The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

James A. FitzPatrick Nuclear Power Plant Approved Power Uprate Application Information

The following table refers to NRC-approved power uprate applications. The table shows the ADAMS accession number for (1) each plant's power uprate application, (2) any supplement to the application, and (3) the license amendment approving the application and allowing the licensee to increase power. These documents illustrate the information that the NRC staff requires in order to complete a power uprate review.

NRC encourages licensees to review the documents listed in the table before preparing a power uprate application. Addressing the information contained in these documents below may improve the quality of the application, thereby reducing the number of RAIs, and expedite the staff's review.

On this page:

James A. FitzPatrick Nuclear Power Plant
Facility Operating License No. DPR-59 (Docket No. 50-333)

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Application Information

Date Description ADAMS
Accession No.
06/12/1992 Application to Amend License DPR-59 to Increase Authorized Maximum Power Level by Approximately 4.1 Percent to 2,536 MWt ML20154D245

To top of page

Supplement Information

Date Description ADAMS
Accession No.
09/17/1992 Response to Request for Additional Information Regarding Proposed Technical Specification Change for Power Uprate ML20106A556
03/17/1993 Response to NRC Second Request for Additional Information – Power Uprate Submittal (TAC No. M83182) ML20035A710
08/17/1993 Proposed Changes to the Technical Specifications Regarding Power Uprate (JPTS-91-025), Revision 2 to NEDC-31317P ML20056E316
08/18/1993 Proposed Changes to the Technical Specifications Regarding Power Uprate (JPTS-91-025), Revision 1 to Safety Analysis NEDC-32016P ML20056F613
12/29/1993 Response to NRC Request for Additional Information Power Uprate Submittal (TAC No. M83182) ML20059E661
06/29/1995 Issuance of Changes to the Technical Specification Regarding Power Uprate (JPTS-91-025) ML20086C498
08/15/1996 Not Available Not Available
10/03/1996 Supplemental Information Regarding Updated Page Changes for Proposed Change to the Technical Specifications Regarding Power Uprate (JPTS-91-025) ML20128H533
10/23/1996 Submittal of Updated Pages Regarding Proposed Changes to the Technical Specifications Contained in the Referenced Letters ML20129F988
11/14/1996 Response to Request for Additional Information Regarding Power Uprate ML20134K943
11/20/1996 Supplemental Information Regarding Updated Page Changes for Proposed Change to the Technical Specifications Regarding Power Uprate (JPTS-91-025) ML20134M167
11/20/1996 Incorrect Attachments Included with Response to Request for Additional Information on Power Uprate ML20134L913
11/27/1996 Response to Request for Additional Information Regarding Power Uprate ML20134Q291

To top of page

Amendment Information

Date Description ADAMS
Accession No.
12/06/1996 Amendment 239 to Operating License DPR-59 to Increase Maximum Power Level of Plant from 2,436 MWth to 2,536 MWth ML20132C337