Historical Timeline
The NRC began its first reassessment of PWR sump and BWR suction strainer performance in 1979. The first reassessment (including all technical and regulatory actions) was completed in 1985.
In 1992, the NRC started a second reassessment of BWR suction strainer performance and completed the reassessment (including all technical and regulatory actions) in 2000.
In 1996, the NRC started a second reassessment of PWR sump performance and that reassessment is ongoing.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
See the following, for a graphical presentation of the information provided in the table below.
- Historical Timeline of NRC Regulatory Actions
- Historical Timeline of Events and NRC Technical Reports
Years | Regulatory Activity | Event | Technical Activity |
---|---|---|---|
1970-1975 | Regulatory Guide 1.82 | ||
1976-1980 | |||
1981-1985 | Regulatory Guide 1.82, Revision 1 | ||
1986-1990 | Information Notice 88-28 Information Notice 89-77 Information Notice 90-07 |
||
1991-1995 | Information Notice 92-71 Information Notice 92-85 Information Notice 93-34 Information Notice 93-02 Temporary Instruction 2515/125 Information Notice 94-57 Information Notice 95-06 Bulletin 95-02 Information Notice 95-47 |
Barseback, Sweden Perry Limerick |
Head loss tests Debris generation tests |
1996-2000 | Information Notice 96-10 Bulletin 96-03 Regulatory Guide 1.82, Revision 2 Information Notice 96-27 Information Notice 96-55 Information Notice 96-59 Generic Letter 96-03 Generic Letter 97-04 Generic Letter 98-04 Regulatory Guide 1.54, Revision 1 |
LaSalle | Debris transport tests Debris erosion tests |
2001-2003 | Bulletin 2003-01 | ||
2004- | Chemical Effects |
Page Last Reviewed/Updated Wednesday, April 02, 2025