Perry Nuclear Power Plant, Unit 1 Approved Power Uprate Application Information
The following table refers to NRC-approved power uprate applications. The table shows the ADAMS accession number for (1) each plant's power uprate application, (2) any supplement to the application, and (3) the license amendment approving the application and allowing the licensee to increase power. These documents illustrate the information that the NRC staff requires in order to complete a power uprate review.
NRC encourages licensees to review the documents listed in the table before preparing a power uprate application. Addressing the information contained in these documents below may improve the quality of the application, thereby reducing the number of RAIs, and expedite the staff's review.
On this page:
Perry Nuclear Power Plant, Unit 1
Facility Operating License No. NPF-58 (Docket No. 50-440)
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Application Information
Date |
Description |
ADAMS
Accession No. |
09/09/1999 |
Perry Nuclear Power Plant, Unit 1, Application for SPU |
ML20138D182 |

Supplement Information
Date |
Description |
ADAMS
Accession No. |
03/01/2000 |
Response to Request for Additional Information Related to a License Amendment Requesting a Power Uprate (TAC No. MA6459) |
ML003690096 |
03/13/2000 |
Response to Request for Additional Information Related to a License Amendment Requesting a Power Uprate |
ML003694321 |
05/11/2000 |
Letter providing plans for implementation of power uprate LAR as requested by NRC during 05/08/00 teleconference |
ML003715086 |

Amendment Information
Date |
Description |
ADAMS
Accession No. |
06/01/2000 |
Perry Nuclear Power Plant, Unit 1, License Amendment for Power Rate |
ML003724441 |