Specific Communications with Spring 2002 Outage Plants
This page presents NRC communications with Nuclear Power Plants having outages during the spring 2002 season. NRC staff held telephone conversations in Pre-Inspection Communications with managers of all plants conducting refueling outages this Spring to ensure they inspect reactor vessel heads for signs of degradation as required in Bulletin 2002-01. Results of those inspections were discussed with NRC staff in Post-Inspection Communications. Links to communications in the table will be activated as quickly as is possible.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Plant | Pre-Inspection Communications | Post-Inspection Communications | Other Communications |
---|---|---|---|
Arkansas 2 | 04/17/2002 – 04/25/2002 | ||
Byron 1 | 03/22/2002 – 03 /25/2002 | ||
Calvert Cliffs 1 | 03/26/2002 | ||
Comanche Peak | 04/04/2002 | 04/10/2002 | |
Cook | 03/28/2002 and 03/29/2002 | ||
Diablo Canyon 1 | 05/21/2002 | ||
Ginna | 03/22/2002 | 03/29/2002 | |
McGuire 2 | 03/21/2002 | ||
Millstone 2 | 03/13/2002 | 03/21/2002 | |
Oconee 1 | 03/26/2002 | 04/03/2002 | |
Palo Verde 2 | 03/20/2002 and 03/28/2002 | 04/02/2002 and 04/04/2002 | |
Surry 2 | 03/28/2002 | 04/04/2002 | |
Turkey Point 4 | 03/22/2002 | 03/29/2002 | |
Vogtle 1 | 03/25/2002 | ||
Waterford 3 | 03/21/2002 | ||
Watts Bar | 03/28/2002 | ||
Wolf Creek | 03/26/2002 | 04/05/2002 and 04/23/2002 |