The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Application Review Schedule for the Early Site Permit Application for Victoria County Station

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Exelon Nuclear Texas Holdings, LLC (Exelon) submitted to obtain an early site permit (ESP) for Victoria County Station.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 03/25/10 - A
Acceptance Review
Acceptance Review Start
04/01/10 - A
Docketing Decision Letter Issued/Acceptance Review Complete
06/08/10 - A
Review Schedule Established/Schedule Letter Issued to Applicant
08/10 - A
Review Schedule Established/(Revised)
12/01/11 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs issued
12/12 - T
Phase B - Advanced safety evaluation report (SER) with no Open Items developed
08/13 - T
Phase C - ACRS meeting on Advanced SER
12/13 - T
Phase D - Final SER issued
04/14 - T
Environmental Review
Phase 1 - Scoping summary report issued
07/11 - A
Phase 2 - Draft EIS issued to EPA
03/13 - T
Phase 3 - Final EIS issued to EPA
03/14 - T
Hearing
Commission or ASLB hold mandatory hearing
TBD
License
Commission decision on issuance of Early Site Permit
TBD