Discuss the content of the Sequoyah Nuclear Plant, Units 1 and 2, draft supplemental environmental impact statement (DSEIS) for license renewal and accept comment from the public.
Meeting of the ACRS Subcommittee on Reliability & PRA - The Subcommittee will review and discuss the progress of the National Fire Protection Association (NFPA) 805 transition for non-pilot plants.
The purpose of this meeting is to discuss phase 2 decision criteria for the flooding hazard reevaluations of Recommendation 2.1, and the relationship to mitigating strategies related to the Near-Term Task Force (NTTF) Recommendations for Enhancing Reactor Safety in the 21st…
To discuss the resolution of open items in support of the safety review of the Fermi 3, Combined License Application (COLA). Other topics related to the Fermi 3 COLA may also be discussed.
To discuss resolution of issues to support the safety review of licensing actions for Southern Nuclear Operating Company's (SNC) Vogtle Electric Generating Plant, Units 3 and 4 and South Carolina Electric and Gas's (SCE&G) V.C. Summer Nuclear Station, Units 2 and 3…
The purpose of this meeting is to clarify information provided in support of the Perry Nuclear Power Plant alternative source term licensing action request.
The purpose of this teleconference is for the NRC staff and the combined license applicants of the AP1000 design center to discuss, ask questions, or note concerns regarding relevant licensing and technical issues.
Joint Meeting of the ACRS Subcommittees on Plant License Renewal and Structural Analysis - The Subcommittee will discuss the effects of concrete degradation on nuclear plant related infrastructure.
Predecisional Enforcement Conference to discuss the apparent violation concerning the failure to comply with the terms of the Confirmatory Order, dated September 3, 2013. This conference is being held to obtain information to assist the NRC in making an enforcement decision.…
To discuss issues related to certain public comments on the “Proposed Procedures for Conducting Hearings on Whether Acceptance Criteria in Combined Licenses Are Met,” which was published in the Federal Register on April 18, 2014. Comments on the proposed procedures were due on…
AREVA NP, Inc., will discuss with NRC staff the path toward resolving technical issues currently being evaluated by the NRC staff, and emergent issues related to Final Safety Analysis Report (FSAR) changes.
The purpose of this meeting is to discuss the status of several initiatives involving the fuel cycle industry. The topics will include the Cumulative Effects of Regulation, revision to NUREG-1520 "Standard Review Plan for the Review of a License Application for a Fuel Cycle…
The purpose of this meeting is to continue discussions between the NRC and Nuclear
Energy Institute (NEI) Steering Committees on activities related to lessons-learned from
the accident at the Fukushima Dai-ichi nuclear power plant in Japan.
To discuss the resolution of open items and responses to outstanding requests for additional information in support of the safety review of the South Texas Project (STP), Units 3 and 4, Combined License Application (COLA). Other topics related to the STP, Units 3 and 4, COLA may…