Application Review Schedule for SHINE Medical Technologies, LLC Operating License
SHINE Medical Technologies, LLC submitted an operating license application for a medical radioisotope facility. The following table summarizes the U.S. Nuclear Regulatory Commission's key milestones for reviewing this application.
| Key Milestones | Completion Date Actual—A Target—T |
|---|---|
| Application Tendered | |
Receipt of Operating License Application |
08/2019—A |
| Acceptance Review | |
Acceptance of Application for Docketing |
10/2019—A |
| Federal Register Notice | |
Issuance of Notice of Opportunity to Request Hearing |
01/2020—A |
Closing of Opportunity to Request Hearing |
03/2020—A |
| Environmental Review Schedule | |
Environmental Scoping Meeting |
12/2019—A |
NUREG Publication of Supplemental Draft Environmental Impact Statement |
06/2022—A |
NUREG Publication of Supplement Final Environmental Impact Statement |
02/2023—A |
| Safety Review Schedule | |
Draft Safety Evaluation Report |
11/2022—A |
Final Safety Evaluation Report |
02/2023—A |
| Advisory Committee on Reactor Safeguards (ACRS) | |
ACRS Subcommittee Meeting |
03/2022—A |
ACRS Subcommittee Meeting |
05/2022—A |
ACRS Subcommittee Meeting |
07/2022—A |
ACRS Subcommittee Meeting |
09/2022—A |
ACRS Full Committee Meeting |
11/2022—A |
| Construction Inspection | |
Notification of Substantial Completion of Construction |
TBD |
| Hearing | |
Contested Hearing on Issuance of Operating License |
No Petitions for Hearing Received by Deadline |
| License | |
Determination on Whether to Issue Operating License |
TBD |
First Production |
2024 |
Page Last Reviewed/Updated Thursday, August 27, 2026