2009 - Calvert Cliffs, Unit 3 Application
On this page:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Applicant Documents
The following table provides access to the COL Application and other documents that Calvert Cliffs 3 Nuclear Project, LLC and UniStar Nuclear Operating Services, LLC submitted in 2009 for Calvert Cliffs, Unit 3.
Date |
Description |
12/31/09 |
Summary Letter of the Differences between the Phase I and Phase II Non Tidal and Stream Mitigation Plans |
12/09/09 |
Letter transmitting Low Level Waste Disposal Options |
12/04/09 |
Letter transmitting Construction Acreage and Timeframe |
10/29/09 |
Response to Questions on Revision 5 of the COL application on impervious surfaces and construction acreage |
09/22/09 |
Revised Work Description Letter to US Army Corps |
09/21/09 |
Electronic Reference Portal Response Letter |
09/10/09 |
TRAGIS and RADTRAN Information Need Response |
08/25/09 |
Revision 1 of New Alternative Site Information for Calvert Cliffs |
07/01/09 |
U.S. EPR RCOLA/SCOLA Standardization Matrix |
06/30/09 |
Transmittal Letter Revision 5 of the COL Application for Calvert Cliffs |
06/01/09 |
Alternate Site Evaluation Report Submittal Schedule |
06/01/09 |
Transmittal of Supplemental Information in Support of Site Geology Audit, Calvert Cliffs Nuclear Power Plant, Unit 3 |
05/22/09 |
Biological Evaluation for Tiger Beetles |
05/15/09 |
Transmittal of Revised Schedule for Seismic Analysis and Geotechnical Deliverables |
05/13/09 |
Federal Fish and Wildlife Permit for Eagle Scientific Collecting |
04/14/09 |
Restrictions of Construction/Refurbishment of the Barge Slip/Unloading Facility and Associated Dredging |
03/27/09 |
Notification to NRC of Extension of Security Submittal |
03/27/09 |
Notification to NRC, COLA Revision 5 Scope |
03/16/09 |
Submittal of Post-April 2009 through FY 2011 Combined License Application Revision Schedule |
03/09/09 |
UniStar transmittal letter for Calvert Cliffs Unit 3 COLA, Revision 4
See Application |
02/13/09 |
Response to FEMA Request for Additional Information Regarding Offsite Emergency Planning Activities |
01/14/09 |
Letter from UniStar on Intake Structure Relocation Changes for the Environmental Report |
NRC Documents
The following table provides access to documents and correspondence that the NRC has issued in 2009 in connection with its review of the COL application that Calvert Cliffs 3 Nuclear Project, LLC and UniStar Nuclear Operating Services, LLC submitted for Calvert Cliffs, Unit 3.
Date |
Description |
09/16/09 |
Condition Letter for the Electronic Portal for the Calvert Cliffs COL Review |
08/20/09 |
Issuance of a Revised Environmental Schedule for the Combined License Application Review for the Calvert Cliffs Nuclear Power Plant, Unit 3 |
08/20/09 |
Safety Project manager Change for the Combined License Safety Review for Calvert Cliffs Nuclear Power Plant Unit 3 |
07/14/09 |
Review Schedule for Calvert Cliffs Unit 3 Combined License Application (Safety Review) |
03/23/09 |
Environmental Project Manager Change for the Combined License Environmental Review for Calvert Cliffs Nuclear Power Plant Unit 3 |
01/16/09 |
Change in Schedule of the Calvert Cliffs Combined License Application Environmental Review |
Page Last Reviewed/Updated Sunday, September 18, 2022