Applicant Documents
The following table provides access to the COL Application and other documents that Nine Mile Point Nuclear Project, LLC and UniStar Nuclear Operating Services, LLC submitted in 2009 for Nine Mile Point, Unit 3.
Date |
Description |
12/01/09 |
Letter to the NRC - Subject: UniStar Nuclear Energy, NRC Docket No. 52-038 Nine Mile Point 3 Nuclear Power Plant - COLA Review |
08/17/09 |
Letter to the NRC - Subject: Nine Mile Point Unit 3 Nuclear Power Plant Combined License Application Review Schedule |
03/31/09 |
UniStar Nuclear Energy transmittal letter for Nine Mile Point COLA - Revision 1 (incorporates supplements dated 10/24/08 and 11/18/08)
See Application |
03/16/09 |
Letter to the NRC - Subject: Nine Mile Point, Unit 3 - FY 2011 Revision Schedule to the Combined License Application for NMP3NPP |
03/06/09 |
Letter to the NRC - Subject: Revised Submittal Date for NMP3NPP COLA Revision 1 Including FSAR 2.5 Update |
02/09/09 |
Letter to the NRC - Subject: Nine Mile Point Unit 3 Combined Operating License Application Review Schedule |
NRC Documents
The following table provides access to documents and correspondence that the NRC has issued in 2009 in connection with its review of the COL application that Nine Mile Point Nuclear Project, LLC and UniStar Nuclear Operating Services, LLC submitted for Nine Mile Point, Unit 3.
Date |
Description |
09/28/09 |
Letter to UniStar - Subject: Status of Review Schedule for Nine Mile Point 3 Nuclear Power Plant Combined License Application |
03/23/09 |
Letter to UniStar - Subject: Status of Review Schedule for Nine Mile Point 3 Nuclear Power Plant Combined License Application |
02/11/09 |
Notice of Cancellation of Environmental Scoping and February 25, 2009 Public Scoping Meeting |
01/26/09 |
Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping |