Application Review Schedule for the Early Site Permit Application for Victoria County Station
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Exelon Nuclear Texas Holdings, LLC (Exelon) submitted to obtain an early site permit (ESP) for Victoria County Station.
Key Milestones |
Completion Date
Actual - A
Target - T |
Application Tendered |
03/25/10 - A |
Acceptance Review |
Acceptance Review Start
|
04/01/10 - A |
Docketing Decision Letter Issued/Acceptance Review Complete
|
06/08/10 - A |
Review Schedule Established/Schedule Letter Issued to Applicant
|
08/10 - A |
Review Schedule Established/(Revised)
|
12/01/11 - A |
Safety Review |
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs issued
|
12/12 - T |
Phase B - Advanced safety evaluation report (SER) with no Open Items developed
|
08/13 - T |
Phase C - ACRS meeting on Advanced SER
|
12/13 - T |
Phase D - Final SER issued
|
04/14 - T |
Environmental Review |
Phase 1 - Scoping summary report issued
|
07/11 - A |
Phase 2 - Draft EIS issued to EPA
|
03/13 - T |
Phase 3 - Final EIS issued to EPA
|
03/14 - T |
Hearing |
Commission or ASLB hold mandatory hearing
|
TBD |
License |
Commission decision on issuance of Early Site Permit
|
TBD |