Station. 06/06/2018
148. Revision to Confirmatory Action Letter – Pilgrim Nuclear Power Station. 06/07/2018
149. Pilgrim 95003 Evaluation and Corrective Actions Memorandum dated June 7, 2018 06/07/2018
150. Pilgrim 95003 Evaluation – Memorandum regarding Licensee Event Report Safety Significance Review in Response to Findings Associated with Inspection Procedure 95003; Evaluation of NRC Assessment and Inspection Processes at Pilgrim Nuclear Power Station 06/07/2018
151. Inspection Procedure 95003:  Evaluation Of NRC Assessment And Inspection Processes At Pilgrim Nuclear Power Station. 06/11/2018
152. 2018 AARM Meeting Agenda 06/19/2018
153. 2018 AARM Slides 06/19/2018
154. 2018 AARM Transcript 06/19/2018
155. 2018 AARM Meeting SRM 06/19/2018
156. Pilgrim Nuclear Power Station – Baseline Security Inspection Report 05000293/2018410 (Letter Only). 06/20/2018
157. Pilgrim Nuclear Power Station – Retraction of Licensee Event Report 2018-002-00, Diesel Generator A Inoperability, a Condition Prohibited by the Plant Technical Specifications. 06/21/2018
158. Pilgrim Nuclear Power Station – Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E. 07/03/2018
159. 08/28/18 – Letter to Representative William Keating from Chairman Svinicki responds to his letter regarding the Proposed Sale of Pilgrim Nuclear Power Station by Entergy Nuclear Operations Inc. to a Subsidiary of Holtec International 09/05/2018
160. Pilgrim Nuclear Power Station - NRC License Transfer Application 9/25/2018 Pre-Submittal Meeting Presentation Slides 09/19/2018
161. Pilgrim Nuclear Power Station - Letter to Pilgrim Watch and Town of Duxbury Nuclear Advisory Committee Related to Questions Regarding Planned License Transfer Application 09/24/2018
162. LER 2018-005-00 for Pilgrim Nuclear Power Station, Condition Prohibited by Technical Specifications Involving Standby Gas Treatment System Pneumatic Leakage Rate 09/25/2018
163. Pilgrim, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications 09/25/2018
164. Pilgrim Nuclear Power Station - Closeout of Generic Letter 2016-01, "Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools" (CAC No. MF9424; EPID L-2016-LRC-0001) 09/27/2018
165. Pilgrim Nuclear Power Station - Response to Request for Information Relating to Notification of Changes to Comprehensive Recovery Plan 10/03/2018
166. 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding - 60 Day Status Report (OEDO-15-00479) (CAC NO. MF6460; EPID L-2015-CRS-0002) 10/10/2018
167. Attachments 1 & 2: Response to Request for Additional Information - License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition. Letters of Agreement Enclosed 10/20/2018
168. Pilgrim, Submittal of Response to Request for Additional Information - License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition 10/10/2018
169. Press Release-I-18-022: NRC Names New Senior Resident Inspector at Pilgrim Nuclear Plant 10/10/2018
170. Revision to Confirmatory Action Letter - Pilgrim Nuclear Power Station 10/11/2018
171. 9/25/2018 Summary of Pre-submittal Meeting with Entergy Nuclear and Holtec International to Discuss Potential License Transfer Application for Pilgrim Nuclear Power Plant 10/16/2018
172. LER 2017-012-01 for Pilgrim, Supplement to Start-Up Transformer Degraded Voltage Relay Found Outside Technical Specification Limit 10/25/2018
173. Pilgrim, Request for Rescission of Security Orders. 10/31/2018
174. Pilgrim Nuclear Power Station - Notification of Revised Post-Shutdown Decommissioning Activities Report and Revised Site-Specific Decommissioning Cost Estimate. 11/16/2018
175. Pilgrim Nuclear Power Station - Request for Exemption from 10 CFR 50.82(a)(8)(I)(A). 11/16/2018
176. Pilgrim Nuclear Power Station - Update to Spent Fuel Management Plan Pursuant to 10 CFR 50.54 (bb). 11/16/2018
177. Post Shutdown Decommissioning Activities Report
Pilgrim Nuclear Power Station
11/16/2018
178. Pilgrim Nuclear Power Station - Application for Order Consenting to Direct and Indirect Transfers of Control of Licenses and Approving conforming License Amendment; and Request for Exemption from 10 CFR 50.82(a)(8)(i)(A). 11/16/2018
179. Pilgrim Nuclear Power Station - Triennial Fire Protection Inspection Report 05000293/2018015. 11/21/2018
180. Pilgrim Nuclear Power Station - Issuance of Amendment No. 248, Revise Site Emergency Plan for On-Shift and Emergency Response Organization Staffing to Address Permanently Defueled Condition (EPID L-2018-LLA-0046). 11/30/2018
181. Pilgrim, Response to Request for Additional Information - Exemption from the Requirements of 10 CFR 50.47 and Appendix E to 10 CFR Part 50. 11/30/2018
182. Pilgrim, Response to Request for Additional Information - Exemption from the Requirements of 10 CFR 50.47 and Appendix E to 10 CFR Part 50. 12/04/2018
183. Pilgrim, Submittal of Emergency Plan Revision. 12/04/2018
184.

