Application Review Schedule

Application Review Schedule for the Combined License Application for Turkey Point, Units 6 and 7

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Florida Power and Light Company (FPL) submitted to obtain a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) pressurized-water reactors (PWRs) designated as Turkey Point, Units 6 and 7.

Key MilestonesCompletion Date
Actual - A
Target - T
Application Tendered06/30/09 - A
Acceptance Review
Acceptance Review Start
06/30/09 - A
Docketing Decision Letter Issued/Acceptance Review Complete
09/04/09 - A
Review Schedule Established/Schedule Letter Issued to Applicant
10/27/15 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs
06/16/15 - A
Phase B - Advance Final safety evaluation report (SER) without Open Items
07/14/16 - A
Phase C - ACRS Review of Advance Final SER
08/19/16 - A
Phase D - Final SER
11/10/16 - A
Environmental Review
Phase 1 - Environmental impact statement (EIS) scoping summary report issued
12/10 - A
Phase 2 - Draft EIS issued to EPA
02/27/15 - A
Phase 3 - Final EIS issued to EPA
10/28/16 - A
Supplement to Final EIS issued
12/02/16 - A
Hearing
Commission or ASLB hold mandatory hearing
Schedule Under
Review
License
Commission decision on issuance of COL application
 

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.