The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Requests for Additional Information Regarding the Combined License Application for Grand Gulf, Unit 3

This page provides access to requests for additional information (RAIs) that the U.S. Nuclear Regulatory Commission (NRC) has issued in connection with its review of the application that Entergy Operations, Inc. (EOI) submitted to obtain a combined license (COL) for Grand Gulf, Unit 3. The purpose of these RAIs is to obtain all of the information that the NRC staff deems necessary to resolve any safety or environmental issues that are not adequately addressed in the application. Consequently, the applicant's responses to RAIs become supplements to the initial application. For details, see the following categories of RAIs on this page:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Safety RAIs

The following table provides access to safety RAIs and the applicant's subsequent responses.

RAI Date RAI Letter No. and Subject Applicant Response
09/05/08 RAI Letter No. 01 SRP Section 191 and 19.2 10/01/08
09/12/08 RAI Letter No. 02 SRP Section 2.31, 2.3.4 and 2.3.5 10/13/08
09/12/08 RAI Letter No. 03 SRP Section 12.03-12.04 10/09/08
09/16/08 RAI Letter No. 04 SRP Section 13.01.02-13.01.03 10/15/08
09/18/08 RAI Letter No. 05 SRP Section 17.5 10/20/08
09/18/08 RAI Letter No. 06 SRP Section 10.04.05 10/14/08
09/29/08 RAI Letter No. 07 SRP Section 09.05.04 10/23/08
10/06/08 RAI Letter No. 08 SRP Section 11.2, 11.3, 11.4 and 11.5 11/05/08
10/06/08 RAI Letter No. 09 SRP Section 12.02 11/05/08
10/06/08 RAI Letter No. 10 SRP Section 02.02.03 12/03/08
10/06/08 RAI Letter No. 11 SRP Section 01.9 10/23/08
10/07/08 RAI Letter No. 12 SRP Section 8.2 and 8.3 11/05/08
10/15/08 RAI Letter No. 13 SRP Section 14.2 11/05/08
10/24/08 RAI Letter No. 14 SRP Section 09.02.01 11/24/08
10/22/08 RAI Letter No. 15 Part 01 11/19/08
10/22/08 RAI Letter No. 16 SRP Section 14.2 11/05/08
10/27/08 RAI Letter No. 17 SRP Section 3.71 11/18/08
10/30/08 RAI Letter No. 18 SRP Section 01 11/24/08
10/30/08 RAI Letter No. 19 SRP Section 13.03 12/01/08
11/04/08 RAI Letter No. 20 SRP Section 14.03.10 12/04/08
11/10/08 RAI Letter No. 21 SRP Section 09.05.01 12/03/08
11/24/08 RAI Letter No. 22 SRP Section 9.5.4 12/17/08
11/24/08 RAI Letter No. 23 SRP Section 13.1.1 12/16/08
11/24/08 RAI Letter No. 24 SRP Section 14.2 12/16/08
11/24/08 RAI Letter No. 25 SRP Section 12.03 12/12/08
12/08/08 RAI Letter No. 26 SRP Section 2.5.1-2.5.5 01/07/09
12/08/08 RAI Letter No. 27 SRP Section 2.4.2, 2.4.12 and 2.4.13 01/07/09
12/10/08 RAI Letter No. 28 SRP Section 1.0 12/30/08
12/22/08 RAI Letter No. 29 SRP Section 3.7.2  
12/22/08 RAI Letter No. 30 SRP Section 13.03 01/05/09

To top of page

Environmental RAIs

The following table provides access to environmental RAIs and the applicant's subsequent responses.

RAI Date RAI Letter No. and Subject Applicant Response
09/08/08 Request for Additional Information Regarding the Environmental Review of the Combined License Application for Grand Gulf Nuclear Station, Unit 3 10/06/08