Response to Request for Additional Information - License Amendment Request to Revise the Pilgrim Nuclear Power Station Emergency Plan and Emergency Action Level Scheme to Address the Permanently Defueled Condition

12/08/2018
185. Pilgrim Nuclear Power Station - Request for Relief and Rescission of Commission Order Modifying Licenses With Regard To Requirements for Beyond-Design-Basis External Events (Order EA-12-049). 12/14/2018
186. Pilgrim Nuclear Power Station - Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Hardened Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109). 12/14/2018
187. Pilgrim Nuclear Power Station - Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051). 12/14/2018
188. Pilgrim - Application for Order Approving Direct and Indirect Transfer of Renewed Facility Operating License and Conforming License Amendment to Holtec Pilgrim, LLC (owner) and Holtec Decommissioning International, LLC (operator) (EPID L-2018-LLO-0003). 12/17/2018
189. Pilgrim - Request for Withholding Info from Public Disclosure - 11/12/18 Affidavit Executed by A. Rosenlieb, Entergy and 11/14/18 Affidavit Executed by A. Ryan, Holtec International Re:  Enclosure 1P, Equity Purchase and Sale Agreement (L-2018-LLO-0003). 12/17/2018
190. Pilgrim Nuclear Power Station - Acceptance Review Letter, Review of Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate (EPID L-2018-LLL-0031). 12/17/2018
191. Pilgrim Nuclear Power Station - Federal Register Notice, Notice of Receipt, Public Meeting, and Request for Comment on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate (EPID L-2018-LLL-0031). 12/18/2018
192. Pilgrim - Acceptance Review Letter, Application for Order for Direct and Indirect Transfers of Control of Licenses, Conforming License Amendment, and Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) (EPID L-2018-LLO-0003 and L-2018-LLE-0020). 12/19/2018
193. Pilgrim - Acceptance Review Letter, Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) to Allow Use of Funds from Nuclear Decommissioning Trust for Spent Fuel Management and Site Restoration Activities (EPID L-2018-LLE-0019). 12/20/2018
194. 12/20/2018, Letter to the Honorable William Keating Responds to His Letter Commenting on Recent NRC Inspection Reports Issued for the Pilgrim Nuclear Power Station. 12/20/2018
195. Arkansas Nuclear One, Indian Point Energy Center, Grand Gulf Nuclear Station, Palisades Nuclear Plant, River Bend Station, Pilgrim Nuclear Station and Waterford 3 - Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element K. 12/28/2018
196. Pilgrim - Letter, Notice of Application for Order for Direct and Indirect Transfer of Renewed Facility Operating License and Conforming License Amendment to Holtec Pilgrim, LLC and Holtec Decommissioning International, LLC (EPID L-2018-LLO-0003). 01/02/2019
197. Pilgrim - FRN, Notice of Application for Order for Direct and Indirect Transfer of Renewed Facility Operating License and Conforming License Amendment to Holtec Pilgrim, LLC and Holtec Decommissioning International, LLC (EPID L-2018-LLO-0003). 01/02/2019
198. Pilgrim Nuclear Power Station - Clarification of Post-Shutdown Decommissioning Activities Report. 01/09/2019
199. Pilgrim - Response to Request for Additional Information - License Amendment Request to Revise the Technical Specifications - Permanently Defueled Technical Specifications. 01/10/2019
200. Pilgrim Nuclear Power Station - Holtec Slides PSDAR Meeting 1-15-19. 01/15/2019
201. Pilgrim Nuclear Power Station - Post-Shutdown Decommissioning Activities Report, NRC Public Meeting January 15, 2019. 01/15/2019
202. Pilgrim Post-Shutdown Decommissioning Activities Report - NRC Presentation at Public Meeting on January 15, 2019. 01/15/2019
203. Pilgrim Nuclear Power Station - Public Meeting on Post-Shutdown Decommissioning Activities Report. 01/15/2019
204. Revision to Confirmatory Action Letter - Pilgrim Nuclear Power Station. 01/17/2019
205. Pilgrim Nuclear Power Station - NRC Investigation Report No.   1-2018-001 and Exercise of Enforcement Discretion. 01/23/2019
206. Summary of 1/15/2019 Public Meeting Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Which Includes the Site-Specific Decommissioning Cost Estimate (EPID L-2018-LLL-0031). 01/30/2019
207. Transcript for Public Meeting Held on Jan. 15, 2019, in Plymouth, Mass., Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report and License Transfer Application (EPID L-2018-LLL-0031). 02/07/2019
208. 2.206 Petition Regarding Pilgrim Nuclear Power Station's Current Licensing Basis for Flooding - 60-Day Status Report (OEDO-15-00479) (CAC No. MF6460; EPID L-2015-CRS-0002). 02/08/2019
209. Pilgrim, Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications. 02/08/2019