2023 Inspection Reports

The purpose of inspection reports is to document the inspection scope, observation, and findings of inspections conducted by the NRC. The NRC performs inspections to oversee the commercial nuclear industry to determine whether its requirements are being met by licensees and their contractors. The NRC performs inspections to verify the quality and suitability of vendor products, licensee-vendor interface, and review of equipment problems found during operation and their corrective action.

For inspections and related vendor inspections conducted by Region II for the Mixed Oxide Fuel Fabrication Facility, please reference the Meetings About Mixed Oxide Fuel page.

Prior to December 1999, the NRC issued NUREG-0040, "Licensee Contractor and Vendor Inspection Status Report," (The White Book) to document the results of inspections performed by the NRC's Quality Assurance, Vendor Inspection, Maintenance and Allegations Branch that were distributed to the inspected organizations. As of November 1999, these inspection reports are available electronically in the NRC's record retrieval system, ADAMS. The following inspections have been conducted since May 2005:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Inspection
Report Date
Description
12/05/2023

Henry Pratt Company, Kimball, TN, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the fabrication, testing, design control, qualification, and commercial grade dedication for safety ASME code and non-code class II and III valves, valve parts, and appurtenances for NRC’s regulated facilities.

12/03/2023

Thermo Fisher Scientific, Oakwood Village, OH, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the manufacturing of replacement parts and calibration and repair services for NRC’s regulated facilities.

11/03/2023

Namco Controls, Elizabethtown, NC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the fabrication, testing, design control, qualification, and commercial grade dedication for safety-related switches, and electronic and electro mechanical devices for NRC’s regulated facilities.

10/27/2023

Westinghouse Electric Company (WEC), Cranberry Township, PA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the design and engineering services of safety-related structures, systems and components for NRC’s regulated facilities.

10/02/2023

Velan Inc., Montreal, Canada, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to design, manufacturing and refurbishment of safety-related components for NRC’s regulated facilities.

09/07/2023

ANSYS, Canonsburg, PA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the design and development of software for NRC’s regulated facilities.

08/31/2023

Fluor, Greenville, SC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the engineering, procurement and construction services of safety-related structures, systems and components for NRC’s regulated facilities.

07/07/2023

Prysmian Group, Willimantic, CT, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the manufacturing of transmission cables for NRC’s regulated facilities.

06/21/2023

Valcor Engineering Corporation, Springfield, NJ, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the manufacturing of valves for NRC’s regulated facilities.

06/09/2023

Mistras Services, Trainer, PA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to nondestructive examinations of safety-related structures, systems, and components at nuclear power plants.

06/02/2023

Nutherm International, Inc, Mount Vernon, IL, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the qualification and dedication activities associated with class 1E components supplied to operating nuclear power plants.

05/09/2023

Global Nuclear Fuel – Americas, LLC’s (GNF-A), Wilmington, NC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to the design and manufacturing of nuclear fuel and core support components for NRC’s regulated facilities.

05/04/2023

Ultra Energy, Round Rock, TX, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the design and manufacturing of sensors and instrumentation components for NRC’s regulated facilities.

04/13/2023

MPR Associates, Inc., Alexandria, VA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to engineering design services, software development, commercial-grade dedication services, and Basler excitation systems and associated components being supplied to NRC’s regulated facilities.

04/03/2023

Curtiss-Wright, QualTech NP, Cincinnati, Ohio, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at your facility related to commercial-grade dedication, seismic qualification and containment products and spare parts supplied to NRC’s regulated facilities.

03/21/2023

Fluke Biomedical Company, Solon, OH, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to as they pertain to activities conducted at their facility related to the manufacturing of radiation monitoring equipment, replacement parts and calibration and repair services for NRC’s regulated facilities.

03/08/2023

Curtiss-Wright – EMS – Target Rock, Farmingdale, NY, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to activities associated with qualification, fabrication, manufacturing, and testing activities for safety-related valves, components, and other items and services supplied to nuclear power plants.