Applicant Documents
The following table provides access to the COL Application and other documents that EOI submitted in 2008 for Grand Gulf, Unit 3.
Date |
Description |
08/29/08 |
Entergy Responses to USNRC COL Information Needs for the Hydrology Safety Audit Items |
08/27/08 |
Entergy USNRC COL Application: Semiannual Departures Report |
07/24/08 |
Entergy Responses to USNRC COL Environmental Site Audit Requests for Electronic Files |
06/30/08 |
Entergy Response to USNRC COL Acceptance Review Questions Regarding Methodology Used to Develop Horizontal and Vertical Site-Specific Hazard Consistent Uniform Hazard Response Spectra |
06/13/08 |
Entergy Response to USNRC COL Acceptance Review Questions Regarding Geologic and Seismic Information |
04/11/08 |
Entergy Response to USNRC COL Acceptance Review Question re: FEMA Acceptance Review of the Offsite Emergency Response Plans for the Grand Gulf Site |
04/09/08 |
Entergy Response to USNRC COLA Acceptance Review Questions re: Geologic and Seismic Information |
02/27/08 |
Entergy transmittal letter for Grand Gulf Unit 3 COLA
See Application |
NRC Documents
The following table provides access to documents and correspondence that the NRC has issued in 2008 in connection with its review of the COL application that EOI submitted for Grand Gulf, Unit 3.
Date |
Description |
11/26/08 |
Environmental Scoping Summary Report |
07/22/08 |
Trip Report - June 16 and 17, 2008, Hydrology-Related Site Visit in Support of Grand Gulf Unit 3 Combined License Application |
06/25/08 |
Federal Register Notice for Hearing and Opportunity to Petition for Leave to Intervene for Grand Gulf Unit 3 COLA and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information and Safeguards Information for Contention Preparation |
05/30/08 |
Notice of Intent To Prepare an Environmental Impact Statement and Conduct Scoping Process |
05/16/08 |
Grand Gulf Nuclear Station Unit 3 Combined License Application Review Schedule |
04/17/08 |
Acceptance for Docketing of the Entergy Application for a Combined License for Grand Gulf Unit 3 |
03/10/08 |
Acknowledgement of Receipt of Application and Federal Register Notice |
02/14/08 |
Acceptance Review Schedule for the Entergy Application for a Combined License for Grand Gulf Unit 3 |
Page Last Reviewed/Updated Sunday, September 18, 2022