Skip to main content

Early Site Permit - North Anna Site

Dominion Nuclear North Anna, LLC submitted its application for an early site permit (ESP) for the North Anna site on September 25, 2003. Revision 9 to the ESP application was the final revision of the application submitted on September 12, 2006. The U.S. Nuclear Regulatory Commission (NRC) approved the application and issued the North Anna ESP on November 27, 2007. 

On July 14, 2026, Virginia Electric and Power Company (doing business as Dominion Energy Virginia) submitted an application to renew the ESP, along with an exemption and notification of the deferral of the North Anna Unit 3 combined license.

Early Site Permit Renewal Application Information

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

To top of page

Early Site Permit Application Information

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

To top of page

Early Site Permit Review Schedule

Milestone Completion Date
Actual - A
Target - T
Receive early site permit application 09/25/03 - A
Press Release announcing receipt and availability 10/09/03 - A
FRN published for receipt and availability 10/16/03 - A
FRN published announcing acceptance 10/30/03 - A
1st inspection complete 11/21/03 - A
FRN published for Notice of Intent (environmental scoping process) 11/24/03 - A
FRN published for mandatory hearing 12/02/03 - A
Environmental scoping meeting 12/08/03 - A
Deadline for filing petitions for intervention 01/02/04 - A
Scoping period ends 01/09/04 - A
Environmental requests for additional information (RAIs) issued to applicant 03/12/04 - A
Deadline for submitting contentions 05/03/04 - A
Safety and emergency planning (EP) RAIs issued to the applicant 06/03/04 - A
Applicant submits response to environmental RAIs 08/12/04 - A
Applicant submits responses to safety and EP RAIs 08/19/04 - A
Draft environmental impact statement (EIS) to EPA, Issue Notice of Availability 12/10/04 - A*
Draft safety evaluation report (SER) issued 12/20/04 - A
2nd inspection complete 02/08/05 - A
Public meeting to discuss draft EIS 02/17/05 - A
End of draft EIS comment period 03/01/05 - A
ACRS subcommittee meeting on draft SER 03/02/05 - A
ACRS full committee meeting on draft SER 03/03/05 - A
ACRS interim letter to Commission 03/11/05 - A
Applicant submits responses to SER open items 03/31/05 - A
Optional final inspection complete N/A 1
Final SER issued 06/16/05 - A*
ACRS subcommittee meeting on final SER N/A 1
ACRS full committee meeting on final SER 07/06/05 - A*
Regional Administrator's Letter N/A 1
ACRS letter to Commission 07/18/05 - A
Final SER issued as NUREG 09/30/05 - A*
Final EIS issued to EPA/Issue Notice of Availability 12/14/06 - A
Atomic Safety and Licensing Board (ASLB) initial decision 06/29/07 - A
Commission decision 11/20/07 - A

1 Optional final inspection and ACRS subcommittee review of final SER not needed.

To top of page

North Anna Early Site Permit

On November 27, 2007, the NRC issued the North Anna ESP for a site located approximately 40 miles north-northwest of Richmond, Virginia.

On January 30, 2013, the NRC issued a revised ESP Amendment 3.

To top of page

Early Site Permit Safety Evaluation Report

NUREG-1835, containing the safety evaluation report for the North Anna ESP Application, was issued in September 2005, followed by Supplement 1 to NUREG-1835 in November 2006.

To top of page

Early Site Permit Final Environmental Impact Statement

See NUREG-1811, "Final Environmental Impact Statement for an Early Site Permit (ESP) at the North Anna ESP Site."

To top of page

Contacts

For additional information regarding the North Anna ESP, please Contact a Public Affairs Officer.

To top of page

Page Last Reviewed/Updated Thursday, August 27, 2026

Page Last Reviewed/Updated Thursday, August 27, 2026